DRAIN WORKS PROGRESS: as at 28 May 2013

NEW ROAD MCO1


S.N. 1 2 3 4 5 6 7 ACTIVITY 900 RCU Drain 1200 RCU Drain 1500 RCU Drain 1400 x 1350 RCBC Approach Slab (1400 RCBC) 1400 x 1200 RC SUMP 1500 x 1500 RC SUMP TOTAL QUANTITY 115 115 30 23.2 99.4 1 1 UNIT m m m m m2 nos. nos. WORK DONE LAST MONTH 15 WORK DONE FOR THE CURRENT MONTH 38 TOTAL WORK DONE 53 PERCENTAGE COMPLETED (%) 46.09

6.5625

6.5625

28.29

UPPER CHANGI ROAD MCO2


S.N. 1 2 3 4 5 6 7 8 ACTIVITY 900 RCU Drain 1500 RCU Drain 1200 X 1200 RCBC 1500 x 1000 RCBC 1500 x 2200 RCBC Approach Slab (1500 RCBC) Approach Slab (1200 RCBC) 1500 x 1500 RC SUMP TOTAL QUANTITY 115 115 30 23.2 99.4 1 1 2 UNIT m m m m m m2 m2 nos. WORK DONE LAST MONTH 17 0 WORK DONE FOR THE CURRENT MONTH 28 7.14 TOTAL WORK DONE 45 7.1428 PERCENTAGE COMPLETED (%) 39.13 6.21

Prepared by :

ALFREDO A. CLARO, JR. RTO

Checked by:

Cheng Kim Hua QP(S)