1. EXISTING MASONRY WALL.

C. MAKE VERTICAL CUTS AT EACH SIDE OF

X
3" 2-4" MAX

2. STEEL CHANNEL C6x8.2

OPENINGS.

EACH SIDE OF WALL. D. INSTALL CHANNELS AND BOLTS.

ONE EACH END AND ONE OVER OPENING. E. MAKE HORIZONTAL CUT AT BOTTOM OF 4. OPENING WIDTH "W" - 8" OPENING AND REMOVE MASONRY.

8"

UP TO 6-0" MAXIMUM.

5. NEW OPENING IN EXISTING 2 " MASONRY WALL.

F. THRU BOLTS SHALL BE INSTALLED IN GROUTED CELLS. IF GROUTED

5 4

1
6. SUGGESTED ERECTION

CELLS ARE NOT ENCOUNTERED, BREAK INTO CELL ABOVE AND

SEQUENCE:

3 1

GROUT SOLID FOR 8" HOLE THRU MASONRY AT ALL 4 CORNERS PRIOR TO CUTTING TO ABOVE AND 4" BELOW BOLT LOCATION.

SECTION

AVOID OVERCUTTING.

B. MAKE HORIZONTAL CUT AT TOP OF FUTURE OPENING. DO NOT OVERCUT.

NEW OPENING IN EXISTING NON-BEARING WALL OR BEARING MASONRY WALL WITH LINE OF BEARING AT LEAST A DISTANCE "W" ABOVE OPENING