DAILY WORK STATUS FORMAT

Name Designation Project Details Date : : : : Mr.Pramod Kumar Tiwari Project Engineer Municipal Solid Waste Management Project, Dehradun 26.10.13 210.560 (25.10.13) NA As on date, plant is non-operational NAME OF VEHICLE TOTAL VEHICLE VEHICLE TIPPER 8 HYWA 2518 2 COMPACTOR 2 TATA 407 3 TATA ACE 42 TRACTOR DUMPER PLACER 1 JCB LODER 1 NA As on date, plant is non-operational WORKING 5 1 1 3 29 1 1

Quantity of MSW Collected (Tonnes/day) Quantity of MSW Processed at the waste processing facility (Tonnes/day) No of vehicle to working

Quantity of MSW Landfilled returned from the project facility as Non-conforming waste (Tonnes/day) Details of Wards visit

Visited Dhamawala ward no 23 Raja Road 4 rahdi garbage and Garuv Hotel 3 rahdi garbage lying on ground. Visited Jhanda Mohlla ward No .24 Jhanda Mohlla 6 rehdi garbage lying on ground. Visited Dalanwala West ward no 26 Balbir road 6 rehdi garbage and BJP office 5 rehdi garbage lying on ground. Visited Mata Mandir Road ward no37 Mata Mandir Road 5 rehdi garbage, Ps chowk 4 rehdi garbage, Sarswati Vihar 6 rehdi garbage and Near Sali Pul 8 rehdi garbage lying on ground. Visited Race Course South ward no 38 Police line In/Out 6 rehdi garbage, Bal yogi asram 2 rehdi and Dharampur Bhatta 6 rehdi garbage lying on ground. Officers Colony and Officers Transit Hostel clean. Visited Kargi ward No .42 Kargi 6 rahdi rehdi garbage lying on ground. Visited Patel Nagar East ward no 43 Near Sahara News office 6 rehdi garbage lying on ground. Visited Kanwali gaon ward no 50 Kanwali gaon 6 rahdi garbage lying on ground. Visited Indra Nagar ward no 51 Near Jal Sasthan 6 rahdi garbage lying on ground.
Treaching ground position is not proper all dp and cp over flow and all ward position is not proper due to vehicle breakdown Instruct to DVWM supervisor

Observations of Project Engineer Remarks/ Steps taken to rectify