PEMBINAAN BANGUNAN TAMBAHAN IBU PEJABAT POLIS KONTIJEN (IPK) JOHOR

DETAIL CLAIM COMPARISON NO. 41 vs 42


SUMMARY

BIL

KETERANGAN

M/S

HARGA KONTRAK (RM)

JUMLAH TUNTUTAN LEPAS


%

(RM)

TUNTUTAN TERKINI
%

PRELIMINARIES
BILLS OF QUANTITIES

A1/41

3,100,000.00

64.99%

2,014,796.50

0.41%

PILING
BILLS
WORKS
OF QUANTITIES
(ALL PROVISIONAL)

B1/14

7,678,020.50

78.00%

5,988,489.20

0.00%

KERJA-KERJA
BILLS OF QUANTITIES
BANGUNAN

29,117,569.61

49.80%

14,500,577.62

0.16%

C01

- MENARA PENTADBIRAN 12 TINGKAT

BANGUNAN BEKALAN DAN PERSENJATAAN


KAFETERIA
SETOR PELURU
KUARTERS KELAS D
KUARTERS KELAS E (2 UNIT)

C08 - KUARTERS KELAS F (40 UNIT)


C09 - ANCILLARY BUILDINGS
D

EXTERNAL
BILLS OF
WORKS
QUANTITIES

PRIME
BILLS
COST
OF &
QUANTITIES
PROVISIONAL SUMS

5,185,294.39

12,600.70

(RM)

JUMLAH CERTIFIED LEPAS


%

(RM)

CERTIFIED TERKINI
%

64.99%

2,027,397.20

60.97%

1,890,159.24

0.56%

78.00%

5,988,489.20

78.00%

5,988,489.20

0.00%

46,170.23

49.80%

14,546,747.84

40.64%

11,832,136.67

0.17%

73,004.15

64.61%

3,423,429.66

46.85%

2,429,377.25

64.61%

3,350,425.51

1.41%

5.50%

C08/S/1
C09/S/1

3,092,202.75
668,840.70
434,698.55
295,782.05
378,554.35
5,864,543.00
330,570.29

66.85%
68.35%
90.99%
65.56%
64.23%
68.39%
61.61%

2,067,269.65
457,119.90
395,550.55
193,910.54
243,155.08
4,010,923.08
203,678.25

0.95%
0.64%
0.00%
6.14%
4.04%
-1.13%
0.00%

29,265.18
4,262.45
18,151.23
15,284.45
(65,996.18)
-

66.85%
68.35%
90.99%
65.56%
64.23%
68.39%
61.61%

2,096,534.83
461,382.35
395,550.55
212,061.77
258,439.53
3,944,926.90
203,678.25

62.16%
61.51%
87.72%
61.55%
55.43%
62.97%
58.45%

1,922,034.37
411,375.55
381,310.76
182,063.03
209,826.30
3,692,705.06
193,205.75

3.17%
1.65%
0.00%
9.66%
3.54%
0.80%
0.00%

D-SUM

10,528,938.65

18.70%

1,968,834.59

3.02%

317,593.42

18.70%

2,286,428.01

17.75%

1,868,834.63

1.87%

66,675,014.84

53.09%

35,394,730.47

0.68%

450,335.62

53.76%

35,845,066.09

31,001,517.81

1.12%

36,881,680.00

29.98%

11,058,153.86

3.05%

1,123,196.75

33.03%

12,181,350.61

#VALUE!

11,918,540.89

1.75%

6%

110,740.00
553.93
647.65
926,600.00
4,632.78
5,416.58
1,923,120.00
9,616.20
10,857.00
2,731,530.70
13,312.45
9,668.75
787,949.62
3,939.77
3,765.08
2,638,100.00
11,338.74
16,373.21
1,298,000.00
6,490.74
2,525.02
390,000.00
1,950.00
2,320.10
146,550.00
732.74
1,422.80

258,580.90
3,133.16
1,095.65
850,000.00
4,250.00
6,137.03
-

6%

110,740.00
553.93
647.65
926,600.00
4,632.78
5,416.58
1,923,120.00
9,616.20
10,857.00
2,990,111.60
16,445.61
10,764.40
787,949.62
3,939.77
3,765.08
3,488,100.00
15,588.74
22,510.24
1,298,000.00
6,490.74
2,525.02
390,000.00
1,950.00
2,320.10
146,550.00
732.74
1,422.80

6.18%

110,740.00
553.93
647.65
926,600.00
4,632.78
5,416.58
1,923,120.00
9,616.20
10,857.00
2,731,530.70
13,312.45
9,668.75
787,949.62
3,939.77
3,765.08
3,488,100.00
15,588.74
22,510.24
1,298,000.00
6,490.74
2,525.02
390,000.00
1,950.00
2,320.10
146,550.00
732.74
1,422.80

11,058,153.86

1,123,196.75

C03/S/1
C04/S/1
C05/S/1
C06/S/1
C07/S/1

E/7

1 - Shooting Range Equipment Installation ( RM 3,848,821.00)


A. Kerja Sistem Simulasi Menembak ( RM 1,792,650.00)
- Profit (0.5% x RM 1,792,650.00) = RM 8,963.25
- Attendance
= RM 10,479.74
B. Kerja Sistem Lapang Sasar ( RM 2,056,171.00.00)
- Profit (0.5% x RM 2,056,171.0.00) = RM 10,280.86
- Attendance
= RM 12,020.26
2 - Lift System ( RM 2,480,000.00)
- Profit (0.5% x RM 2,480,000.00) = RM 12,400.00
- Attendance
= RM 14,000.00
3 - Sistem Penyaman Udara ( RM 8,398,800.00)
- Profit (0.5% x RM 8,398,800.00) = RM 41,994.00
- Attendance
= RM 30,500.00
4 - Fire Protection (RM 2,888,056.60)
- Profit (0.5% x RM 2,888,056.60) = RM 14,440.28
- Attendance
= RM 13,800.00
5 - Pemasangan Sistem Elektrik (RM 7,499,966.00)
- Profit (0.5% x RM 7,499,966.00) = RM 37,499.83
- Attendance
= RM 54,150.00
6 - Sistem ICT & Telefon (RM 3,598,777.00)
- Profit (0.5% x RM 3,598,777.00) = RM 17,993.89
- Attendance
= RM 7,000.00
7 - Pemasangan ELV (RM 1,529,680.00)
- Profit (0.5% x RM 1,529,680.00) = RM 7,648.40
- Attendance
= RM 9,100.00
8 - Peralatan dapor (RM 206,000.00)
- Profit (0.5% x RM 206,000.00) = RM 1,030.00
- Attendance
= RM 2,000.00

45%

78%

33%

27%

35%

36%

0%

0%

36,881,680.00
Jumlah Harga

C01/S/1

C02 - CAWANGAN TRAFIK DAN JABATAN SIASATAN C02/S/1


JENAYAH
C03
C04
C05
C06
C07

JUMLAH TUNTUTAN NO 41

(RM)

103,556,694.84

44.86%

46,452,884.33

MATERIALS ON SITE (90%)

3,614,356.26

VARIATION OF PRICE

3,929,049.52

1.52%

1,573,532.36

143,869.50
-

37%

78%

32%

27%

35%

35%

19%

71%

45.06%

77.55%

32.52%

27.28%

35.17%

36.07%

25.50%

71.14%

12,181,350.61
46.38%

48,026,416.70

11,918,540.89
41.45%

42,920,058.70

3,758,225.76

3,614,356.26

3,929,049.52

3,929,049.52

0.59%

PEMBINAAN BANGUNAN TAMBAHAN IBU PEJABAT POLIS KONTIJEN (IPK) JOHOR


DETAIL CLAIM COMPARISON NO. 41 vs 42
SUMMARY

BIL

KETERANGAN

M/S

HARGA KONTRAK (RM)

JUMLAH TUNTUTAN LEPAS


%

TUNTUTAN TERKINI
%

424,872.42

VARIATION WORKS (refer 'Appendix A')


JUMLAH DIBAWA KE PERAKUAN BAYARAN KEMAJUAN NO. 39

(RM)

103,556,694.84

52.55%

54,421,162.53

JUMLAH TUNTUTAN NO 41

(RM)

%
-

1.66%

1,717,401.86

(RM)

JUMLAH CERTIFIED LEPAS


%

424,872.42
54.21%

56,138,564.40

(RM)

CERTIFIED TERKINI
%

424,872.42
49.14%

50,888,336.90

1.10%

AN IBU PEJABAT POLIS KONTIJEN (IPK) JOHOR

M COMPARISON NO. 41 vs 42
SUMMARY
CERTIFIED TERKINI
(RM)

JUMLAH CERTIFIED NO 41
%

11,322.37

(RM)

DIFFERENCE CLAIM 40 VS
41
%
(RM)

AMOUNT HOLD - NCR

OTHER

(RM)

(RM)

61.34%

1,901,481.61

3.65%

78.00%

5,988,489.20

0.00%

24,965.44

40.72%

11,857,102.11

9.08%

2,689,645.73

2,124,053.44

565,592.29

188,306.54

50.48%

2,617,683.79

14.13%

805,745.87

712,010.94

93,734.93

66,362.40
7,609.90
20,490.20
9,146.65
31,486.70
-

64.30%
62.64%
87.72%
68.48%
57.84%
63.50%
58.45%

1,988,396.77
418,985.45
381,310.76
202,553.23
218,972.95
3,724,191.76
193,205.75

2.55%
5.71%
3.27%
-2.92%
6.39%
4.89%
3.16%

108,138.06
42,396.90
14,239.80
9,508.54
39,466.57
220,735.14
10,472.50

54,328.72
23,098.10
10,985.00
2,059.17
11,490.00
141,753.31

53,809.34
19,298.80
3,254.80
7,449.37
27,976.57
78,981.83
10,472.50

42,826.00

18.16%

1,911,660.63

0.54%

374,767.39

402,516.20

31,404,034.01

212,853.85

32.89%

44,400.00
222.00
259.56
144,000.00
720.00
522.93
22,400.00
111.96
217.40

6.18%

47.22%

77.55%

34.24%

27.28%

46.51%

36.07%

25.50%

82.01%

212,853.85
615,370.05

12,131,394.74

0.00%

110,740.00 0.00%
553.93
647.65
971,000.00 -10.18%
4,854.78
5,676.14
1,923,120.00 0.00%
9,616.20
10,857.00
2,875,530.70 -2.23%
14,032.45
10,191.68
787,949.62 0.00%
3,939.77
3,765.08
3,488,100.00 -11.34%
15,588.74
22,510.24
1,298,000.00 -1.11%
6,490.74
2,525.02
390,000.00 -6.54%
1,950.00
2,320.10
168,950.00 -10.87%
844.70
1,640.20

43,535,428.75

3,614,356.26

3,929,049.52

49,955.86

374,767.39
3,079,778.68
-

(44,400.00)
(222.00)
(259.56)
114,580.90
2,413.16
572.72
(22,400.00)
(111.96)
(217.40)

49,955.86
4.34%

125,915.59

4,441,032.08

12,131,394.74
42.04%

125,915.59

4,490,987.95

143,869.50
-

1,361,253.40
49,955.86

(44,400.00)
(222.00)
(259.56)
114,580.90
2,413.16
572.72
(22,400.00)
(111.96)
(217.40)

3,079,778.68

49,955.86
1,411,209.26

143,869.50
-

AN IBU PEJABAT POLIS KONTIJEN (IPK) JOHOR

M COMPARISON NO. 41 vs 42
SUMMARY
CERTIFIED TERKINI
(RM)

JUMLAH CERTIFIED NO 41
%

615,370.05

(RM)

DIFFERENCE CLAIM 40 VS
41
%
(RM)

424,872.42
49.73%

51,503,706.95

8.52%

4,634,857.45

AMOUNT HOLD - NCR

OTHER

(RM)

(RM)
-

3,079,778.68

1,555,078.76

PEMBINAAN BANGUNAN TAMBAHAN IPK JOHOR


n/a

not applicable

BILL NO. C01 - MENARA PENTADBIRAN

SUMMARY
BILL NO.

DESCRIPTION

FROM PAGE

HARGA
KONTRAK (RM)

WORKDONE
AMOUNT (RM)

VERIFIED

C01-1

WORK BELOW LOWEST FLOOR FINISH

C01/1/9

2,884,055.29

2,530,739.34

2,530,739.35

C01-2

REINFORCED CONCRETE FRAME

C01/2/4

7,711,490.40

6,591,421.20

5,378,297.99

DIFFERENCE

REMARKS

STATUS

METHOD
STATEMENT

PICTURE ON SITE

DRAWING

P.E ENDORSEMENT

n/a

n/a

n/a

(0.00)
1,213,123.21

OMK 47
OMK 48
OMK 50

OMK 53
OMK 55
OMK 57
OMK 58
OMK 59
OMK 60
OMK 61
OMK 62
OMK 72
OMK 73
OMK 77
OMK 83

OMK 91

BANGUNAN TAMBAHAN IPK JOHOR

ISSUE

Besi tetulang terdedah pada struktur konkrit dinding Blok A aras 1 kawasan Kerja pembaikan di tapak masih
lapang sasar.
belum dilakukan
Sagging of Ramp "perlengkungan ramp" di garisan grid 8a - 8 / B - C (TLK 2 - Kerja pembaikan di tapak masih
2A)
belum dilakukan
Tiang 'in situ" CIS mangalami pembentukan struktur yang teruk dan
honeycomb di aras tempat letak kereta 3A
Rasuk konkrit in - situ berada di dalam keadaan melengkung di Blok A

Kerja pembaikan di tapak telah


siap.Dalam proses penutupan NCR
,hantar ke OMK

Kerja pembaikan di tapak masih


belum dilakukan
Besi tetulang rasuk pasang siap (IBS) berada didalam keadaan bengkok di
Paperwork siap
Blok A
Kerja memecahkan parapet wall untuk ramp tempat letak kereta blok A
Dalam proses penutupan NCR ke
sehingga menampakkan besi tetulang
OMK
Melaksanakan keraj konkrit struktur tiang dan ramp parapet waall tanpa
surat sokongan dari
memaklumkan kepada pihak perunding sivil dan struktur
Permukaan struktur dinding CIS tidak rata dan honeycomb struktur rasuk
CIS dan papak CIS di Lapang Sasar
Pembentukan muka struktur 'nip' yang teruk pada tiang 'in situ'
Kecacatan jenis honeycomb pada struktur ramp parapet wall dan rasuk di
Blok A tempat letak kereta
Kerja memecahkan parapet wall sehingga menampakkan besi tetulang di
Dalam Proses Penutupan NCR ke
aras tempat letak kereta 2 ke 2A
OMK
Ketidak seragaman pada permukaan pugak tiang blok A Aras Bawah
Tiada Grout pada ruang antara rasuk pasang siap (IBS) dan 'corbel' pada
tiang 'in-situ' (CIS) di blok A menara pentadbiran
Rasuk konkrit in - situ berada di dalam keadaan melengkung di Blok A
Pemasangan struktur rasuk IBS yang tidak mengikut lukisan pembinaa di
Blok A
Menjalankan kerja pembinaan struktur tiang tanpa membuat penutupan
NCR rujukan Jilid 2/OMK/IPK/NCR/090, tidak mematuhi prosedur kerja

C01/S/5

n/a

n/a

n/a

n/a

n/a

n/a

n/a

n/a

n/a

n/a

n/a


SUMMARY
BILL NO.

C01-3

DESCRIPTION

UPPER FLOOR SLAB

FROM PAGE

C01/3/1

HARGA
KONTRAK (RM)

3,490,528.74

WORKDONE
AMOUNT (RM)

3,173,157.25

VERIFIED

DIFFERENCE

2,495,830.18

677,327.07

REMARKS

OMK 90

OMK 97

OMK 99

C01-4

ROOF (INCLUDING ROOF FINISHES)

C01/4/5

1,615,418.44

23,878.30

23,878.30

C01-5

STAIRCASE

C01/5/4

493,663.97

298,621.13

122,937.38

OMK 80
MNA 13
EXTERNAL WALL

C01/6/1

511,288.55

201,552.99

175,569.35

Resapan air pada struktur 'hollow core slab' retak pada sambungan struktur
CIS dan 'precast' beam dan pembaiaknnya tanpa 'method statement' di
lokasi Blok A (menara pentadbiran) aras 9

Pembinaan Struktur Aras 10

25,983.64
MNA 18
MNA19

Pelarasan formwork rate


Keretakan pada tangga pasang siap (IBS) di Blok A.
Saiz dan dimensi tangga pasang siap (IBS) yang telah dipasang berkurangan,
ianya tidak sama sepertimana lukisan pembinaan.
Gagal mematuhi lukisan pembinaan arkitek bagi rekabentuk tangga di
tempat letak kereta bangunan menara pentadbiran
Parapet wall workdone
Gagal mematuhi 'Standard Spesifications for building work 2005' Section 5 Brickwaorks
Gagal melindungi lapisan kalis lembap di permukaan bumbung konkrit
rata di kawasan pencawang MSB Blok Menara

C01-7

INTERNAL WALL AND PARTITION

C01/7/1

1,587,801.08

429,370.77

369,656.95

59,713.82

SPK, Workdone, Work Progress

C01-8

WINDOWS AND VENTS

C01/8/8

1,502,159.01

41,481.07

24,672.07

16,809.00

Lintol - Paid Up To 65%

C01-9

DOOR

C01/9/10

824,787.04

48,349.99

33,223.22

15,126.77

C01-10

INTERNAL FLOOR FINISHES

C01/10/5

1,572,851.82

130,212.00

74,940.00

55,272.00

429,509.04

321,356.67

108,152.37

C01-11

INTERNAL WALL FINISHES

C01/11/1

1,139,098.32

C01-12

INTERNAL CEILING FINISHES

C01/12/1

549,896.00

C01-13

EXTERNAL FINISHES

C01/13/5

807,896.17

79,177.56

73,910.66

5,266.90

C01-14

COLD WATER SERVICES

C01/14/6

348,278.52

28,677.90

1,006.00

27,671.90

BANGUNAN TAMBAHAN IPK JOHOR

STATUS

METHOD
STATEMENT

PICTURE ON SITE

DRAWING

P.E ENDORSEMENT

"

"

"

"

n/a

"

"

"

"

n/a

175,683.75
OMK 78

C01-6

ISSUE
Kerja konkrit struktur rasuk dan tapak tanpa (1) pengemukaan rekabentuk
perincian sambungan struktur 'in situ' dengan IBS yang telah disahkan oleh
penyemak bebas sepertimana dikehendaki HODT (ii) ulasan disiplin
arkitek, mekanikal & elektrikal, borang pemeriksaan kerja di Blok A
(Menara Pentadbiran) aras 9

OMK 93

Pembinaan Lintol dan stiffener tidak sebagaimana gred konkrit 35N/mm2


dan 20N/mm2 masing masing dan juga lukisan pembinaan berlokasi di Blok
A menara pentadbiran aras tempat letak kereta 4A, Aras 2 dan 4 ,
kontraktor gagal mematuhi kontrak

OMK 93

Lintol - Paid Up To 65%


Pembinaan Lintol dan stiffener tidak sebagaimana gred konkrit 35N/mm2
dan 20N/mm2 masing masing dan juga lukisan pembinaan berlokasi di Blok
A menara pentadbiran aras tempat letak kereta 4A, Aras 2 dan 4 ,
kontraktor gagal mematuhi kontrak
BQ - Pelarasan floor hardener.qty exceed bq
SPK Form Issue and percentage workdone.

Percentage Workdone
M&E Measurement

C01/S/6


SUMMARY
BILL NO.

DESCRIPTION

FROM PAGE

HARGA
KONTRAK (RM)

DIFFERENCE

SOIL, WASTE AND VENT PIPE

C01/15/4

C01-16

SANITARY FITTINGS AND ACCESSORIES

C01/16/6

381,249.80

C01-17

BUILT-IN FURNITURE

C01/17/1

1,382,329.62

C01-18

SUNDRIES

C01/18/13

2,167,299.84

492,472.20

192,357.00

300,115.20

29,117,569.61

14,546,747.84

11,857,102.11

2,689,645.73

BANGUNAN TAMBAHAN IPK JOHOR

48,127.10

VERIFIED

C01-15

TOTAL FOR BILL C01 - MENARA PENTADBIRAN


CARRIED TO RINGKASAN TENDER

147,477.00

WORKDONE
AMOUNT (RM)

38,727.00

9,400.10

REMARKS

ISSUE
M&E Measurement

Encik Naza to update.


Lokap
Material approved
Mock up pending inspection
Pangkin pending (cost)
Toilet stainless steel
Electrical and CCTV
Flush valveand tap
Toilet bowl

C01/S/7

STATUS

METHOD
STATEMENT

PICTURE ON SITE

DRAWING

P.E ENDORSEMENT

BANGUNAN TAMBAHAN IPK JOHOR


BILL NO. C02 - CAWANGAN TRAFIK & JABATAN SIASATAN JENAYAH
SUMMARY
BILL NO.

DESCRIPTION

FROM PAGE

HARGA KONTRAK
(RM)

WORKDONE
AMOUNT (RM)

VERIFIED

DIFFERENCE

REMARKS

C02/1

WORK BELOW LOWEST FLOOR FINISH

C02/1/6

936,225.00

771,599.95

714,523.59

57,076.36

C02/2

REINFORCED CONCRETE FRAME

C02/2/4

704,439.59

704,439.59

683,714.12

20,725.47

NCR OMK 66

C02/3

UPPER FLOOR SLAB

C02/3/1

266,112.55

266,112.55

263,099.98

3,012.57

NCR OMK 68

ISSUE
Brick Sump, Retaining Wall Qty Workdone
Honeycomb dan permukaan struktur yang teruk pada
beberapa struktur rasuk dan tiang 'in situ' di Blok B
Kebanyakan kedudukan steel column bersaiz UB
305x127x8mm tidak berada di dalam lingkungan lebar
rasuk IBS di Blok B
Kualiti Lapisan Cat Anti Oksida yang diragui di
permukaan "I Beam Rafter" / Kekuda (Kerangka
Bumbung) di Blok "B'
Kebanyakan kedudukan steel column bersaiz UB
305x127x8mm tidak berada di dalam lingkungan lebar
rasuk IBS di Blok B
Kualiti Lapisan Cat Anti Oksida yang diragui di
permukaan "I Beam Rafter" / Kekuda (Kerangka
Bumbung) di Blok "B'

NCR MNA 9

C02/4

ROOF (INCLUDING ROOF FINISHES)

C02/4/4

1,189,171.00

690,740.80

4,967.25

685,773.55

C02/5

STAIRCASE

C02/5/3

79,244.75

52,542.75

39,880.75

12,662.00

C02/6

EXTERNAL WALL

C02/6/1

35,705.00

34,633.85

32,134.50

2,499.35 OMK MNA 16

C02/7

INTERNAL WALL AND PARTITION

C02/7/1

184,686.00

73,463.94

69,943.20

3,520.74

SPK, Workdone, Work Progress

C02/8

WINDOWS AND VENTS

C02/8/4

338,060.00

38,899.00

38,682.00

217.00

SPK, Workdone, Work Progress

C02/9

DOOR

C02/9/6

121,241.00

37,933.30

37,215.00

718.30

SPK, Workdone, Work Progress

C02/10

INTERNAL FLOOR FINISHES

C02/10/4

452,439.00

375,936.88

369,792.20

6,144.68

C02/11

INTERNAL WALL FINISHES

C02/11/1

118,915.00

99,726.40

88,466.50

11,259.90

C02/12

INTERNAL CEILING FINISHES

C02/12/1

197,055.00

1,474.20

1,474.20

NCR OMK 68

NCR MNA 9

Memotong permukaan dinding bata yang telah dilepa di


blok Trafik dan Siasatan Jenayah (Blok B)

To get 90%
SPK, Workdone, Work Progress

C02/13

EXTERNAL FINISHES

C02/13/3

61,774.50

23,441.25

22,207.50

1,233.75

SPK, Workdone, Work Progress

C02/14

COLD WATER SERVICES

C02/14/5

63,632.00

3,841.20

1,075.00

2,766.20

M&E Measurement

C02/15

SOIL, WASTE AND VENT PIPE

C02/15/4

34,438.00

8,884.00

10,748.00

(1,864.00)

M&E Measurement

C02/16

SANITARY FITTINGS AND ACCESSORIES

C02/16/5

40,454.00

C02/17

BUILT-IN FURNITURE

C02/17/1

47,500.00

C02/18

SUNDRIES

C02/18/3

314,202.00

239,760.00

239,760.00

5,185,294.39

3,423,429.66

2,617,683.79

TOTAL BILL NO. C02 - CAWANGAN TRAFIK & JABATAN SIASATAN


JENAYAH CARRIED TO RINGKAS TENDER

BANGUNAN TAMBAHAN IPK JOHOR

STATUS

SPK, Workdone, Work Progress

805,745.87

C02/S/8

Pending calculation 2 inch base plate - GPC

Pending calculation 2 inch base plate - GPC

METHOD
STATEMENT

PICTURE ON
SITE

DRAWING

P.E ENDORSEMENT

BANGUNAN TAMBAHAN IPK JOHOR


BILL C03 - BANGUNAN BEKALAN & PERSENJATAAN
SUMMARY
BILL NO.

C03/1

C03/2

DESCRIPTION

WORK BELOW LOWEST FLOOR FINISH

REINFORCED CONCRETE FRAME

FROM PAGE

C03/1/5

C03/2/3

HARGA
KONTRAK (RM)

WORKDONE
AMOUNT (RM)

552,775.35

476,200.35

359,540.95

359,540.95

VERIFIED

DIFFERENCE

476,035.50

353,044.58

REMARKS

164.85

6,496.37

C03/3

UPPER FLOOR SLAB

C03/3/1

126,488.10

126,488.10

119,533.60

6,954.50

ROOF (INCLUDING ROOF FINISHES)

C03/4/4

499,411.50

445,465.80

397,633.45

47,832.35

OMK 51

Menggunakan batu bata bagi menutupi jurang pada


tiang pasang siap (IBS) pada aras tangki air di Bangunan
Bekalan dan Persenjataan
Memasang rasuk pasang siap (IBS) dimana besi
tetulang rasuk tersebut berada di dalam keadaan
bengkok di Bangunan Bekalan dan Persenjataan Aras 1
Scupper drain Workdone
Terdapat kotoran tanah pada 'purlin' yang tidak
dibersihkan yang telah dipasang di Blok C

to be closed, paperwork

NCR OMK 79

Purlin bengkok pada sistem kekuda bumbung di Blok


Cbekalan dan Persenjataan.

to be closed, paperwork

MNA 12
MNA 7

Permukaan kemasan kerangka bumbung (I Beam


Rafter) rosak akibat serpihan simen dan kemasan cat
tidak dilakukan mengikut spesifikasi piawai &
dokumen kontrak di Blok C
Gagal mematuhi lukisan pembinaan arkitek bagi
rekabentuk "GI" Gutter
Permukaan kawasan bumbung (metal decking) rosak
akibat terkena konkrit pada retaining wall di Blok D
(Stor Peluru)

C03/5

STAIRCASE

C03/5/4

26,427.85

24,266.66

17,414.85

6,851.81

Pelarasan formworks

C03/6

WALL

C03/6/1

74,785.50

71,046.23

67,306.95

3,739.28

SPK, Workdone, Work Progress

C03/7

INTERNAL WALL AND PARTITION

C03/7/1

76,719.00

72,883.05

72,883.05

SPK, Workdone, Work Progress

C03/8

WINDOWS AND VENTS

C03/8/6

243,250.00

58,822.05

58,615.05

207.00

SPK, Workdone, Work Progress

C03/9

DOOR

C03/9/8

125,688.00

58,210.90

54,513.79

3,697.11

SPK, Workdone, Work Progress

C03/10

INTERNAL FLOOR FINISHES

C03/10/3

199,422.50

190,638.39

172,965.23

17,673.16

Settled, To get 90%

C03/11

INTERNAL WALL FINISHES

C03/11/1

134,618.50

116,045.30

112,319.68

3,725.63

SPK, Workdone, Work Progress

C03/12

INTERNAL CEILING FINISHES

C03/12/1

90,596.00

22,191.60

17,953.00

4,238.60

C03/13

EXTERNAL FINISHES

C03/13/3

78,950.50

46,335.05

46,288.85

46.20

C03/14

COLD WATER SERVICES

C03/14/5

147,272.00

6,073.80

2,416.00

3,657.80

M&E Measurement

C03/15

SOIL, WASTE AND VENT PIPE

C03/15/4

34,091.00

12,150.60

9,806.00

2,344.60

M&E Measurement

C03/16

SANITARY FITTINGS AND ACCESSORIES

C03/16/5

36,347.00

C03/17

BUILT-IN FURNITURE

C03/17/1

240,576.00

C03/18

SUNDRIES

C03/18/4

45,243.00

10,176.00

9,667.20

508.80

3,092,202.75

2,096,534.83

1,988,396.77

108,138.06

TOTAL FOR BILL C03 - BANGUNAN BEKALAN &


PERSENJATAAN
CARRIED TO RINGKASAN TENDER

BANGUNAN TAMBAHAN IPK JOHOR

Dalam Proses Penutupan NCR ke OMK

NCR OMK 65

MNA 8

STATUS

SPK, Workdone, Work Progress

OMK 52

C03/4

ISSUE

SPK, Workdone, Work Progress

SPK, Workdone, Work Progress

C03/S/1

METHOD
STATEMENT

PICTURE ON
SITE

DRAWING

P.E ENDORSEMENT

BANGUNAN TAMBAHAN IPK JOHOR


BILL C04 - CAFETERIA
SUMMARY
BILL NO.

DESCRIPTION

FROM PAGE

HARGA
KONTRAK (RM)

WORKDONE
AMOUNT (RM)

VERIFIED

DIFFERENCE

C04-1

WORK BELOW LOWEST FLOOR FINISH

C04/1/5

128,813.90

112,693.90

112,693.90

C04-2

REINFORCED CONCRETE FRAME

C04/2/3

81,381.30

81,381.30

75,861.30

ROOF

C04/3/4

111,721.50

103,122.90

89,972.45

C04-4

EXTERNAL WALL

C04/4/1

6,676.50

6,676.50

6,676.50

C04-5

INTERNAL WALL AND PARTITION

C04/5/1

9,801.00

9,801.00

9,801.00

C04-6

WINDOWS AND VENTS

C04/6/3

22,962.00

10,170.30

8,057.10

2,113.20

C04-7

DOOR

C04/7/5

24,359.50

8,883.00

8,400.60

482.40

C04-8

INTERNAL FLOOR FINISHES

C04/8/1

33,907.00

25,787.75

26,256.65

(468.90)

INTERNAL WALL FINISHES

C04/9/1

C04-10

INTERNAL CEILING FINISHES

C04-11

EXTERNAL FINISHES

C04-12

ISSUE

5,520.00

C04-3

C04-9

REMARKS

13,150.45

Formwork

NCR MNA 15

Gagal mematuhi lukisan pembinaan arkitek bagi


kawasan bumbung tampak hadapan bangunan kafeteria
(Blok E)

SPK, Workdone, Work Progress


SPK, Workdone, Work Progress

30,939.00

29,380.20

19,432.55

9,947.65

C04/10/1

14,394.00

14,394.00

10,191.80

4,202.20

SPK, Workdone, Work Progress

C04/11/3

33,740.00

12,579.70

4,813.60

7,766.10

SPK, Workdone, Work Progress

COLD WATER SERVICES

C04/12/5

46,284.00

985.00

955.00

30.00

M&E Measurement

C04-13

SOIL, WASTE AND VENT PIPE

C04/13/4

44,859.00

11,516.80

11,863.00

(346.20)

M&E Measurement

C04-14

SANITARY FITTINGS AND ACCESSORIES

C04/14/3

10,992.00

1,500.00

1,500.00

C04-15

BUILT-IN FURNITURE

C04/15/1

35,000.00

C04-16

SUNDRIES

C04/16/1

33,010.00

32,510.00

32,510.00

668,840.70

461,382.35

418,985.45

TOTAL FOR BILL C04 - CAFETERIA


CARRIED TO RINGKASAN TENDER

BANGUNAN TAMBAHAN IPK JOHOR

NCR MNA 14

Gagal mematuhi spesifikasi piawai kerja kerja binaan


bangunan, blok kafeteria (Blok E) Bagi skop kerja
mengubin dan menjubin

42,396.90

C04/S/2

STATUS

METHOD
STATEMENT

PICTURE ON
SITE

DRAWING

P.E ENDORSEMENT

BANGUNAN TAMBAHAN IPK JOHOR


BILL NO C05 - SETOR PELURU
SUMMARY
BILL NO.

DESCRIPTION

FROM PAGE

HARGA
KONTRAK (RM)

WORKDONE
AMOUNT (RM)

VERIFIED

DIFFERENCE

REMARKS

ISSUE

SUMMARY
10,985.00

NCR OMK 54

Besi tetulang terdedah pada struktur tiang konkrit insitu di Blok D

C05/1

WORK BELOW LOWEST FLOOR FINISH

C05/1/5

128,503.40

128,103.40

117,118.40

C05/2

REINFORCED CONCRETE FRAME

C05/2/3

181,707.15

170,697.15

170,646.68

50.47

SPK

C05/3

ROOF (INCLUDING ROOF FINISHES)

C05/3/5

63,005.50

61,145.50

60,735.50

410.00

SPK

C05/4

DOOR

C05/4/1

17,020.00

1,180.00

1,180.00

C05/5

INTERNAL FLOOR FINISHES

C05/5/1

3,206.00

3,206.00

3,206.00

C05/6

INTERNAL WALL FINISHES

C05/6/1

13,345.50

12,054.00

11,257.58

796.42

SPK

C05/7

INTERNAL CEILING FINISHES

C05/7/1

1,995.00

1,396.50

1,339.50

57.00

SPK

C05/8

EXTERNAL FINISHES

C05/8/1

10,536.00

6,618.00

6,287.10

330.90

SPK

C05/9

SUNDRIES

C05/9/1

15,380.00

11,150.00

9,540.00

1,610.00

SPK

434,698.55

395,550.55

381,310.76

14,239.80

TOTAL BILL NO. C05 - SETOR PELURU

CARRIED TO RINGKASAN TENDER

BANGUNAN TAMBAHAN IPK JOHOR

C05/S/1

STATUS

METHOD
STATEMENT

PICTURE ON SITE

DRAWING

P.E ENDORSEMENT

BANGUNAN TAMBAHAN IPK JOHOR


BILL NO. C06 - KUARTERS KELAS D
BILL NO.

DESCRIPTION

FROM PAGE

HARGA
KONTRAK (RM)

WORKDONE
AMOUNT (RM)

VERIFIED

DIFFERENCE

REMARKS

ISSUE

SUMMARY

C06/1

WORK BELOW LOWEST FLOOR FINISH

C06/1/5

50,092.85

42,672.74

42,672.74

C06/2

FRAME

C06/2/3

27,955.50

27,955.50

25,896.33

2,059.17

OMK 82

Pemasangan Lightning Arrestor oleh NSC 'Hacking' yang


telah merosakkan struktur rasuk di Blok G

C06/3

UPPER FLOOR SLAB

C06/3/4

14,255.75

14,255.75

12,376.75

1,879.00

SPK

C06/4

ROOF STRUCTURE AND FINISHES

C06/4/6

33,999.00

33,304.00

31,710.08

1,593.93

SPK

C06/5

STAIRCASE AND FINISHES

C06/5/3

6,180.95

4,500.20

3,535.20

965.00

SPK

C06/6

EXTERNAL WALL

C06/6/1

10,313.00

10,313.00

10,313.00

C06/7

INTERNAL WALL AND PARTITION

C06/7/1

7,971.00

7,971.00

7,971.00

C06/8

WINDOWS

C06/8/3

10,841.00

9,330.95

7,320.80

2,010.15
-

C06/9

DOOR

C06/9/4

11,699.50

2,381.00

2,381.00

C06/10

INTERNAL FLOOR FINISHES

C06/10/3

14,449.00

12,252.35

11,706.05
14,442.38

C06/11

INTERNAL WALL FINISHES

C06/11/1

16,687.50

14,653.58

C06/12

INTERNAL CEILING FINISHES

C06/12/1

4,475.00

4,239.80

4,239.80

C06/13

EXTERNAL FINISHES

C06/13/3

13,362.00

11,295.90

10,786.23

C06/14

COLD WATER SERVICES

C06/14/4

22,366.00

3,000.00

2,949.00

C06/15

SOIL, WASTE AND VENT PIPE

C06/15/4

19,499.00

1,161.00

3,484.03

C06/16

SANITARY FITTINGS AND ACCESSORIES

C06/16/4

4,876.00

1,500.00

C06/17

BUILT-IN FURNITURE

C06/17/1

14,710.00

C06/18

SUNDRIES

C06/18/1

12,049.00

11,275.00

10,768.85

295,782.05

212,061.77

202,553.23

TOTAL FOR BILL C06 - KUARTERS KELAS D


CARRIED TO RINGKASAN TENDER

BANGUNAN TAMBAHAN IPK JOHOR

51.00
(2,323.03)

M&E Measurement
M&E Measurement

6,235.22

C06/S/1

STATUS

METHOD
STATEMENT

PICTURE ON SITE

DRAWING

P.E ENDORSEMENT

BANGUNAN TAMBAHAN IPK JOHOR


BILL NO. C07 - KUARTERS KELAS E (2 UNIT)
SUMMARY
ITEM

DESCRIPTION

FROM PAGE

HARGA
KONTRAK (RM)

WORKDONE
AMOUNT (RM)

65,860.55
30,992.40

45,346.98
28,412.40

VERIFIED

DIFFERENCE

REMARKS

ISSUE

SUMMARY
C07/1
C07/2

WORK BELOW LOWEST FLOOR FINISH


FRAME

C07/1/5
C07/2/3

45,346.97
28,371.93

0.00
40.47
-

C07/3

UPPER FLOOR SLAB

C07/3/4

23,994.20

21,362.20

21,362.20

C07/4

ROOF ( INCLUDING ROOF FINISHES)

C07/4/6

43,407.50

35,679.00

35,679.00

C07/5

STAIRCASE

C07/5/4

13,051.20

7,782.65

8,229.95

(447.30)

C07/6

EXTERNAL WALL

C07/6/1

14,060.00

14,060.00

14,060.00

C07/7

INTERNAL WALL AND PARTITION

C07/7/1

8,296.00

8,296.00

8,296.00

C07/8

WINDOW AND VENTS

C07/8/1

18,030.00

17,202.00

6,438.00

C07/9

DOOR

C07/9/4

14,473.00

1,891.50

1,891.50

C07/10

INTERNAL FLOOR FINISHES

C07/10/3

15,150.00

14,392.50

3,525.60

OMK 70

Berlaku keretan pada rasuk in-situ di Apron

10,764.00
10,866.90

C07/11

INTERNAL WALL FINISHES

C07/11/1

18,728.00

17,671.60

17,671.60

C07/12

INTERNAL CEILING FINISHES

C07/12/1

5,484.00

4,143.90

4,064.10

79.80

C07/13

EXTERNAL FINISHES

C07/13/3

21,253.50

11,939.10

11,939.10

C07/14

COLD WATER SERVICES

C07/14/4

27,077.00

6,723.00

4,920.00

1,803.00

M&E Measurement

C07/15

SOIL, WASTE AND VENT PIPE

C07/15/4

23,447.00

7,246.70

7,177.00

69.70

M&E Measurement

C07/16

SANITARY FITTINGS AND ACESSORIES

C07/16/4

10,420.00

4,800.00

4,800.00

M&E Measurement

C07/17

BUILT IN FURNITURE

C07/17/1

6,390.00

C07/18

SUNDRIES

C07/18/1

18,440.00

11,490.00

378,554.35

258,439.53

TOTAL FOR BILL C07 - KUARTERS KELAS 'E' (2 unit)


CARRIED TO RINGKASAN TENDER

BANGUNAN TAMBAHAN IPK JOHOR

218,972.95

11,490.00

NCR MNA 10

Gagal mematuhi kaedah 'Vertical Coping' di bahagian


'Gable End' di kawasan kuarters kelas E

39,466.57

C07/S/1

STATUS

METHOD
STATEMENT

PICTURE ON SITE

DRAWING

P.E ENDORSEMENT

BANGUNAN TAMBAHAN IPK JOHOR


BILL NO. C08 - KUARTERS KELAS F
SUMMARY
ITEM

DESCRIPTION

FROM PAGE

HARGA
KONTRAK (RM)

WORKDONE
AMOUNT (RM)

VERIFIED

DIFFERENCE

REMARKS

ISSUE

SUMMARY

WORK BELOW LOWEST FLOOR FINISH

C08/1/5

423,524.05

380,945.57

379,708.40

1,237.17

FRAME

C08/2/3

1,096,288.90

1,078,783.75

1,054,154.13

24,629.62

UPPER FLOOR

C08/3/3

1,071,953.70

933,210.00

932,123.70

Mr Naza deal with cube test


OMK 24

Melaksanakan pemasangan struktur IBS tanpa 2 dokumen


sokongan di Blok F iaitu rekod ujian konkrit dan sijil
pemasangan IBS installer.

OMK 67

Membuat penutupan terhadap 'pocket' pada panel dinding IBS


sebelum pihak perunding menjalankan kerja semakan terhadap
kerja kimpalan 'vertical tie bar' dengan plat sambungan pada
'pocket' tersebut di Blok F

OMK 74

Memecahkan panel dinding pasang siap (IBS) tanpa terlebih


dahulu memaklumkan kepada perunding sivil dan struktur.
Ianya bertujuan untuk kerja pembaikan kerangka pintu di Blok
F (Kuarters Kelas F) Aras 1

OMK 84

Melaksanakan penebukan pada struktur papak in situ dan pada


panel dinding IBS di Blok F

OMK 84

Undertaking letter request


Melaksanakan penebukan pada struktur papak in situ dan pada
panel dinding IBS di Blok F
Pemecahan pada 'pre cast toilet slab'

1,086.30

OMK 75
4

ROOF

C08/4/6

311,454.00

157,744.76

125,597.35

32,147.41

STAIRCASE

C08/5/4

85,095.85

75,476.47

67,236.23

8,240.24

Paid on design only 5%

OMK 24

EXTERNAL WALL

C08/6/1

174,284.50

163,712.25

155,289.64

8,422.61

INTERNAL WALL AND PARTITION

C08/7/1

237,123.50

237,123.50

225,267.33

11,856.17

Rectification work backcharge to GPS


Dapatkan method of work from GPS
"
MNA 21

WINDOWS

C08/8/1

229,220.00

73,652.00

73,582.20

69.80

DOOR

C08/9/6

355,063.50

114,032.60

98,573.08

15,459.52

INTERNAL FLOOR FINISHES

C08/10/3

388,872.00

241,881.60

201,654.10

40,227.50

11

INTERNAL WALL FINISHES

C08/11/1

289,865.50

245,684.39

240,074.15

5,610.24

BANGUNAN TAMBAHAN IPK JOHOR

Rectification and SPK


Kualiti kerja ikatan batu bata dan blok pengudaraan tidak
mematuhi kualiti binaan yang terkandung dalam item no. 8 dan
9 borang JKR.PK(O).04-SKC.ST.4B

"

MNA 5

MNA 17

10

Melaksanakan pemasangan struktur IBS tanpa 2 dokumen


sokongan di Blok F iaitu rekod ujian konkrit dan sijil
pemasangan IBS installer.

Pemasangan kerangka pintu (door frame) di aras satu gagal


mematuhi lukisan pembinaan arkitek di Kuarters Kelas F (Blok
F)
Gagal mematuhi lukisan pembinaan arkitek bagi kuarters kelas
"F" dan lukisan pembinaan struktur IBS bagi kuarters kelas "F"
bagi rekabentuk kedudukan pintu "Toilet 2"
Rectification and SPK

C08/S/1

STATUS

METHOD
STATEMENT

PICTURE ON SITE

DRAWING

P.E ENDORSEMENT

ITEM

DESCRIPTION

FROM PAGE

HARGA
KONTRAK (RM)

WORKDONE
AMOUNT (RM)

VERIFIED

DIFFERENCE

REMARKS

ISSUE

12

INTERNAL CEILING FINISHES

C08/12/1

87,649.00

24,275.20

24,275.20

13

EXTERNAL FINISHES

C08/13/1

286,066.00

120,248.21

79,994.25

14

COLD WATER SERVICES

C08/14/5

170,998.00

22,299.40

23,637.00

15

SOIL, WASTE AND VENT PIPE

C08/15/4

170,438.00

71,857.20

42,825.00

29,032.20

M&E Measurement

16

SANITARY FITTINGS AND ACCESSORIES

C08/16/4

81,100.00

4,000.00

200.00

3,800.00

M&E Measurement

17

BUILT-IN FURNITURE

C08/17/1

381,200.00

18

SUNDRIES

C08/18/1

TOTAL FOR BILL C08 - KUARTERS KELAS F


CARRIED TO RINGKASAN TENDER

BANGUNAN TAMBAHAN IPK JOHOR

24,346.50
5,864,543.00

3,944,926.90

3,724,191.76

40,253.96
(1,337.60)

IBS Panel Uneven


M&E Measurement

220,735.14

C08/S/1

STATUS

METHOD
STATEMENT

PICTURE ON SITE

DRAWING

P.E ENDORSEMENT

PEMBINAAN BANGUNAN TAMBAHAN IPK JOHOR


BILL NO. C09C - STESEN SUIS UTAMA
SUMMARY

BILL NO.

DESCRIPTION

FROM PAGE

HARGA KONTRAK
(RM)

WORKDONE
AMOUNT (RM)

VERIFIED

DIFFERENCE

C9A - PUSAT PENGUMPULAN SAMPAH

C9A/(i)

81,484.44

C9B - PENTAS HORMAT

C9B/(i)

40,115.10

C9C - STESEN SUIS UTAMA (SSU)

C9C/(i)

208,970.75

203,678.25

193,205.75

10,472.50

330,570.29

203,678.25

193,205.75

10,472.50

TOTAL FOR 'BILL NO. C09C - STESEN SUIS UTAMA


CARRIED TO RINGKASAN TENDER

BANGUNAN TAMBAHAN IPK JOHOR

C09C/S/1

REMARKS

ISSUE

STATUS

PEMBINAAN BANGUNAN TAMBAHAN IBU PEJABAT POLIS KONTIJEN (IPK) JOHOR


BILL NO. D - EXTERNAL WORKS
PERAKUAN BAYARAN KEMAJUAN NO. 30
ITEM

DESCRIPTION

PAGE
CONTRACT AMOUNT

WORKDONE
(RM)
AMOUNT (RM)

VERIFIED

DIFFERENCE

REMARKS

ISSUE

SUMMARY
D1

DEMOLITION, SITE CLEARING AND EARTHWORKS

D1-6

1,038,955.90

D2

LANDSCAPING WORKS (ALL PROVISIONAL)

D2-10

491,069.00

D3

ROAD, CARPARK AND FOOTPATH (ALL PROVISIONAL)

D3-5

2,800,384.33

D4

COVERED WALKWAY (ALL PROVISIONAL)

D4-5

253,168.75

D5

SURFACE WATER DRAINAGE (ALL PROVISIONAL)

D5-4

2,607,860.00

512,701.81

59,113.20
410,895.15

412,701.81

59,113.23
344,529.12

100,000.00

NCR - Jambatan Kuning

OMK 64

(0.03)
66,366.03

OMK 85
OMK 96
OMK 81
OMK 88
OMK 92
OMK 94

OMK 95

D6

SEWERAGE WORKS (ALL PROVISIONAL)

D6-8

1,289,165.00

371,665.00

278,665.00

Kawasan cerun dan tanah terbuka yang terlibat di dalam


pembinaan longkang utama untuk tidak ditanam dengan rumput
kaedah closed turf dan spot turf di Silt Trap

93,000.00

OMK 46
OMK 49
OMK 56
OMK 63

OMK 86

OMK 87

OMK 89
OMK 98

Pembinaan sump bagi longkang utama telah rosak


Sump yang telah dibina mengalami kerosakan (brickwork)
pembinaan semula perlu dilakukan
Tiada Strut bertulang pada pembinaan longkang utama
berhampiran Blok B.
Pembinaan parit utamaberhampiran Blok F tanpa stiffener
starter bar, kontraktor utama tidak mematuhi lukisan
pembinaan
Dinding saliran utama berdekatan Blok D telah runtuh.
Struktur stiffeneer yang dibina tidak sebagaimana gred konkrit
25N/mm2
Pembinaan dinding bata tidak mengikut seperti mana 'standard
specifications for building works 2005' klausa 5.1 brick walling.
Ketidak patuhan ini boleh menyebabkan runtuhan dinding
saliran utama sebagaimana yang telah berlaku di Blok D
NCR OMK 46 = Cerun runtuh di kawasan STP.
NCR OMK 49 = Penanaman cerucuk (150mmx150mm) tanpa
mengemukakn borang SPK JKR dan penyeliaan perunding civil
dan struktur
NCR OMK 56 = Menggunakan beberapa cerucuk sebagai
platform bagi jentera melantak cerucuk
NCR OMK 63 = Melaksanakan kerja menanam cerucuk tanpa
mengemukakan 'method statement' , katalog jentera dan
dokumen dokumen yang berkaitan
NCR OMK 86 = SPK form untuk penyemakan kerja dan lukisan
pelan 'as built' bagi cerucuk tidak dikemukakan sebelum kerja
kerja lean konkrit untuk sub struktur
NCR OMK 87 = Menggunakan "Sledge hammer" sebagai kaedah
kerja pemotongan cerucuk yang telah siap ditanam di STP
NCR OMK 89 = Melaksanakan kerja "Lean Concrete' tanpa
kelulusan lukisan pelan 'as built" bagi cerucuk - cerucuk yang
telah siap ditanam di STP, tidak mematuhi prosedur yang telah
digariskan oleh JKR
NCR OMK 98 = Pembinaan Substruktur STP

STATUS

METHOD
STATEMENT

PICTURE ON SITE

DRAWING

P.E ENDORSEMENT

D7

EXTERNAL WATER RETICULATION (ALL PROVISIONAL)

D7-5

D8

CHILDREN PLAYGROUND (ALL PROVISIONAL)

D8-1

465,505.00
37,600.00

D9

RETAINING WALL (ALL PROVISIONAL)

D9-7

631,054.62

591,772.12

589,528.12

2,244.00

OMK 26
OMK 69

D10

ELEVATED WATER TANK (ALL PROVISIONAL)

D11

SPORT FACILITIES (ALL PROVISIONAL)

D10/(i)

681,496.05

D11-5

232,680.00

340,280.74

227,123.35

113,157.39
OMK 71
OMK76

PRELIM

OMK 31
OMK 34

TOTAL CARRIED TO SUMMARY

10,528,938.65

2,286,428.01

1,911,660.63

Kebocoran pada struktur tembok jenis W1 di Blok A aras separa


bawah
Berlaku resapan air keluar dan tembok penahan jenis batu-bata
di Blok B

374,767.39

Borang pemariksaan SPK JKR (SPK) yang tidak lengkap bagi


kerja kerja di tapak bina
Tidak melaksanakan penyelengaraan terhadap longkang tanah
sementara berhampiran blok G kuarters kelas D, Blok H kuarters
kelas E dan kantin sementara
Tidak melaksanakan penyelenggaraan silt trap dan closed turfing
pada cerun di kawasan silt trap dan terdapat sisa binaan di
kawasan silt trap.
Pembuangan sisa air kumbahan dari lubang pembentung
sementara ke dalam silt trap.

Item

Descriptions

NCR No.

GGMSB Reply

Consultant Reply

Amount Deducted (RM)

Remarks

BLOK B (Trafik dan Jenayah)

Kedudukan Steel Column (sistem kekuda) tidak berada


dalam lingkungan lebar rasuk IBS

OMK/IPK/NCR/068 Dated 16/01/2013


(See Attachment 1)

GGMSB(S)/CONS/IPKJ/MEMO/OMK/
64/13 Dated 13/02/2013
(See Attachment 2)

PENDING

370,577.20

Blok C (Bekalan & Persenjataan)


2

Purlin Bengkok pada sistem Kekuda Bumbung

OMK/IPK/NCR/079 Dated 18/02/2013


(See Attachment 3)

PENDING

Terdapat kotoran tanah pada purlin

OMK/IPK/NCR/065 Dated 14/01/2013


(See Attachment 4)

IN PROGRESS To rectified at site

Keadaan cat sebanyak 5 lapisan di kekuda bumbung

47,832.35

IN PROGRESS To rectified at site

VARIATION ORDER
5

Kerja-kerja Tambahan perparitan 'Open L-Shape Drain'

Kerja-kerja Tambahan bagi item di atas.

Jumlah

102,055.50

As Built Drawing submitted


GGMSB(S)CONS/IPKJ/JKR/354
/2012 Dated 28 Dis. 2012
(See Attachment 5)

29,245.00

Tuntutan Tambahan telah


dihantar
GGMSB(S)/CONS/IPKJ/JKR/32
6/2012 Dated 19 Oktober 2012
(See Attachment 6)

549,710.05