Professional Documents
Culture Documents
Contract Title:
NTP Actual Date Original Contract Duration Original Construction Value Forecast Construction Value $0.00
Actual % Complete
Schedule Summary
rev.1
Issues/Action
rev.1
$ $ $ $ $ Total $
BUDGET SUMMARY
SYSTEMS CONTRACT AMOUNT CURRENT CLAIM CUMULATIVE CLAIM DUE AMOUNT ANY VARIANCE COST TO COMPLETE
SAR 0.00 SAR 0.00 SAR 0.00 SAR 0.00 SAR 0.00 SAR 0.00 SAR 0.00 SAR 0.00 SAR 0.00
SAR 0.00 SAR 0.00 SAR 0.00 SAR 0.00 SAR 0.00 SAR 0.00 SAR 0.00 SAR 0.00
SAR 0.00 SAR 0.00 SAR 0.00 SAR 0.00 SAR 0.00 SAR 0.00 SAR 0.00 SAR 0.00
SAR 0.00 SAR 0.00 SAR 0.00 SAR 0.00 SAR 0.00 SAR 0.00 SAR 0.00 SAR 0.00
SAR 0.00 SAR 0.00 SAR 0.00 SAR 0.00 SAR 0.00 SAR 0.00 SAR 0.00 SAR 0.00
SAR 0.00 SAR 0.00 SAR 0.00 SAR 0.00 SAR 0.00 SAR 0.00 SAR 0.00 SAR 0.00
rev.1
Original Contract Award Value: Executed Change Orders/CQV's in CMS Pending Change Orders/CQV's in CMS Total with executed & Pending Change Orders/CQV's in CMS SAR -
SAR 0.00
rev.1
PENDING CLAIM TOTAL VALUE SUBTOTAL OF PENDING CHANGE ORDERS & CLAIMS NOT IN CMS
SAR 0.00
rev.1
Contract #:
rev.1