Alberto Buenda / Manuel Pareja / Carlos Len Southern Peru Copper Corporation 2011
INTRODUCTION
TOQUEPALA CONCENTRATOR: -THROUGHPUT: 60,000 t/d. -HEAD: 0.60 % COPPER AND 0.025 % MOLYBDENUM. PORPHIRY ORE. -CONCENTRATE PRODUCTION: 1500 t/d. -CONCENTRATE GRADE: 27.0 % COPPER. - COPPER RECOVERY: 88-91 %. - MOLYBDENUM RECOVERY: 68-72 %.
ROUGHER FLOTATION
WEMCO
130 (02)
WEMCO 60 (04)
CLEANER FLOTATION
COLUMN CELLS (15) REGRINDING BALL MILLS (07) CENTRAL TANK SCAVENGER FLOTATION MIDDLING THICKENER (02) (05) (05)
OK 50 (03) WEMCO 60 (01)
BULK THICKENER
CONVENTIONAL THICKENER (02) REGRINDING BALL MILL (01) MIDDLING THICKENER (01) WATER RECOVERY PUMPS (06) TO TAILING DAM "QUEBRADA HONDA" COPPER THICKENER (02)
ROUGHER FLOTATION(30)
MOLYBDENUM PLANT
CONDITIONER TANK (01)
1 CLEANER (05) 2 CLEANER (12) 3 CLEANER (12) 4 CLEANER (08) 5 CLEANER (06) 6 CLEANER (04)
ORE FROM MINE BULK CONCENTRATE COPPER CONCENTRATE MOLIBDENUM CONCENTRATE FINAL TAIL WATER
FILTRATION PLANT
SEDIMENTATION TANKS (04) PRESSURE FILTER (01) PRESSURE FILTERS (02) DISC FILTERS (04)
DRYERS (03) 7 CLEANER (02) 8 CLEANER (01) 9 CLEANER (01) MOLYBDENUM CONCENTRATE (BIG BAGS)
Ore feed
Ore feed
Mill discharge
Mill discharge
THE ALTERNATIVES PROPOSED WERE: - CHANGE OF HYDROCYCLONES AND OPTIMISATION OF APEX SIZE IN SECONDARY GRINDING. - CHANGE OF VORTEX SIZE TO 304.8 mm IN SECONDARY GRINDING HYDROCYCLONES. - USAGE OF 50.8 mm BALLS CURRENTLY USED OF 63.5 mm. INSTEAD OF THE BALLS
CONCLUSIONS
- BOTH PROPOSAL TO DATE IMPLEMENTED REPORTED CLEAR ECONOMICAL BENEFITS. IT IS EXPECTED THAT CHANGE IN BALL SIZE PRODUCES SIGNIFICANT BENEFITS ALIKE. - FOR THE CHANGE IN THE APEX SIZE, IT WAS VERIFIED THE TENDENCY PREDCITED BY THE SIMULATOR. THE MAJOR DIAMETER IN THE APEX AVOIDED THE ROPING EFFECT, LIMITING CONDITION OF TONNAGE. - FOR THE INCREMENT IN THE VORTEX SIZE, WE REACHED TO INCREASE THE TONNAGE PROCESSED MAINTAINING THE SAME FINENESS IN THE OVERFLOW. THE INCREMENT IN THE QUANTITY OF WATER ADDED TO THE SUMP PUMP CONTRIBUTED TO CONTROL +65 MESH PRODUCING A SIMILAR P80 AS THE STANDARD CONDITION.
CONCLUSIONS
- FOR THE PROPOSAL OF CHANGE OF BALL SIZE, SIMULATIONS PREDICT AN IMPORTANT IMPROVEMENT IN TONNAGE PROCESSED MAINTAINING THE SAME GRANULOMETRY IN HYDROCYCLONES OVERFLOW OR AN IMPORTANT IMPROVEMENT IN P80 FOR A CONSTANT TONNAGE - THESE EVALUATIONS DEVELOPED IN PLANT PROVE THAT SIMULATION SOFTWARE IS A POWERFUL TOOL FOR DEVELOPING OPTIMISATION OF PROCESSING PLANTS. IN TOQUEPALA CONCENTRATOR, AS SHOWN, IT HAS BEEN USED TO OPTIMISE THE GRINDING THROUGHPUT IN NORMAL CONDITIONS OF ORE HARDNESS, AND REDUCE THE IMPACT OF LESSER TONNAGE WHEN HIGH HARDNESS ORE IS TREATED.