Contents
Key Points Hardware Installation Equipment Commissioning DCN Commissioning Acceptance Other Specifications
Key Points
Caution
1 Properly handle the IF board and SCC power switches.
Cause
The field personnel do not know how to operate the power switches. As a result, a large number of boards on the existing network are damaged.
Requirement
This point must be imparted to every field engineer, especially the personnel of the partners. This point must be imparted to every field engineer, especially the personnel of the partners.
The ODU and IF board are damaged by the reseating of IF cables when the power is on.
If the seal of the ODU is torn up or the cover of the ODU is removed, the vendor will refuse to provide warranty services.
This point must be imparted to every field engineer, especially the personnel of the partners. This point must be imparted to every field engineer,
Huawei Confidential
Page 3
Key Points
Train microwave partners for standardized operations according to projects. Hand out related training materials to every partner and every engineering team. Provide special trainings for the partners with serious problems. Provide effective trainings to all new partners.
improper operations of the personnel. Note: So many boards are found damaged in only one project!
Huawei Confidential
Page 4
Key Points
Train microwave partners for standardized operations according to projects. Hand out related training materials to every partner and every engineering team. Provide special trainings for the partners with serious problems. Provide effective trainings to all new partners.
Huawei Confidential
Page 5
Key Points
Train microwave partners for standardized operations according to projects. Hand out related training materials to every partner and every engineering team. Provide special trainings for the partners with serious problems. Provide effective trainings to all new partners.
reseating IF cables.
Reseating IF cables when the power is on tends to cause a short circuit between the 48V power supply and the GND, which will blow out the protection tube.
Huawei Confidential
Page 6
Key Points
Train microwave partners for standardized operations according to projects. Hand out related training materials to every partner and every engineering team. Provide special trainings for the partners with serious problems. Provide effective trainings to all new partners.
the cover of the ODU is removed without permission, the vendor will refuse to provide warranty services.
The seal of the ODU shall not be torn
up.
The ODU cover shall not be removed
without permission.
Huawei Confidential
Page 7
Key Points
Train microwave partners for standardized operations according to projects. Hand out related training materials to every partner and every engineering team. Provide special trainings for the partners with serious problems. Provide effective trainings to all new partners.
engineering operations must be returned as soon as possible. The vendor shall not provide warranty services after the warranty expires.
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 8
Contents
Key Points Hardware Installation Equipment Commissioning DCN Commissioning Acceptance Other Specifications
Note
Key Points The Standardized Operating Process (SOP) is implemented based on the existing process. Courseware for partners . 3D animation.
Installation of The operation is the same as that of the traditional ODUs microwave.
Installation of The operation is the same as that of the RTN 900 V1R1. IDUs
Huawei Confidential
Page 10
Installation of IDUs
Requirements for the input power of the IDU Rated Voltage
RTN 910 RTN 950
48V/60V
48V/60V
38.4V72V
38.4V72V
10A
20A
Huawei Confidential
Page 11
Contents
Key Points Hardware Installation Equipment Commissioning DCN Commissioning Acceptance Other Specifications
Commissioning Strategies
B
IDU BTS
A
IDU
Means for supporting the partner to complete the construction of BTSs independently: WEBLCT Handheld terminal Remote access in wireless mode SOP Means for remote access: Downloading the script files for remote access in wireless mode Centralized NMS (including 2M and shared 2M)
Huawei Confidential
Page 13
System commissioning
Station work
Hardware installation
Equipment power-on
RF configuration
Antenna alignment
Equipment commissioning
Hardware personnel
Antenna alignment
Huawei Confidential
Page 14
The AM function of the hybrid microwave should be disabled before the antennas are aligned.
The antennas should be aligned in low modulation mode provided by network planning.
The received signal level (RSL) value must be within the scope as required. The AM function of the hybrid microwave must be enabled after
the antennas are aligned. Note: During equipment commissioning, perform operations as required. Otherwise, the boards may be damaged and you have to enter the station to replace the damaged boards!
Huawei Confidential
Page 15
Power on equipment
Basic configuration
Align antennas
Equipment Commissioning
Power On There is no power switch on the RTN 900 IDU cabinet, so that, it is important to test the input voltage value.
Huawei Confidential
Page 16
Power on equipment
Basic configuration
Align antennas
Equipment Commissioning
Power on equipment and IF boards
RTN 950
Power on the corresponding power distribution box first. Power on the ODUs on the IF board (including active and standby ODUs). Note: The switches must be first pulled out and then turned.
RTN 910
The switches must be pulled out first and then turned to the right. Forcible pulling is prohibited!
Huawei Confidential
Page 17
Power on equipment
Basic configuration
Align antennas
Equipment Commissioning
Connect Laptop with RTN 900
ETH-OAM
WEBLCT
Huawei Confidential
Page 18
Power on equipment
Basic configuration
Align antennas
Equipment Commissioning
Login U2000 Web LCT
passwordT2000
Huawei Confidential
Page 19
Power on equipment
Basic configuration
Align antennas
Equipment Commissioning
Creat NE
Huawei Confidential
Page 20
Power on equipment
Basic configuration
Align antennas
Equipment Commissioning
Configure NE ID/ NE Name
Configure NE names. Change NE IDs. The IDs in one network must be unique.
Power on equipment
Basic configuration
Align antennas
Equipment Commissioning
Add boards.
Huawei Confidential
Page 22
Power on equipment
Basic configuration
Align antennas
Equipment Commissioning
Create the IF 1+1 protection group (this step can be omitted for the 1+0 mode).
Slot 1 and Slot 2 constitute a protection group with Slot 1 as the recommended working slot. Slot 3 and Slot 5 constitute a protection group with Slot 3 as the recommended working slot. Slot 4 and Slot 6 constitute a protection group with Slot 4 as the recommended working slot.
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 23
Power on equipment
Basic configuration
Align antennas
Equipment Commissioning
Configure Link
Power on equipment
Basic configuration
Align antennas
Equipment Commissioning
function is disabled.
Confirm that the AM function is disable .the default value is disable.
Huawei Confidential
Page 25
Power on equipment
Basic configuration
Align antennas
Equipment Commissioning
Align the antennas query the receive power.
Huawei Confidential
Page 26
Power on equipment
Basic configuration
Align antennas
Equipment Commissioning
Enable the AM function.
It is zero when
After the AM function is enabled, set IF Channel Band, Modulation Mode of the Assured AM Capacity, and Modulation Mode of the Full AM Capacity according to networking planning.
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 27
Contents
Key Points Hardware Installation Equipment Commissioning DCN Commissioning Acceptance Other Specifications
For one telecom room, multiple RTN600s can interwork through the extended ECC. This work must be made clear to partners in advance.
NMS
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 29
Description
The customer provides the Ethernet or E1 (or N x 64 K) channels, and NMS information of Huawei is directly connected to the third-party Ethernet port as common services or connected to E1 channels through the protocol
Advantage
The interface of Huawei is simple, involving no cooperation with third-party equipment.
Disadvantage
The service channels of the customer are occupied.
Priority
1
converter/clock port.
Transparent transmission through synchronous ports or asynchronous ports The third-party equipment is required to provide the synchronous or asynchronous data ports. Then, information is transmitted transparently through the third-party microwave equipment. Finally, information is converted back to Ethernet NMS information through the protocol converter. The NMS can also be connected to the third-party equipment directly. Service channels are not occupied. 1. Special connectors need to be prepared. 2. The cooperation of the third party is required, which is very risky. 2
Through the IP
over DCC protocol
1. It is hard to configure. 2.
The cooperation of the third party is required, which is very risky.
The NEs of the third-party equipment are required to support OSI (TP4) and NMS network ports. NMS information is transmitted in OSI sharing mode.
1. It is harder to configure this solution than the IP solution. 2. The cooperation of the third party is required, which is very risky.
Huawei Confidential
Page 30
Contents
Key Points Hardware Installation Equipment Commissioning DCN Commissioning Acceptance Other Specifications
Acceptance Strategies
1. The operations must be strictly compliant with the Acceptance Guide. 2. The acceptance consists of two parts, namely, Acceptance Items and Form (Recommended) and Acceptance Items and Form (Optional).
3. It is recommended that the items to be tested should be selected only from the
Acceptance Items and Form (Recommended) and the items should be as few as possible. If the customer has special requirements, a few items that can be tested can be selected from the Acceptance Items and Form (Optional). 4. Before the acceptance, acceptance items and operation instructions that correspond to these items should be printed based on the selected items, combined into a manual, and submitted to the customer. The manual submitted to the customer cannot consist of items not to be tested and corresponding test instructions. It is prohibited to submit the unedited Acceptance Guide to users.
5. The items selected from the Acceptance Items and Form (Optional) need to be
quoted and charged separately. 6. Recommend remote acceptance to customers. It is recommended that the percentage of items subject to on-site acceptance be 5% - 10%.
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 32
Online test methods of Ethernet services: The ETH-OAM function is used for testing Ethernet services.
Prerequisite: Antenna alignment is completed. The RTN605 V100R300 or RTN620 V100R300 is configured
1. 2. 3. 4. 5. 6.
Select the NE from the Object Tree in the NE Explorer of the NE1, and then choose Configuration > Ethernet OAM Management > Ethernet Service OAM Management Select the MD, MA, and MEP that correspond to Port 1, click OAM. Select Start LB. The LB Test window is displayed. . Select MP ID, and set the parameters in Test Node. Click Start Test. Check Detection Result. The LossRate in the Detection Result should be 0.
Huawei Confidential
Page 33
Acceptance AM Test
Method of testing the AM handover function: If the hybrid microwave is used for transmission, whether the handover function is normal can be verified by testing the AM handover function.
Procedure:
Disable the AM function. Enable 15-minute performance monitoring. Query the performance: No FEC-BER-CORER, and only the low modulation mode is available. Enable the AM function. Query the performance: No FEC-BER-COR- 3 ER exists. It can be found that the modulation modes is adjusted from low to high.
Notes: 1. The two ends of the link must be configured synchronously. 2. This method is not the same as the method of decreasing the optical power described in the Commissioning Guide. This is better. The Commissioning Guide will be modified later.
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 34
Contents
Key Points Hardware Installation Equipment Commissioning DCN Commissioning Acceptance Other Specifications
Reclaiming Licenses
Strategies and requirements for microwave licenses
Due to the uncertainty of microwave network planning, delivery based on
BTSs is impossible. Therefore, under the microwave strategy, the Supply Chain delivers the maximum number of licenses. The GTS is in charge of reclaiming the frontline licenses. For projects delivered by customers, customer support engineers should mark them clearly and the Supply Chain delivers the licenses as planned.
During the engineering implementation or before preliminary acceptance, GTS
engineers reclaim licenses according to the actual license capacity in the orders.
GTS engineers download license files of the corresponding capacity from the
support website of Huawei, load them on the site or remotely through the DC software, and then click the files to activate them.
Huawei Confidential
Page 36
Reclaiming Licenses
Hybrid microwave license solution
Huawei Confidential
Page 37
Entry to CEAS
In 2008, the Network Product Technical Service Dept issued the Notice on Requirements for Entry of Information About RTN Microwave Customer Equipment to CEAS, clearly requiring that engineering information about RTN microwave should be entered to CEAS in a timely manner.
Currently, CEAS features low entry rate, low accuracy, and poor availability, which seriously affects the follow-up implementation of services. To improve the data entry rate of CEAS and enhance the timeliness and accuracy of CEAS data entry, the Network
The requirements and mode of entering homegrown products to CEAS should be the same as those of other products. After a project is completed, related data needs to be entered in CEAS. For entry criteria and operation methods, see the appendix to the Notice.
For RTN microwave engineering projects completed in 2008 or earlier, all missing data should be entered in CEAS in Q1 of 2009.
The network product manager of the technical service department at each representative office is the first owner for entering and supplementing data about homegrown microwave
in CEAS. The product manager designates microwave engineers to complete the entry.
Huawei Confidential
Page 38
Entry to CEAS
Guide to entry of data about RTN900 V1000R200 in CEAS:
Huawei Confidential
Page 39
frontline for trial use. Representative offices and project teams need to return damaged parts and purchased parts as required. Guide to Repair and Return of Overseas Purchased Microwave Parts (V1.0) Guide to the Process of Handling the Faulty Purchased ODU (Applicable to the Countries Outside China)(V1.0) Guide to the Process of Handling the Faulty Purchased ODU (Applicable to China)(V1.0) Criteria for Determining Whether an ODU Fault Is Caused by a Quality Defect of the ODU Checklist for the Description of the Faulty ODU.xls Overseas Return and Repair Process for Spare Parts of Purchased ODUs Used in SelfMade Microwave Equipment
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 40
parts to be installed. GTS engineers should control the sales of microwave spare parts to customers effectively.
The HQ does not store spare parts for OEM microwave or purchased equipment such
a certain number of IDU and ODU spare parts according to the lowest requirement.
The HQ should review and approve the applications of representative offices for spare
parts in strict compliance with related service contracts and service SLAs.
The OEM microwave and OEM spare parts applied for by representative offices shall, in
principle, not be returned to the HQ (the method of handling the returned equipment or spare parts is unavailable).
Huawei Confidential
Page 41
Thank you