-: Action Plan: S.N. 1. 2. 3. 4. 5. Details of activity Review and recalculation of vent size as per API standards.

Preparation of instrument PDS (PCV (9), PSV (8), BV(2) etc.) for tank farm & utility fluids. PID and Hydraulic calculations check for tank farm & utility fluids for 3 phases with pipe rack table. Data consistency check of process datasheets, equipment list, specifications, PFD & PID. Review and modify process design basis, summary reports according to latest pipe rack table & PID.

Date :- 14.12.2012

Duration 17 Dec12 to 21 Dec12 24 Dec12 to 28 Dec12 31 Dec12 to 9 Jan13 10 Jan13 to 18 Jan13 21 Jan13 to 31 Jan13