PE95-LT-PV-0002
Rev. :
Step 1: GAUGING AND CUTTING WHER REQUIRED BEETWEN LT-p0010, LT-p0011, and LT-p0009
Gauging/cut
DRAWING NO :
PE95-LT-PV-0002
Rev. :
STEP 2:
CLAMP OR LOCKDOWN AS CLOSE AS POSSIBLE TO PLATES LT-p0012/LT-p0013
Shim plate
Shim plate
DRAWING NO :
PE95-LT-PV-0002
Rev. :
Step 3
Brace
Stopper
90
-Align plates LT-p0012/LT-p0013 90 to base plate LT-k0005 and weld in brace before release hydraulic RAM. - Same technique for all plates.
DRAWING NO :
PE95-LT-PV-0002
Rev. :
Step 4
Check levelness for bottom part upon straightening the side plate
Note: 1) Dimension tolerance for bottom plate should be less than 5mm if more than 5mm fairing to be done.
DRAWING NO :
PE95-LT-PV-0002
Rev. :
STEP 5
HEATING POINT
HEATING POINT
NOTE: 1) Please refer to the procedure FFCM-PDR-PE95-01 for fairing methods. 2) Supports should NOT be removed after the fairing works, Item will be sending for PWHT.