1,200

REMOVE DAIS

Sill 1,100

REMOVE EXISTING PINBOARDS

600 900

REMOVE DAIS, CHALKBOARD & WALL FITTINGS

BREAK OPEN FOR NEW VISION PANEL

REMOVE DAIS, CHALKBOARD & WALL FITTINGS

G1 INTERVIEW

SCABBLE EXISTING CONCRETE SURFACE IN PREPARATION FOR RAMPED CONCRETE TOPPING

W04

R.L. + 19.500

GENERAL PURPOSE LEARNING AREA


REMOVE EXISTING CEILING TILES

G20 (A8): GENERAL PURPOSE LEARNING AREA


REMOVE EXISTING CEILING TILES

CPT

G19 (E): CURRENT BOOK HIRE ROOM TO REMAIN


950 2,070
WIDEN DOOR TO 950mm

SEAL UP NEW DOOR REPLACE UPPER PANELS OF GLASS WITH FROSTED GLASS

REVERSE HAND DOOR, OPEN OUT AND MAKE GOOD

980 2,988

980 2,990

PREPARE FOR NEW RAMP CONSTRUCTION

carste STUDIO P TY LTD


ABN 16122394450 trading as ACN 122394450

W01

001

stephen
R.L. + 19.650

booker
and

architect
Consultants

015

Architects
950 2,100
ENLARGE OPENING REMOVE DOOR

Heritage

950 2,050

NEW DOOR

CURRENT GENERAL PURPOSE LEARNING AREA

p: (02) 4951 2578 m: 0427 432 720 f: ( 0 2 ) 4 9 5 0 0 5 9 1 e: b o o k e r a r c h @ t p g . c o m . a u a: P O B o x 1 4 9 Wa l l s e n d 2 2 8 7

016

005

G18 - CURRENT GYM / ASSEMBLY ROOM


REMOVE EXISTING PANELS TO WALL AND REINSTATE OPENING
REMOVE WINDOW AND BREAK OUT SILL

REMOVE EXISTING DOOR INFILL AND MAKE GOOD

017
FORM NEW DOOR WAY

018

REMOVE DAIS AND STEPS

EXISTING GPLA
REMOVE FLOOR

CURRENT SPECIAL LEARNING UNIT


1,029 2,486 1,540 2,400
EXISTING R.L. 17.33

009

REMOVE WALL

All information, concepts and ideas contained herein are the property of Carste Studio Pty Ltd and may not be distributed and/ or reproduced without express permission from Carste Studio Pty Ltd. It is the responsibility of the builder to check and verify all dimensions on-site prior to the commencement of work and to notify Carste Studio Pty Ltd of any errors and omissions. Do not scale drawing. Do not use drawing for consrtuction purposes unless issued by Carste Studio Pty Ltd for construction.

1,000 2,100

EXISTING SEAT

950 2,100

950 2,100

STRIP OUT INTERNAL FIXTURES FOR RENEWAL.

Project:
Client:
NEW DOOR OPENING

STOP OFF SERVICES, REMOVE BENCHES & FITTINGS COMPLETE.


REGLAZE WITH CLEAR GLASS

004

W05
REPLACE EXISTING WINDOW WITH DOOR. RETAIN WINDOW

Bin

EXISTING LIGHTWELL

1,000 2,400

950 2,040

CATHOLIC SCHOOLS OFFICE


Diocese of Maitland - Newcastle

012

010

EXISTING R.L. 18.50


REMOVE HONOUR BOARDS FOR RELOCATION IN RECEPTION AS REQUESTED

REMOVE EXISTING DAIS

Project Name:

G23 (B3): FOOD TECHNOLOGY


SV

CURRENT MUSIC ROOM

Alterations Stage 2: San Clemente Catholic High School 78 Havelock Street Mayfield
Project No:

DEMOLISH FLOOR OVER STOP OFF SERVICES REMOVE DIAS & BENCH

REMOVE EXISTING WALL

08:16 North Point:

POWER DISTRIBUTION BOARD

EXISTING CONCRETE COLUMN AND STEEL POSTS


REMOVE DOOR FRAME

022
900 2,100

020
19A 900 2,100

890 3,190

G17 (A5): PERFORMING ARTS


CPT

CURRENT CAREERS OFFICE


REMOVE SINK & STOP OFF SERVICES

REMOVE EXISTING WALL AND DOOR AND MAKE GOOD

G16 EXISTING STAIR (REMOVED)

RENEW CARPET

REMOVE EXISTING STAIR AND MAKE GOOD INFILL TIMBER FRAME TO FLOOR

REMOVE DOOR AND FRAME

1,000 2,100

REMOVE SINK, BENCHES & SPLASHBACK

RENEW DOOR

855 2,050

CURRENT MUSIC ROOM


900 2,400
CPT

CURRENT DESIGN & TECHNOLOGY ROOM


CPT

023
885 2,085

STOP OFF SERVICES, REMOVE BENCHES & FITTINGS COMPLETE.

G24 (B3): PANTRY


SV

3,580

REMOVE WINDOW

019

13A

G15 WC: WOMEN


CT

24A
REMOVE INTERNAL PARTITIONS, WALLS, FITTINGS AND FIXTURES AND MAKE GOOD. REPLACE ENTRY DOOR WITH NEW UNIT COMPLIANT WITH AS AND BCA.

Bar Scale:
0 1 2 3 4 5

EXISTING R.L. 18.47

REMOVE BENCH

EXISTING R.L. 18.49

REMOVE DOOR AND FRAME

R.L. 18.60

G26 STAFF ROOM (SEPARABLE PORTION)


CPT
STRIP OUT WC AREA FOR REFURB

Legend:
EXISTING CONSTRUCTION

RAISE TROUGH HEIGHT TO SUIT NEW PAVEMENT LEVELS

EXCAVATE FOR FOOTINGS FOR NEW RAMP

ACOUSTIC WALL - PBD EQUIV TO BORAL T1616F


230 BRICK. SEE SCHEDULE OF FINISHES FOR SURFACE FINISH

1,020 3,180

Bin

EXISTING SCIENCE

014

EXISTING WALKWAY
CBR

270 BRICK SEE SCHEDULE OF FINISHES FOR SURFACE FINISH

GARDEN BED

BK

= BRICK
= STUD (TIMBER OR STEEL)

ST

RELOCATE SEAT

Amendments:
Rev:
Detail:

EXISTING SEAT

PAVERS

Date:

REMOVE PAVERS IN PREPARATION FOR RAMP CONSTRUCTION

DP

EXISTING GARDEN BED


LIFT PAVERS FOR RELAYING AT HIGHER LEVEL AS SHOWN DWG A 02.
LINE OF OVERHEAD BRIDGE CONNECTION OVER - FFL RL 22.20m

GROUND FLOOR WALKWAY


CBR RL 19.00m

OPENING

DP

Bin

D.P.

Bin

Bin

Bin

EXISTING R.L. 18.64

Notice Board
POWER DISTRIBUTION BOARD

1,000 2,100

PAVERS R.L. 18.65

024

REHANG DOOR TO OPEN OUT EXISTING PAVERS RAISED

BOOK HIRE
CPT 28.55m2
DOOR

ENTRY
SV 10.60m2

WINDOW

DOORS

WINDOW

REMOVE EXISTING SEAT

RAISE LEVEL OF EXISTING SEAT

REMOVE EXISTING SEAT


REMOVE EXISTING WALL AND DOOR, MAKE GOOD. PREPARE SURFACES FOR RETILING FLOOR AND WALLS

EXISTING R.L. 18.50

G27 WC

EXISTING R.L. 18.60

REMOVE PAVERS IN PREPARATION FOR RELAYING AT NEW LEVELS

Bin

NEW OPENING IN EXISTING WALL

Drawing:
Title:
LIBRARIAN OFFICE/ WORKROOM
CPT 35.70m2

CANTEEN

Ground Floor Demolition Plan


Scale: Date: Status: Drawn: Drawing No.:

EXISTING STAIRS
DOOR

1:100 30.08.08 CC SRB/LE 08:16-CC A-01


2/04/09

Compactus

Catalogues

OR WALKWAY

BR 8.50m

AV STORE
CPT 9.00m2

WINDOW