La Tropicana PART - A
ID

Task Name

LaTropicanaPartA
PackageFinalisation
BasementVentilationwork
MarbleFlooringandGraniteCountersWorks
PartAFinishes
Tower23

3
8
10
20
21

% Complete

25%
99%
0%
0%
25%
32%

Duration

568days
267days
0days
0days
568days
509days

Start

200212
250912
150413
290413
200212
200212

Finish

22
23

Brick Work

78%

216 days

01-08-12

10-04-13

InternalPlasterworks

78%

180days

080912

220413

24
25

Door Frame

26
27
28
29
30
31
41
43
44
45
46
59
62
64
66
77
80
82
83
89
95
98
100
101
102
107
113
116
118
120
125
131
134
136
138
143
149
152
153
154
156
161
167
170
171
172
173
174
179
185
188

BalconyRailingWork
BedroomCC
Counterslab
Basement1Level(Villa)
FFLMarkings
Brickwork
SandFilling
GroundFloor
FishWiretest
PlumbingworksKitchen+Toilet
POPonwalls&Ceilings
WaterProofingKitchen+toilet
Firstfloor
PlumbingworksKitchen+Toilet
WaterProofingKitchen+toilet
SunkenFilling
SecondFloor
PlumbingworksKitchen+Toilet
WaterProofingKitchen+toilet
Watersupplypiping
PlumbingWorksShafts
Thirdfloor
PlumbingworksKitchen+Toilet
WaterProofingKitchen+toilet
Watersupplypiping
SunkenFilling
PlumbingWorksShafts
FourthFloor
PlumbingworksKitchen+Toilet
WaterProofingKitchen+toilet
SunkenFilling
PlumbingWorksShafts
FifthFloor
PlumbingworksKitchen+Toilet
WaterProofingKitchen+toilet
SunkenFilling
PlumbingWorksShafts
SixthFloor
PlumbingworksKitchen+Toilet
POPonwalls&Ceilings
WaterProofingKitchen+toilet
SunkenFilling
PlumbingWorksShafts
SeventhFloor
PlumbingworksKitchen+Toilet
POPonwalls&Ceilings
WaterProofingKitchen+toilet
Watersupplypiping
SunkenFilling
PlumbingWorksShafts
EighthFloor
PlumbingworksKitchen+Toilet

Masters Developement Management (I) Pvt. Ltd.

tr 1, 2012
Feb
Mar

Apr

Qtr 2, 2012
May
Jun

Jul

Qtr 3, 2012
Aug
Sep

Oct

Qtr 4, 2012
Nov
Dec

Jan

Qtr 1, 2013
Feb
Mar

Apr

Qtr 2, 2013
May
Jun

Jul

Qtr 3, 2013
Aug
Sep

Oct

Qtr 4, 2013
Nov
Dec

161213
050813
150413
290413
161213
081013

75%

160 days

03-09-12

19-04-13

35%
62%
0%
6%
0%
25%
0%
1%
0%
0%
0%
0%
32%
75%
0%
0%
34%
75%
0%
80%
0%
38%
75%
0%
40%
0%
0%
39%
73%
0%
0%
0%
40%
80%
0%
0%
0%
25%
75%
0%
0%
0%
0%
23%
75%
0%
0%
50%
0%
0%
29%
50%

80days
40days
30days
114days
3days
22days
10days
263days
5days
15days
20days
8days
266days
54days
8days
7days
468days
50days
8days
8days
10days
272days
95days
8days
8days
8days
10days
275days
78days
8days
7days
10days
224days
75days
8days
7days
10days
229days
80days
20days
8days
7days
10days
233days
65days
20days
8days
8days
7days
10days
291days
75days

071112
191112
300313
250213
290313
250213
170413
151012
030413
020413
170413
260413
101012
300113
090413
290313
200212
040213
020413
200212
270413
121012
141212
060413
221212
100413
220413
131012
050113
150413
130413
160413
151212
090113
120413
150413
100413
151212
140113
280313
250413
220413
040413
151212
180113
030413
300413
291212
200413
290313
121012
210113

300513
030513
030513
050713
010413
120413
270413
170813
080413
180413
090513
040513
160813
010413
170413
050413
200813
010413
100413
090413
080513
260813
030413
150413
170413
180413
020513
300813
050413
230413
200413
260413
030913
050413
200413
220413
200413
090913
160413
190413
030513
290413
150413
130913
030413
250413
080513
090513
270413
090413
170913
170413
1 of 9

28 Mar 13

La Tropicana PART - A
ID
189
192
197
203
205
206
221
224
225
242
243
246
247
248
249
250
254
255
260
261
264
266
267
268
269
270
271
273
274
275
283
287
288
289
290
291
292
293
294
295
296
297
298
299
300
301
308
309
313
314
315
316
317
319
327
328
329
335
337
345
346

Task Name

% Complete

POPonwalls&Ceilings
SunkenFilling
PlumbingWorksShafts
NinthFloor
FishWiretest
PlumbingworksKitchen+Toilet
TenthFloor
PlumbingworksKitchen+Toilet
POPonwalls&Ceilings
CommonArea
Mumties,MachineRooms(Brickwork,Plaster&o
StaircaseRailing
Lobbies
Lifts(2P+1S)
InternalLighting&Whitewashing
LiftLeadTime
VillaLift
InternalLighting&Whitewashing
ExternalPlaster
PergolasinElevation
Tower1
BalconyRailingWork
Door Frame

BedroomCC
Counterslab
Basement1Level(Villa)
FFLMarkings
SandFilling
FlooringPCC
Internal&ExternalPlaster
GroundFloor
POPonwalls&Ceilings
WaterProofingKitchen+toilet
Watersupplypiping
SunkenFilling
CounterMarble
Tilingworks(Floor&Dado)Toilet
FlooringandDadoKitchen&FlooringBalconies
FlooringLiving&DiningRoom
PlumbingWorksShafts
FloorPolishingPreliminary
1stCoatPaint+1stCoatWoodenpolish
MaindoorShutter&Lock
BalanceDoorshutters+Windows
ElectricalWiring,Swicthes&DB
Firstfloor
SunkenFilling
CounterMarble
PlumbingWorksShafts
FloorPolishingPreliminary
1stCoatPaint+1stCoatWoodenpolish
MaindoorShutter&Lock
BalanceDoorshutters+Windows
SecondFloor
CounterMarble
Tilingworks(Floor&Dado)Toilet
FlooringandDadoKitchen&FlooringBalconies
BalanceDoorshutters+Windows
Thirdfloor
CounterMarble
Tilingworks(Floor&Dado)Toilet

Masters Developement Management (I) Pvt. Ltd.

Duration

Start

170413
290413
230313
050313
030413
020413
050313
080413
110413
150113
080413
150113
010413
100313
300313
100313
300313
300313
011012
051212
010812
011112

Finish

0%
0%
0%
0%
0%
0%
0%
0%
0%
16%
60%
26%
0%
0%
0%
0%
0%
0%
65%
95%
58%
75%

20days
7days
10days
172days
7days
12days
176days
25days
20days
217days
30days
40days
40days
165days
30days
90days
117days
30days
140days
60days
353days
155days

95%

225 days

01-08-12

20-04-13

85%
45days
25%
125days
7%
149days
0%
4days
0%
7days
0%
10days
0%
7days
65% 227.5days
90%
20days
62%
130days
60%
100days
60%
105days
60%
5days
50%
10days
50%
14days
50%
25days
80%
28days
50%
20days
50%
12days
50%
110days
80%
5days
50%
5days
62%
197days
0%
50days
0%
5days
80%
46days
50%
20days
50%
90days
0%
7days
0%
10days
83%
246days
50%
20days
50%
40days
50%
14days
50%
30days
69% 173.7days
60%
3days
50%
3days

181012
111212
251212
020413
030413
110413
230413
260912
221212
061112
061212
061212
201012
201012
251012
301012
280113
121112
131112
151112
101112
251112
051012
120213
240413
250113
271012
141112
220413
300413
290912
290912
131012
181012
151012
011112
100113
150113

050413
040513
150613
050413
100413
220413
300413
190613
050413
050413
010413
060413
080513
150513
230513
280513
080413
030613
080613
140613
150613
190613
220513
090413
290413
080413
050413
170413
290413
100513
130713
250513
240613
130713
020413
220513
100513
150513

tr 1, 2012
Feb
Mar

Apr

Qtr 2, 2012
May
Jun

Jul

Qtr 3, 2012
Aug
Sep

Oct

Qtr 4, 2012
Nov
Dec

Jan

Qtr 1, 2013
Feb
Mar

Apr

Qtr 2, 2013
May
Jun

Jul

Qtr 3, 2013
Aug
Sep

Oct

Qtr 4, 2013
Nov
Dec

090513
060513
030413
200913
100413
150413
250913
060513
030513
250913
110513
190913
160513
180913
030513
210613
130813
030513
060513
130513
180913
300413

2 of 9

28 Mar 13

La Tropicana PART - A
ID
347
350
351
352
353
355
368
369
370
371
373
386
387
388
389
391
404
405
409
422
427
440
445
448
449
451
452
456
458
459
460
463
466
467
468
470
471
484
486
487
488
490
492
496
498
504
506

Task Name

% Complete

FlooringandDadoKitchen&FlooringBalconies
FloorPolishingPreliminary
1stCoatPaint+1stCoatWoodenpolish
MaindoorShutter&Lock
BalanceDoorshutters+Windows
FourthFloor
FloorPolishingPreliminary
1stCoatPaint+1stCoatWoodenpolish
MaindoorShutter&Lock
BalanceDoorshutters+Windows
FifthFloor
FloorPolishingPreliminary
1stCoatPaint+1stCoatWoodenpolish
MaindoorShutter&Lock
BalanceDoorshutters+Windows
SixthFloor
FloorPolishingPreliminary
1stCoatPaint+1stCoatWoodenpolish
SeventhFloor
FloorPolishingPreliminary
EighthFloor
FloorPolishingPreliminary
NinthFloor
PlumbingworksKitchen+Toilet
POPonwalls&Ceilings
Watersupplypiping
SunkenFilling
FlooringLiving&DiningRoom
FloorPolishingPreliminary
1stCoatPaint+1stCoatWoodenpolish
MaindoorShutter&Lock
TenthFloor
PlumbingworksKitchen+Toilet
POPonwalls&Ceilings
WaterProofingKitchen+toilet
Watersupplypiping
SunkenFilling
CommonArea
Terrace(Waterproofing&Flooring)
StaircaseFlooring
StaircaseRailing
Lifts(2P+1S)
LiftLeadTime
VillaLift
LiftLeadTime
ExternalPaint(incl.Pergolas)
Tower2

Duration

50%
0%
0%
0%
0%
65%
0%
0%
0%
0%
57%
0%
0%
0%
0%
59%
0%
0%
70%
0%
64%
0%
41%
85%
75%
60%
0%
50%
0%
0%
0%
43%
75%
0%
0%
0%
25%
50%
40%
56%
44%
0%
0%
0%
0%
10%
22%

5days
25days
12days
7days
10days
278days
20days
12days
7days
10days
285days
20days
12days
7days
10days
285days
20days
12days
291days
15days
298days
15days
199days
75days
10days
16days
7days
3days
20days
12days
7days
210days
75days
10days
8days
8days
7days
190days
30days
40days
82days
256days
90days
196days
60days
50days
383days

Start

150113
120313
020413
130413
220413
010812
120313
290313
120413
200413
010812
180313
040413
180413
260413
010812
100413
260413
010812
220413
010812
240413
051212
150113
010413
150213
270313
150213
250313
110413
250413
051212
150113
270313
090413
150413
140313
281212
280113
150113
150213
231112
100313
231112
100313
100413
010812

Finish

507
508

Brick Work

91%

212 days

01-08-12

05-04-13

InternalPlasterworks

78%

20days

191112

300413

509
510

Door Frame

66%

220 days

01-08-12

20-04-13

61%
113days
78%
30days
20% 168.09days
0%
4days
0%
7days
0%
10days
13%
7days
4%
232days
0%
7days
0%
12days
0%
20days

261012
061012
121212
020413
130413
220413
150313
301112
010413
130413
200413

100613
060513
260613
050413
200413
020513
100513
280813
080413
260413
130513

511
513
514
516
517
518
526
528
529
530

BalconyRailingWork
BedroomCC
Basement1Level(Villa)
FFLMarkings
SandFilling
FlooringPCC
Internal&ExternalPlaster
GroundFloor
FishWiretest
PlumbingworksKitchen+Toilet
POPonwalls&Ceilings

Masters Developement Management (I) Pvt. Ltd.

tr 1, 2012
Feb
Mar

Apr

Qtr 2, 2012
May
Jun

Jul

Qtr 3, 2012
Aug
Sep

Oct

Qtr 4, 2012
Nov
Dec

Jan

Qtr 1, 2013
Feb
Mar

Apr

Qtr 2, 2013
May
Jun

Jul

Qtr 3, 2013
Aug
Sep

Oct

Qtr 4, 2013
Nov
Dec

220513
090413
150413
200413
020513
210613
030413
110413
190413
010513
290613
090413
170413
250413
070513
290613
020513
090513
060713
080513
150713
100513
240713
110413
110413
210513
030413
060413
160413
240413
020513
060813
110413
060413
170413
230413
240413
060813
200413
250713
200513
180913
210613
090713
170513
020713
241013

3 of 9

28 Mar 13

La Tropicana PART - A
ID
531
532
544
546
547
548
549
562
565
567
568
580
583
584
585
586
598
600
601
602
603
604
605
616
618
619
620
621
622
634
636
637
639
640
652
670
688
706
727
731
733
734
735
739
740
741
745
749

Task Name

% Complete

WaterProofingKitchen+toilet
Watersupplypiping
Firstfloor
FishWiretest
PlumbingworksKitchen+Toilet
POPonwalls&Ceilings
WaterProofingKitchen+toilet
SecondFloor
PlumbingworksKitchen+Toilet
WaterProofingKitchen+toilet
Watersupplypiping
Thirdfloor
PlumbingworksKitchen+Toilet
POPonwalls&Ceilings
WaterProofingKitchen+toilet
Watersupplypiping
FourthFloor
FishWiretest
PlumbingworksKitchen+Toilet
POPonwalls&Ceilings
WaterProofingKitchen+toilet
Watersupplypiping
SunkenFilling
FifthFloor
FishWiretest
PlumbingworksKitchen+Toilet
POPonwalls&Ceilings
WaterProofingKitchen+toilet
Watersupplypiping
SixthFloor
FishWiretest
PlumbingworksKitchen+Toilet
WaterProofingKitchen+toilet
Watersupplypiping
SeventhFloor
EighthFloor
NinthFloor
TenthFloor
CommonArea
StaircaseRailing
Lifts(2P+1S)
InternalLighting&Whitewashing
LiftLeadTime
VillaLift
InternalLighting&Whitewashing
LiftLeadTime
ExternalPlaster
Tower21

Duration

0%
8days
0%
8days
5%
229days
0%
7days
0%
12days
0%
20days
0%
8days
19%
237days
0%
12days
0%
8days
0%
8days
24%
216days
0%
12days
38%
20days
0%
8days
0%
8days
4%
219days
0%
7days
0%
12days
0%
20days
0%
8days
0%
8days
0%
7days
6%
225days
0%
6days
0%
12days
0%
20days
0%
8days
0%
8days
4%
190days
0%
7days
0%
12days
0%
8days
0%
8days
2%
195days
4%
198days
0%
188days
0%
191days
42% 218.1days
33%
30days
0%
165days
0%
30days
0%
90days
0%
110days
0%
30days
0%
60days
61%
20days
15%
392days

Start

230413
290413
291112
010413
060413
200413
240413
291112
090413
170413
260413
291212
020413
160313
160413
220413
311212
250313
090413
100413
180413
240413
270413
311212
290313
150413
080413
240413
300413
150213
190413
130413
230413
290413
150213
150213
040313
050313
241212
250113
100313
080413
100313
100313
080413
100313
011012
010812

Finish

750
751

Brick work

70%

216 days

01-08-12

10-04-13

InternalPlasterworks

63%

20days

241112

300413

752
753

Door Frame

52%

200 days

01-08-12

22-04-13

50%
58%
0%
15%
5%
0%
0%
0%
0%
0%

77days
40days
30days
115days
2days
7days
10days
131days
7days
12days

071112
191112
250413
250213
270213
080413
180413
030413
030413
090413

050613
110513
290513
060713
030413
150413
290413
030913
100413
220413

754
755
756
757
759
760
769
770
772

BalconyRailingWork
BedroomCC
Counterslab
Basement1Level(Villa)
FFLMarkings
SandFilling
FlooringPCC
GroundFloor
FFLMarkings
PlumbingworksKitchen+Toilet

Masters Developement Management (I) Pvt. Ltd.

tr 1, 2012
Feb
Mar

Apr

Qtr 2, 2012
May
Jun

Jul

Qtr 3, 2012
Aug
Sep

Oct

Qtr 4, 2012
Nov
Dec

Jan

Qtr 1, 2013
Feb
Mar

Apr

Qtr 2, 2013
May
Jun

Jul

Qtr 3, 2013
Aug
Sep

Oct

Qtr 4, 2013
Nov
Dec

010513
070513
230813
080413
190413
130513
020513
020913
220413
250413
040513
070913
150413
080413
240413
300413
120913
010413
220413
020513
260413
020513
040513
190913
040413
270413
300413
020513
080513
240913
260413
260413
010513
070513
300913
041013
091013
141013
050913
050913
180913
110513
210613
150713
110513
170513
200513
041113

4 of 9

28 Mar 13

La Tropicana PART - A
ID
774
775
776
787
789
790
791
792
793
794
805
807
808
810
811
812
823
825
826
828
829
830
841
844
846
847
848
859
861
862
864
865
866
877
879
880
881
882
883
884
895
897
898
900
901
902
913
915
916
918
919
920
931
933
934
936
937
938
949
952
954

Task Name

% Complete

WaterProofingKitchen+toilet
Watersupplypiping
SunkenFilling
Firstfloor
FishWiretest
PlumbingworksKitchen+Toilet
POPonwalls&Ceilings
WaterProofingKitchen+toilet
Watersupplypiping
SunkenFilling
SecondFloor
FishWiretest
PlumbingworksKitchen+Toilet
WaterProofingKitchen+toilet
Watersupplypiping
SunkenFilling
Thirdfloor
FishWiretest
PlumbingworksKitchen+Toilet
WaterProofingKitchen+toilet
Watersupplypiping
SunkenFilling
FourthFloor
PlumbingworksKitchen+Toilet
WaterProofingKitchen+toilet
Watersupplypiping
SunkenFilling
FifthFloor
FishWiretest
PlumbingworksKitchen+Toilet
WaterProofingKitchen+toilet
Watersupplypiping
SunkenFilling
SixthFloor
FishWiretest
PlumbingworksKitchen+Toilet
POPonwalls&Ceilings
WaterProofingKitchen+toilet
Watersupplypiping
SunkenFilling
SeventhFloor
FishWiretest
PlumbingworksKitchen+Toilet
WaterProofingKitchen+toilet
Watersupplypiping
SunkenFilling
EighthFloor
FishWiretest
PlumbingworksKitchen+Toilet
WaterProofingKitchen+toilet
Watersupplypiping
SunkenFilling
NinthFloor
FishWiretest
PlumbingworksKitchen+Toilet
WaterProofingKitchen+toilet
Watersupplypiping
SunkenFilling
TenthFloor
PlumbingworksKitchen+Toilet
WaterProofingKitchen+toilet

Masters Developement Management (I) Pvt. Ltd.

0%
0%
0%
6%
0%
75%
0%
0%
0%
0%
8%
0%
75%
0%
0%
0%
11%
0%
50%
0%
0%
0%
11%
50%
0%
0%
0%
12%
0%
50%
0%
0%
0%
15%
0%
75%
0%
0%
0%
0%
17%
0%
75%
0%
0%
0%
5%
0%
25%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%

Duration

8days
8days
7days
195days
5days
10days
20days
8days
8days
7days
185days
7days
12days
8days
8days
7days
192days
3days
30days
8days
8days
7days
192days
30days
8days
8days
7days
209days
7days
50days
8days
8days
7days
198days
7days
35days
20days
8days
8days
7days
201days
7days
45days
8days
8days
7days
203days
7days
30days
8days
8days
7days
185days
7days
15days
8days
8days
7days
169days
40days
8days

Start

180413
240413
270413
120113
080413
040413
250413
100413
160413
190413
200113
170413
060413
090413
150413
180413
250113
250413
250113
280313
030413
060413
290113
290113
010413
060413
100413
120113
290413
060213
300313
050413
090413
300113
100413
220213
260413
290313
040413
080413
300113
220413
220213
100413
160413
190413
300113
270413
060313
040413
100413
130413
230213
270413
040413
170413
230413
260413
150313
180313
290413

Finish

tr 1, 2012
Feb
Mar

Apr

Qtr 2, 2012
May
Jun

Jul

Qtr 3, 2012
Aug
Sep

Oct

Qtr 4, 2012
Nov
Dec

Jan

Qtr 1, 2013
Feb
Mar

Apr

Qtr 2, 2013
May
Jun

Jul

Qtr 3, 2013
Aug
Sep

Oct

Qtr 4, 2013
Nov
Dec

260413
020513
040513
280813
120413
150413
170513
180413
240413
260413
240813
240413
190413
170413
230413
250413
060913
270413
010413
050413
110413
130413
090913
040413
090413
150413
170413
130913
060513
030413
080413
130413
160413
170913
170413
020413
180513
060413
120413
150413
200913
290413
130413
180413
240413
260413
230913
040513
080413
120413
180413
200413
260913
040513
200413
250413
010513
030513
280913
020513
070513
5 of 9

28 Mar 13

La Tropicana PART - A
ID
955
970
971
976
977
978
982
983
988
992

Task Name

% Complete

WaterproofingTerrace
CommonArea
Mumties,MachineRooms(Brickwork,Plaster&o
Lifts(2P+1S)
InternalLighting&Whitewashing
LiftLeadTime
VillaLift
InternalLighting&Whitewashing
ExternalPlaster
Tower3

993
994

Brick Work

995
996

Door Frame

997
999
1000
1001
1002
1003
1004
1012
1014
1015
1016
1017
1018
1019
1030
1031
1033
1035
1036
1037
1048
1049
1051
1053
1054
1055
1066
1070
1084
1086
1087
1088
1089
1090
1091
1102
1105
1106
1107
1108
1109
1120
1122
1123
1124
1138
1140

InternalPlasterworks
BalconyRailingWork
BedroomCC
Basement1Level(Villa)
FFLMarkings
Brickwork
SandFilling
FlooringPCC
Internal&ExternalPlaster
GroundFloor
FishWiretest
PlumbingworksKitchen+Toilet
POPonwalls&Ceilings
WaterProofingKitchen+toilet
Watersupplypiping
SunkenFilling
Firstfloor
FFLMarkings
PlumbingworksKitchen+Toilet
WaterProofingKitchen+toilet
Watersupplypiping
SunkenFilling
SecondFloor
FFLMarkings
PlumbingworksKitchen+Toilet
WaterProofingKitchen+toilet
Watersupplypiping
SunkenFilling
Thirdfloor
POPonwalls&Ceilings
FourthFloor
FishWiretest
PlumbingworksKitchen+Toilet
POPonwalls&Ceilings
WaterProofingKitchen+toilet
Watersupplypiping
SunkenFilling
FifthFloor
PlumbingworksKitchen+Toilet
POPonwalls&Ceilings
WaterProofingKitchen+toilet
Watersupplypiping
SunkenFilling
SixthFloor
FishWiretest
PlumbingworksKitchen+Toilet
POPonwalls&Ceilings
SeventhFloor
FishWiretest

Masters Developement Management (I) Pvt. Ltd.

Duration

Start

290413
280313
280313
100313
080413
100313
080413
080413
010812
010812

Finish

0%
0%
0%
0%
0%
0%
0%
0%
61%
9%

8days
169days
30days
151days
30days
90days
132days
30days
20days
398days

85%

225 days

01-08-12

20-04-13

0%

40days

100413

250513

tr 1, 2012
Feb
Mar

Apr

Qtr 2, 2012
May
Jun

Jul

Qtr 3, 2012
Aug
Sep

Oct

Qtr 4, 2012
Nov
Dec

Jan

Qtr 1, 2013
Feb
Mar

Apr

Qtr 2, 2013
May
Jun

Jul

Qtr 3, 2013
Aug
Sep

Oct

Qtr 4, 2013
Nov
Dec

070513
121013
010513
020913
110513
210613
090913
110513
290513
111113

0%

60 days

27-04-13

05-07-13

0%
0%
27%
0%
50%
0%
0%
10%
2%
0%
0%
0%
0%
0%
0%
2%
10%
0%
0%
0%
0%
2%
12%
0%
0%
0%
0%
0%
0%
3%
0%
0%
0%
0%
0%
0%
2%
0%
0%
0%
0%
0%
2%
0%
0%
0%
2%
0%

125days
50days
166days
4days
75days
10days
10days
10days
187days
7days
10days
20days
8days
8days
7days
191days
35days
12days
8days
8days
7days
180days
30days
12days
8days
8days
7days
186days
20days
243days
7days
12days
20days
8days
8days
7days
242days
12days
20days
8days
8days
7days
249days
7days
12days
20days
234days
7days

241112
100413
241212
040413
241212
160413
270413
150113
050213
120413
030413
240413
080413
100413
110413
110213
110213
030413
050413
110413
150413
270213
270213
130413
160413
220413
250413
250213
080413
231212
010413
020413
170413
110413
170413
190413
271212
110413
190313
200413
260413
300413
231212
120413
250413
290413
140113
080413

180413
060613
040713
080413
150413
260413
080513
180513
100913
200413
130413
170513
160413
180413
180413
200913
130413
160413
130413
190413
220413
240913
080413
260413
240413
300413
020513
280913
300413
041013
080413
150413
090513
190413
250413
260413
071013
240413
100413
290413
040513
070513
111013
190413
080513
210513
151013
150413
6 of 9

28 Mar 13

La Tropicana PART - A
ID
1142
1156
1158
1160
1174
1176
1192
1213
1217
1218
1219
1221
1223
1224
1231
1235

Task Name

% Complete

POPonwalls&Ceilings
EighthFloor
FishWiretest
POPonwalls&Ceilings
NinthFloor
FishWiretest
TenthFloor
CommonArea
StaircaseRailing
Lobbies
Lifts(2P+1S)
LiftLeadTime
CarInstallation
Testing&Commissioning
ExternalPlaster
Tower4

Duration

0%
3%
0%
0%
0%
0%
0%
8%
40%
0%
0%
0%
0%
0%
61%
8%

20days
239days
7days
20days
240days
7days
231days
263days
40days
40days
110days
90days
25days
20days
20days
413days

Start

240413
110113
080413
240413
140113
220413
020213
291212
300113
220313
150213
100313
210313
190413
061012
010812

Finish

1236
1237

Brickwork

45%

233 days

01-08-12

30-04-13

InternalPlasterworks

15%

40days

250113

290513

1238
1239

Door Frame

1240
1242
1243
1244
1255
1257
1258
1260
1273
1274
1291
1293
1294
1295
1296
1297
1298
1309
1311
1312
1313
1314
1315
1316
1327
1329
1330
1331
1345
1347
1348
1349
1363
1365
1367
1381
1383
1385
1399
1401
1417

BalconyRailingWork
BedroomCC
Basement1Level
FFLMarkings
Brickwork
GroundFloor
FishWiretest
PlumbingworksKitchen+Toilet
WaterProofingKitchen+toilet
Firstfloor
FFLMarkings
SecondFloor
FishWiretest
PlumbingworksKitchen+Toilet
POPonwalls&Ceilings
WaterProofingKitchen+toilet
Watersupplypiping
SunkenFilling
Thirdfloor
FishWiretest
PlumbingworksKitchen+Toilet
POPonwalls&Ceilings
WaterProofingKitchen+toilet
Watersupplypiping
SunkenFilling
FourthFloor
FishWiretest
PlumbingworksKitchen+Toilet
POPonwalls&Ceilings
FifthFloor
FishWiretest
PlumbingworksKitchen+Toilet
POPonwalls&Ceilings
SixthFloor
FishWiretest
POPonwalls&Ceilings
SeventhFloor
FishWiretest
POPonwalls&Ceilings
EighthFloor
FishWiretest
NinthFloor

Masters Developement Management (I) Pvt. Ltd.

0%

65 days

20-02-13

04-05-13

35%
0%
3%
0%
25%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
3%

184days
40days
122days
4days
10days
139days
7days
12days
8days
114days
6days
219days
7days
12days
20days
8days
8days
7days
223days
7days
12days
20days
8days
8days
7days
226days
7days
12days
20days
229days
7days
12days
20days
232days
7days
20days
235days
3days
20days
242days
7days
205days

171112
050413
230213
150413
230213
260313
260413
180413
270413
180413
180413
201212
300313
100413
160413
120413
180413
220413
201212
030413
290313
190413
080413
130413
170413
201212
050413
220413
220413
211212
050413
260413
220413
221212
010413
170413
231212
010413
120413
251212
040413
120213

200613
210513
130713
180413
300413
040913
030513
010513
060513
290813
240413
020913
060413
230413
080513
200413
260413
290413
060913
100413
110413
110513
160413
220413
240413
100913
120413
040513
140513
140913
120413
090513
140513
190913
080413
090513
240913
030413
040513
041013
110413
091013

0%
0%
0%
0%
0%
0%

2%
0%
0%
0%

1%
0%
0%
0%

1%
0%
0%

1%
0%
0%

2%
0%

2%

tr 1, 2012
Feb
Mar

Apr

Qtr 2, 2012
May
Jun

Jul

Qtr 3, 2012
Aug
Sep

Oct

Qtr 4, 2012
Nov
Dec

Jan

Qtr 1, 2013
Feb
Mar

Apr

Qtr 2, 2013
May
Jun

Jul

Qtr 3, 2013
Aug
Sep

Oct

Qtr 4, 2013
Nov
Dec

160513
181013
150413
160513
221013
290413
301013
021113
261013
070513
210613
210613
180413
110513
290613
281113

7 of 9

28 Mar 13

La Tropicana PART - A
ID
1419
1435
1436
1456
1457
1478

Task Name

% Complete

FishWiretest
TenthFloor
FFLMarkings
CommonArea
Mumties,MachineRooms(Brickwork,Plaster&o
Tower5

0%

Duration

9%

7days
163days
3days
182days
40days
388days

0%
0%

0%
0%

Start

240413
110413
110413
110413
110413
010812

Finish

1479
1480

Brickwork

86%

219 days

01-08-12

13-04-13

InternalPlasterworks

65%

35days

010812

140513

1481
1482

Door Frame

1483
1485
1486
1487
1488
1489
1498
1499
1500
1501
1502
1503
1504
1505
1516
1518
1519
1520
1521
1522
1523
1534
1536
1537
1538
1539
1540
1541
1552
1555
1557
1558
1559
1570
1572
1573
1575
1576
1588
1590
1591
1593
1606
1608
1609
1624
1626
1627
1629
1630
1631

BalconyRailingWork
BedroomCC
Basement1Level(Villa)
FFLMarkings
Brickwork
SandFilling
FlooringPCC
GroundFloor
FFLMarkings
FishWiretest
PlumbingworksKitchen+Toilet
POPonwalls&Ceilings
WaterProofingKitchen+toilet
Watersupplypiping
SunkenFilling
Firstfloor
FishWiretest
PlumbingworksKitchen+Toilet
POPonwalls&Ceilings
WaterProofingKitchen+toilet
Watersupplypiping
SunkenFilling
SecondFloor
FishWiretest
PlumbingworksKitchen+Toilet
POPonwalls&Ceilings
WaterProofingKitchen+toilet
Watersupplypiping
SunkenFilling
Thirdfloor
PlumbingworksKitchen+Toilet
WaterProofingKitchen+toilet
Watersupplypiping
SunkenFilling
FourthFloor
FishWiretest
PlumbingworksKitchen+Toilet
WaterProofingKitchen+toilet
Watersupplypiping
FifthFloor
FishWiretest
PlumbingworksKitchen+Toilet
WaterProofingKitchen+toilet
SixthFloor
FishWiretest
PlumbingworksKitchen+Toilet
SeventhFloor
FishWiretest
PlumbingworksKitchen+Toilet
WaterProofingKitchen+toilet
Watersupplypiping
SunkenFilling

Masters Developement Management (I) Pvt. Ltd.

8%

220 days

01-08-12

29-04-13

65%
15%
0%

40days
40days
74days
2days
10days
7days
10days
135days
3days
7days
12days
20days
8days
8days
7days
211days
7days
12days
20days
8days
8days
7days
213days
4days
12days
20days
8days
8days
7days
216days
12days
8days
8days
7days
217days
3days
12days
8days
8days
222days
4days
12days
8days
223days
7days
12days
262days
7days
12days
8days
8days
7days

291212
060313
090413
190413
090413
200413
290413
290313
030413
290313
090413
150413
180413
240413
270413
251212
290313
030413
200413
050413
110413
150413
241212
020413
020413
150413
040413
100413
130413
251212
030413
120413
180413
220413
281212
180413
120413
220413
270413
261212
020413
160413
250413
291212
080413
250413
201112
110413
090413
180413
240413
270413

100613
210613
030713
200413
190413
270413
090513
030913
050413
050413
220413
070513
260413
020513
040513
280813
050413
160413
130513
130413
190413
220413
290813
050413
150413
070513
120413
180413
200413
030913
160413
200413
260413
290413
070913
200413
250413
300413
060513
110913
050413
290413
030513
160913
150413
080513
210913
180413
220413
260413
020513
040513

0%
0%
0%
0%

0%
0%
0%
0%
0%
0%
0%
0%

2%
0%
0%
0%
0%
0%
0%

2%
0%
0%
0%
0%
0%
0%

1%
0%
0%
0%
0%

2%
0%
0%
0%
0%

1%
0%
0%
0%

1%
0%
0%

0%
0%
0%
0%
0%
0%

tr 1, 2012
Feb
Mar

Apr

Qtr 2, 2012
May
Jun

Jul

Qtr 3, 2012
Aug
Sep

Oct

Qtr 4, 2012
Nov
Dec

Jan

Qtr 1, 2013
Feb
Mar

Apr

Qtr 2, 2013
May
Jun

Jul

Qtr 3, 2013
Aug
Sep

Oct

Qtr 4, 2013
Nov
Dec

010513
191013
130413
111113
270513
301013

8 of 9

28 Mar 13

La Tropicana PART - A
ID
1642
1644
1660
1662
1678
1679
1699
1700
1705
1706
1707
1711
1712
1717
1721
1722
1723
1724
1726
1735
1736
1738
1742
1743
1744
1745
1746
1753
1754
1755
1756
1757
1758
1759

Task Name

EighthFloor
FishWiretest
NinthFloor
FishWiretest
TenthFloor
FFLMarkings
CommonArea
Mumties,MachineRooms(Brickwork,Plaster&o
Lifts(2P+1S)
InternalLighting&Whitewashing
LiftLeadTime
VillaLift
InternalLighting&Whitewashing
ExternalPlaster
Nontowerarea
BalanceStructureWorks
DrainBrickWork
MEPRoomsBrickwork,Plaster
PCC
MEPRooms(incl.CivilWorks)
WaterTank
PumpRoom
ExternalDevelopmentWorks
PeripherialWorks
BoundaryWall
ExternalSewerage
StormWaterDrainage
AboveBasementWorks
Rendering
Planters
PedestrianBridge
ChangingRoom,ToiletsStructure
Backfilling
SwimmingPoolMechanicalWorks

Masters Developement Management (I) Pvt. Ltd.

% Complete

4%
0%

2%
0%

0%
0%

3%
40%

0%
0%

0%
0%
0%

50%
71%
68%
100%
100%
100%
55%
100%
100%
5%
9%
14%
38%
38%
1%
5%
0%
0%
0%
0%
0%

Duration

219days
7days
218days
7days
149days
3days
200days
10days
165days
30days
90days
125days
30days
20days
280days
133days
85days
90days
80days
130days
50days
70days
235days
235days
90days
40days
40days
195days
60days
50days
30days
40days
80days
60days

Start

150113
060413
220113
150413
170413
170413
230213
230213
100313
220413
100313
220413
220413
011012
271112
271112
120213
010113
020113
040413
040413
160413
270213
270213
010313
270213
270213
120313
120313
220413
160413
040413
220413
160413

Finish

tr 1, 2012
Feb
Mar

Apr

Qtr 2, 2012
May
Jun

Jul

Qtr 3, 2012
Aug
Sep

Oct

Qtr 4, 2012
Nov
Dec

Jan

Qtr 1, 2013
Feb
Mar

Apr

Qtr 2, 2013
May
Jun

Jul

Qtr 3, 2013
Aug
Sep

Oct

Qtr 4, 2013
Nov
Dec

270913
130413
041013
220413
091013
190413
151013
060613
180913
250513
210613
140913
250513
240613
211013
300413
200513
150413
040413
030913
310513
050713
281113
281113
010813
120413
120413
261013
090713
180613
200513
200513
230713
240613

9 of 9