Professional Documents
Culture Documents
100 m2 12.5000 h/m2 UNIDAD hh hh hh hh hh CANTIDAD 0.0160 0.1600 0.0800 0.6400 0.0800 COSTO 18.14 15.12 13.14 11.84 17.39 TOTAL COSTO 22.50 14.45 5.70 TOTAL COSTO 11.70 57.00 5.65 TOTAL COSTO 30.50 12.73 TOTAL TOTAL P.U. SUBTOTAL 0.29 2.42 1.05 7.58 1.39 12.73 SUBTOTAL 14.63 2.19 0.05 16.86 SUBTOTAL 0.35 0.06 0.01 0.42 SUBTOTAL 30.50 0.64 31.14 61.15
UNIDAD m3 bls m3
COMB. Y LUB. GASOLINA 84 OCTANOS (GRIFO LIMA) ACEITE MOTOR GASOLINA SAE 30W GRASA MULTIPLE EP
UNIDAD hm % MO
ANALISIS DE COSTO UNITARIO PROYECTO: DESCRIPCION: RENDIMIENTO EN 8 HRS: APORTE: MANO DE OBRA CAPATAZ OPERARIO OFICIAL PEON OPERADOR EQUIPO LIVIANO EXAMEN PARCIAL
CONCRETO PREMEZCLADO F'c=100 Kg/cm2 PARA CIMIENTOS
m3 h/m3 CANTIDAD 0.0320 0.6400 0.3200 1.2800 0.3200 COSTO 18.14 15.12 13.14 11.84 16.33 TOTAL COSTO 185.00 TOTAL COSTO 5.53 34.84 TOTAL TOTAL P.U. SUBTOTAL 0.58 9.68 4.20 15.16 5.23 34.84 SUBTOTAL 190.55 190.55 SUBTOTAL 1.77 1.05 2.81 228.21
UNIDAD m3
CANTIDAD 1.0300
UNIDAD hm % MO
ANALISIS DE COSTO UNITARIO PROYECTO: DESCRIPCION: RENDIMIENTO EN 8 HRS: APORTE: MANO DE OBRA CAPATAZ OPERARIO OFICIAL EXAMEN PARCIAL
ENCOF. Y DESENCOF. PARA SOBRECIMIENTOS
m2 h/m2 CANTIDAD 0.0500 0.5000 0.5000 COSTO 18.14 15.12 13.14 TOTAL COSTO 2.96 3.02 5.40 TOTAL COSTO 15.04 TOTAL TOTAL P.U. SUBTOTAL 0.91 7.56 6.57 15.04 SUBTOTAL 0.77 0.48 18.09 19.34 SUBTOTAL 0.90 0.90 35.28
MATERIALES ALAMBRE NEGRO RECOCIDO BWG N 8 CLAVO C/CABEZA P/CONSTRUCCION D. PROMEDIO MADERA TORNILLO
UNIDAD KG KG p2
UNIDAD % MO
CANTIDAD 0.0300
ANALISIS DE COSTO UNITARIO PROYECTO: DESCRIPCION: RENDIMIENTO EN 8 HRS: APORTE: MANO DE OBRA CAPATAZ OPERARIO PEON OPERADOR EQUIPO EXAMEN PARCIAL
CONCRETO EN FALSOPISO MEZCLA 1:8 E=4"
110 m2 13.7500 h/m2 UNIDAD CANTIDAD COSTO SUBTOTAL hh hh hh hh 0.0218 0.2182 0.5818 0.0727 18.14 15.12 11.84 17.39 TOTAL 0.40 3.30 6.89 1.26 11.85
UNIDAD CANTIDAD COSTO SUBTOTAL m3 p2 m3 0.1450 0.0600 0.0160 22.50 5.20 5.70 TOTAL 3.26 0.31 0.09 3.67
COMB. Y LUB. GASOLINA 84 OCTANOS (GRIFO LIMA) ACEITE MOTOR GASOLINA SAE 30W GRASA MULTIPLE EP
UNIDAD CANTIDAD COSTO SUBTOTAL gal gal lb 0.0273 0.0009 0.0018 11.70 57.00 5.65 TOTAL 0.32 0.05 0.01 0.38
UNIDAD CANTIDAD COSTO SUBTOTAL hm % MO 0.0727 0.0300 30.50 11.85 TOTAL 30.49 4.89 35.38 51.27
TOTAL P.U.
ANALISIS DE COSTO UNITARIO EXAMEN PARCIAL EXCAVACION DE ZANJAS 4.00 m3 0.5000 h/m3 UNIDAD hh hh CANTIDAD 0.2000 2.0000 COSTO 18.14 15.12 TOTAL COSTO 33.87 TOTAL TOTAL P.U. SUBTOTAL 3.63 30.24 33.87 SUBTOTAL 1.69 1.69 35.56
UNIDAD % MO
CANTIDAD 0.0500
ANALISIS DE COSTO UNITARIO EXAMEN PARCIAL CORTE MANUAL DE TERRENO 40.00 m2 5.0000 h/m2 UNIDAD hh hh CANTIDAD 0.2000 0.2000 COSTO 18.14 15.12 TOTAL COSTO 6.65 TOTAL TOTAL P.U. SUBTOTAL 3.63 3.02 6.65 SUBTOTAL 0.33 0.33 6.98
UNIDAD % MO
CANTIDAD 0.0500
ANALISIS DE COSTO UNITARIO PROYECTO: DESCRIPCION: RENDIMIENTO EN 8 HRS: APORTE: MANO DE OBRA CAPATAZ PEON EXAMEN PARCIAL ELIMINACION DESMONTE CON EQUIPO 345.00 m3 43.1250 h/m3 UNIDAD hh hh CANTIDAD 0.0023 0.0464 COSTO 18.14 11.84 TOTAL COSTO 195.15 153.62 TOTAL TOTAL P.U. SUBTOTAL 0.04 0.55 0.59 SUBTOTAL 18.11 3.56 21.67 22.27
UNIDAD hm hm
ANALISIS DE COSTO UNITARIO EXAMEN PARCIAL RELLENO CON MATERIAL PROPIO 7.00 m3 0.8750 h/m3 UNIDAD hh hh CANTIDAD 0.1143 1.1429 COSTO 18.14 11.84 TOTAL COSTO 15.61 TOTAL TOTAL P.U. SUBTOTAL 2.07 13.53 15.61 SUBTOTAL 0.78 0.78 16.39
UNIDAD % MO
CANTIDAD 0.0500
ANALISIS DE COSTO UNITARIO PROYECTO: DESCRIPCION: RENDIMIENTO EN 8 HRS: APORTE: MANO DE OBRA CAPATAZ OPERARIO PEON EXAMEN PARCIAL TRAZO Y REPLANTEO 300.00 m2 37.5000 h/m2 UNIDAD hh hh hh CANTIDAD 0.0027 0.0267 0.0533 COSTO 18.14 15.12 11.84 TOTAL COSTO 30.52 3.02 5.40 TOTAL COSTO 13.5 44.80 1.08 TOTAL TOTAL P.U. SUBTOTAL 0.05 0.40 0.63 1.08 SUBTOTAL 0.76 0.02 0.14 0.92 SUBTOTAL 0.00 0.02 0.03 0.06 2.06
UNIDAD bls KG P2
ANALISIS DE COSTO UNITARIO PROYECTO: DESCRIPCION: RENDIMIENTO EN 8 HRS: APORTE: MANO DE OBRA CAPATAZ OPERARIO PEON EXAMEN PARCIAL
TRAZO DE NIVELES Y REPLANTEO DURANTE EL PROCESO
m2 h/m2 CANTIDAD 0.0027 0.0267 0.0533 COSTO 18.14 15.12 11.84 TOTAL COSTO 30.52 3.02 TOTAL COSTO 13.5 44.80 1.08 TOTAL TOTAL P.U. SUBTOTAL 0.05 0.40 0.63 1.08 SUBTOTAL 0.76 0.02 0.78 SUBTOTAL 0.00 0.02 0.03 0.06 1.92
UNIDAD bls KG
PROYECTO: DESCRIPCION: RENDIMIENTO EN 8 HRS: APORTE: MANO DE OBRA CAPATAZ OPERARIO PEON
ANALISIS DE COSTO UNITARIO EXAMEN PARCIAL ZOCALO DE CERAMICO 20X20 4.00 m2 0.5000 h/m2 UNIDAD hh hh hh CANTIDAD 0.200000 2.000000 0.660000 COSTO 18.14 15.12 11.84 TOTAL COSTO 35.00 8.00 19.95 TOTAL COSTO 41.68 TOTAL TOTAL P.U. SUBTOTAL 3.63 30.24 7.81 41.68 SUBTOTAL 0.88 1.60 20.95 23.42 SUBTOTAL 2.08 2.08 67.19
UNIDAD m3 kg m2
UNIDAD % MO
CANTIDAD 0.0500
ANALISIS DE COSTO UNITARIO PROYECTO: DESCRIPCION: RENDIMIENTO EN 8 HRS: APORTE: MANO DE OBRA CAPATAZ OPERARIO PEON EXAMEN PARCIAL
ZOCALO DE CEMENTO SIMPLE MEZCLA CEMENTOARENA
m2 h/m2 CANTIDAD 0.057100 0.571400 0.382900 COSTO 18.14 15.12 11.84 TOTAL COSTO 35.00 14.45 3.02 5.40 5.70 TOTAL COSTO 14.21 TOTAL TOTAL P.U. SUBTOTAL 1.04 8.64 4.53 14.21 SUBTOTAL 0.74 2.70 0.09 2.81 0.03 6.37 SUBTOTAL 0.43 0.43 21.00
MATERIALES ARENA FINA CEMENTO PORTLAND TIPO I (BLS.:42.5 KG) CLAVO C/CABEZA P/CONSTRUCCION DE PROMEDIO MADERA ANDAMIAJE AGUA
UNIDAD m3 bls kg p2 m3
UNIDAD % MO
CANTIDAD 0.030000
ANALISIS DE COSTO UNITARIO PROYECTO: DESCRIPCION: RENDIMIENTO EN 8 HRS: APORTE: MANO DE OBRA CAPATAZ OPERARIO OFICIAL EXAMEN PARCIAL
PUERTA POSTERIOR CONTRAPLACADA DE 0.65 M DE ANCHO
m2 h/m2 CANTIDAD 0.666700 2.666700 2.666700 COSTO 18.14 15.12 13.14 TOTAL COSTO 3.02 8.60 33.00 1.00 22.70 TOTAL SUBTOTAL 12.09 40.32 35.04 87.45 SUBTOTAL 0.20 88.49 33.00 1.10 2.33 125.13
MATERIALES CLAVO C/CABEZA P/CONSTRUCCCION D. PROMEDIO MADERA CEDRO TRIPLAY LUPUNA 4X 8 X 6mm LIJA P/MADERA COLA SINTETICA
UNIDAD hm hm % MO
ANALISIS DE COSTO UNITARIO PROYECTO: DESCRIPCION: RENDIMIENTO EN 8 HRS: APORTE: MANO DE OBRA CAPATAZ OPERARIO OFICIAL EXAMEN PARCIAL
PUERTAS CONTRAPLACADAS DE 0.65 M DE ANCHO
m2 h/m2 CANTIDAD 0.666700 2.666700 2.666700 COSTO 18.14 15.12 13.14 TOTAL COSTO 3.02 8.60 21.75 1.00 22.70 TOTAL COSTO 4.29 3.91 87.45 TOTAL SUBTOTAL 12.09 40.32 35.04 87.45 SUBTOTAL 0.20 88.49 21.75 1.10 2.33 113.88 SUBTOTAL 2.29 2.09 2.62 7.00 208.33
MATERIALES CLAVO C/CABEZA P/CONSTRUCCCION D. PROMEDIO MADERA CEDRO TRIPLAY LUPUNA 4X 8 X 4mm LIJA P/MADERA COLA SINTETICA
UNIDAD hm hm % MO
TOTAL P.U.
ANALISIS DE COSTO UNITARIO PROYECTO: DESCRIPCION: RENDIMIENTO EN 8 HRS: APORTE: MANO DE OBRA CAPATAZ OPERARIO OFICIAL EXAMEN PARCIAL RED DE DISTRIBUCION TUBERIA DE 1/2" PVC-SAP 25.00 pza 3.1250 h/pza UNIDAD hh hh hh CANTIDAD 0.032000 0.320000 0.320000 COSTO 18.14 15.12 13.14 TOTAL COSTO 137.10 6.19 TOTAL COSTO 9.62 TOTAL TOTAL P.U. SUBTOTAL 0.58 4.84 4.20 9.62 SUBTOTAL 1.37 1.30 2.67 SUBTOTAL 0.29 0.29 12.58
MATERIALES PEGAMENTO P/TUBO PVC TUBO PVC AGUA S.P CLASE 10 " X 5m
UNIDAD % MO
CANTIDAD 0.030000
ANALISIS DE COSTO UNITARIO PROYECTO: DESCRIPCION: RENDIMIENTO EN 8 HRS: APORTE: MANO DE OBRA CAPATAZ OPERARIO OFICIAL EXAMEN PARCIAL SALIDA DE AGUA FRIA DE 1/2" 3.00 Pto 0.3750 h/pto UNIDAD hh hh hh CANTIDAD 0.266700 2.666700 1.333333 COSTO 18.14 15.12 13.14 TOTAL COSTO 139.92 6.19 0.96 1.23 TOTAL COSTO 62.68 TOTAL TOTAL P.U. SUBTOTAL 4.84 40.32 17.52 62.68 SUBTOTAL 4.20 2.55 1.92 1.23 9.90 SUBTOTAL 1.88 1.88 74.46
MATERIALES PEGAMENTO P/TUBO PVC TUBO PVC AGUA S.P CLASE 10 " X 5m CODO PVC AGUA DOBLE CAMPAA S.P. " X 90 TEE PVC AGUA S.P. "
UNIDAD % MO
CANTIDAD 0.030000
ANALISIS DE COSTO UNITARIO PROYECTO: DESCRIPCION: RENDIMIENTO EN 8 HRS: APORTE: MANO DE OBRA CAPATAZ OPERARIO OFICIAL EXAMEN PARCIAL VALVULAS DE COMPUERTA DE BRONCE DE 1/2" 6.00 pza 0.7500 h/pza UNIDAD hh hh hh CANTIDAD 0.133300 1.333300 0.666700 COSTO 18.14 15.12 13.14 TOTAL COSTO 1.16 7.64 1.40 22.76 TOTAL COSTO 31.34 TOTAL SUBTOTAL 2.42 20.16 8.76 31.34 SUBTOTAL 0.12 15.28 2.80 22.76 40.96 SUBTOTAL 0.71 0.71 73.00
MATERIALES CINTA TEFLON UNION UNIVERSAL ACERO GALV. " NIPLE ACERO GALV. TIPO ISO -" X 1" VALVULA COMPUERTA PESADA BRONCE 250 LB "
UNIDAD % MO
CANTIDAD 0.030000
TOTAL P.U.
ANALISIS DE COSTO UNITARIO PROYECTO: DESCRIPCION: RENDIMIENTO EN 8 HRS: APORTE: MANO DE OBRA CAPATAZ OPERARIO PEON EXAMEN PARCIAL RED DE DESAGUE DE 4" EN PVC m h/m CANTIDAD 0.040000 0.400000 0.800000 COSTO 18.14 15.12 11.86 TOTAL COSTO 137.10 19.11 TOTAL COSTO 16.26 TOTAL TOTAL P.U. SUBTOTAL 0.73 6.05 9.49 16.26 SUBTOTAL 1.37 6.69 8.06 SUBTOTAL 0.49 0.49 24.81
UNIDAD % MO
CANTIDAD 0.030000
ANALISIS DE COSTO UNITARIO PROYECTO: DESCRIPCION: RENDIMIENTO EN 8 HRS: APORTE: MANO DE OBRA CAPATAZ OPERARIO PEON EXAMEN PARCIAL
TUBERIA DE DESAGUE PVC SAL DE 2" PARA VENTILACION
m h/m CANTIDAD 0.040000 0.400000 0.800000 COSTO 18.14 15.12 11.86 TOTAL COSTO 137.10 7.48 TOTAL COSTO 16.26 TOTAL TOTAL P.U. SUBTOTAL 0.73 6.05 9.49 16.26 SUBTOTAL 1.37 2.62 3.99 SUBTOTAL 0.49 0.49 20.74
UNIDAD % MO
CANTIDAD 0.030000
ANALISIS DE COSTO UNITARIO PROYECTO: DESCRIPCION: RENDIMIENTO EN 8 HRS: APORTE: MANO DE OBRA CAPATAZ OPERARIO PEON EXAMEN PARCIAL RED DE DESAGUE DE 2" EN PVC m h/m CANTIDAD 0.040000 0.400000 0.800000 COSTO 18.14 15.12 11.86 TOTAL COSTO 137.10 7.48 TOTAL COSTO 16.26 TOTAL TOTAL P.U. SUBTOTAL 0.73 6.05 9.49 16.26 SUBTOTAL 1.37 2.62 3.99 SUBTOTAL 0.49 0.49 20.74
UNIDAD % MO
CANTIDAD 0.030000
ANALISIS DE COSTO UNITARIO PROYECTO: DESCRIPCION: RENDIMIENTO EN 8 HRS: APORTE: MANO DE OBRA CAPATAZ OPERARIO PEON EXAMEN PARCIAL SALIDA DE DESAGUE DE 4" pto h/pto CANTIDAD 0.200000 2.000000 2.000000 COSTO 18.14 15.12 11.86 TOTAL COSTO 137.10 19.11 5.33 34.21 8.61 TOTAL COSTO 57.59 TOTAL TOTAL P.U. SUBTOTAL 3.63 30.24 23.72 57.59 SUBTOTAL 4.11 6.69 5.49 35.24 8.87 60.40 SUBTOTAL 1.73 1.73 119.71
MATERIALES PEGAMENTO P/TUBO PVC TUBO PVC DESAGUE SAL 4" X 3m CODO PVC DESAGUE SAL 4" X 90" TRAMPA P PVC DESAGUE SAL 4" YEE PVC DESAGUE SAL 4"
UNIDAD % MO
CANTIDAD 0.030000
ANALISIS DE COSTO UNITARIO PROYECTO: DESCRIPCION: RENDIMIENTO EN 8 HRS: APORTE: MANO DE OBRA CAPATAZ OPERARIO PEON EXAMEN PARCIAL SALIDA DE DESAGUE DE 2" pto h/pto CANTIDAD 0.200000 2.000000 2.000000 COSTO 18.14 15.12 11.86 TOTAL COSTO 137.10 7.48 1.31 5.80 2.44 TOTAL COSTO 57.59 TOTAL TOTAL P.U. SUBTOTAL 3.63 30.24 23.72 57.59 SUBTOTAL 4.11 2.62 1.35 5.97 2.51 16.57 SUBTOTAL 1.73 1.73 75.88
MATERIALES PEGAMENTO P/TUBO PVC TUBO PVC DESAGUE SAL 2" X 3m CODO PVC DESAGUE SAL 2" X 90" TRAMPA P PVC DESAGUE SAL 2" YEE PVC DESAGUE SAL 2"
UNIDAD % MO
CANTIDAD 0.030000
ANALISIS DE COSTO UNITARIO PROYECTO: DESCRIPCION: RENDIMIENTO EN 8 HRS: APORTE: MANO DE OBRA CAPATAZ OPERARIO PEON EXAMEN PARCIAL CAJA DE REGISTRO DE ALBAILERIA DE 10" X 20" 4.00 pza 0.5000 h/pza UNIDAD hh hh hh CANTIDAD 0.200000 2.000000 2.000000 COSTO 18.14 15.12 11.86 TOTAL COSTO 38.00 35.00 41.00 14.45 4.35 3.02 571.43 5.70 TOTAL COSTO 57.59 TOTAL SUBTOTAL 3.63 30.24 23.72 57.59 SUBTOTAL 1.14 2.10 10.25 21.68 43.50 2.60 20.00 0.06 101.32 SUBTOTAL 1.73 1.73 160.63
MATERIALES ARENA FINA ARENA GRUESA PIEDRA CHANCADA DE " - " HUSO 67 CEMENTO PORTLAND TIPO I (BLS.:42.5 KG) ACERO LISO GDO. 60 PRECIO PROM. P/Kg CLAVO C/CABEZA P/CONSTRUCCION DE PROMEDIO LADRILLO ARCILLA KING KONG 18 HUECOS AGUA
UNIDAD % MO
CANTIDAD 0.030000
TOTAL P.U.
ANALISIS DE COSTO UNITARIO PROYECTO: DESCRIPCION: RENDIMIENTO EN 8 HRS: APORTE: MANO DE OBRA CAPATAZ OPERARIO EXAMEN PARCIAL REGISTRO ROSCADO DE BRONCE DE 2" 8.00 pza 1.0000 h/pza UNIDAD hh hh CANTIDAD 0.100000 1.000000 COSTO 18.14 15.12 TOTAL COSTO 8.55 3.18 12.68 TOTAL COSTO 16.93 TOTAL SUBTOTAL 1.81 15.12 16.93 SUBTOTAL 8.55 3.18 12.68 24.41 SUBTOTAL 0.51 0.51 30.12
MATERIALES REGISTRO ROSCADO DE BRONCE 2" CODO PVC DESAGUE SAL 2" X 90 TEE SANITARIA PVC DESAGUE SAL 2"
UNIDAD % MO
CANTIDAD 0.030000
TOTAL P.U.
ANALISIS DE COSTO UNITARIO PROYECTO: DESCRIPCION: RENDIMIENTO EN 8 HRS: APORTE: MANO DE OBRA CAPATAZ OPERARIO PEON EXAMEN PARCIAL REGISTRO ROSCADO DE BRONCE DE 4" 6.00 pza 0.7500 h/pza UNIDAD hh hh hh CANTIDAD 0.133300 1.333300 0.666700 COSTO 18.14 15.12 11.84 TOTAL COSTO 26.14 5.30 11.84 TOTAL COSTO 30.47 TOTAL TOTAL P.U. SUBTOTAL 2.42 20.16 7.89 30.47 SUBTOTAL 26.14 5.30 11.84 43.28 SUBTOTAL 0.91 0.91 74.67
MATERIALES REGISTRO ROSCADO DE BRONCE CROMADO 4" CODO PVC DESAGUE SAL 4" X 90 TEE SANITARIA PVC DESAGUE SAL 4"
UNIDAD % MO
CANTIDAD 0.030000
ANALISIS DE COSTO UNITARIO PROYECTO: DESCRIPCION: RENDIMIENTO EN 8 HRS: APORTE: MANO DE OBRA CAPATAZ OPERARIO PEON EXAMEN PARCIAL CENTRO DE LUZ 5.00 0.6250 UNIDAD hh hh hh pto h/pto CANTIDAD 0.160000 1.600000 1.600000 COSTO 18.14 15.12 11.84 TOTAL COSTO 1.29 3.90 2.45 2.35 0.16 0.54 0.27 TOTAL COSTO 46.04 TOTAL TOTAL P.U. SUBTOTAL 2.90 24.19 18.94 46.04 SUBTOTAL 11.61 3.90 0.25 3.53 0.16 1.62 0.27 21.33 SUBTOTAL 2.30 2.30 69.67
MATERIALES CABLE TW 12 AWG CAJA DE PASE OCTOGONAL F.G. LIVIANA 4" CINTA AISLANTE ELECTRICA TUBO PVC ELECTRICO SEL " X 3M CONEXIN A CAJA PVC ELECTRICA SEL " CURVA PVC ELECTRICA SEL " X 45 UNION PVC ELECTRICA SEL "
UNIDAD % MO
CANTIDAD 0.050000
ANALISIS DE COSTO UNITARIO PROYECTO: DESCRIPCION: RENDIMIENTO EN 8 HRS: APORTE: MANO DE OBRA CAPATAZ OPERARIO PEON EXAMEN PARCIAL SALIDA PARA BRAQUETES 4.00 pza 0.5000 h/pza UNIDAD CANTIDAD COSTO SUBTOTAL hh hh hh 0.200000 2.000000 1.000000 18.14 15.12 11.84 TOTAL 3.63 30.24 11.84 45.71
UNIDAD CANTIDAD COSTO SUBTOTAL pza 1.000000 81.97 TOTAL 81.97 81.97
UNIDAD CANTIDAD COSTO SUBTOTAL % MO 0.030000 45.71 TOTAL 0.69 0.69 128.36
TOTAL P.U.
ANALISIS DE COSTO UNITARIO PROYECTO: DESCRIPCION: RENDIMIENTO EN 8 HRS: APORTE: MANO DE OBRA CAPATAZ OPERARIO PEON EXAMEN PARCIAL
SALIDA PARA TOMACORRIENTE BIPOLAR DOBLE
4.00 0.5000
pto h/pto
UNIDAD CANTIDAD COSTO SUBTOTAL hh hh hh 0.200000 2.000000 2.000000 18.14 15.12 11.84 TOTAL 3.63 30.24 23.68 57.55
MATERIALES CABLE TW 12 AWG TOMACORRIENTE DOBLE UNIVERSAL CAJA DE PASE RECTANGULAR F.G. LIVIANA 50 X 100mm TUBO PVC ELECTRICO SEL " X 3M CONEXIN A CAJA PVC ELECTRICA SEL " CURVA PVC ELECTRICA SEL " X 45 UNION PVC ELECTRICA SEL "
UNIDAD CANTIDAD COSTO SUBTOTAL m pza pza pza pza pza pza 16.000000 1.050000 1.050000 1.500000 2.000000 3.000000 1.000000 1.29 7.80 1.35 4.89 0.37 1.71 0.61 TOTAL 20.64 8.19 1.42 7.34 0.74 5.13 0.61 44.06
UNIDAD CANTIDAD COSTO SUBTOTAL % MO 0.050000 57.55 TOTAL 1.44 1.44 103.05
TOTAL P.U.
ANALISIS DE COSTO UNITARIO PROYECTO: DESCRIPCION: RENDIMIENTO EN 8 HRS: APORTE: EXAMEN PARCIAL SALIDA DE TIMBRE 2.00 pto 0.2500 h/pto UNIDA D hh hh hh CANTIDA D 0.400000 4.000000 2.000000 COST O 18.14 15.12 11.84 TOTAL COST O 4.50 4.89 0.37 1.71 0.61 TOTAL COST O 91.42 TOTAL SUBTOTA L 7.26 60.48 23.68 91.42 SUBTOTA L 4.50 29.34 0.74 3.42 1.22 39.22 SUBTOTA L 1.14 1.14 131.78
MATERIALES CAJA DE PASE CUADRADA F.G. 100 X 100 X 40mm TUBO PVC ELECTRICO SAP " X 3M CONEXIN A CAJA PVC ELECTRICA SAP " CURVA PVC ELECTRICA SAP " X 90 UNION PVC ELECTRICA SAP "
UNIDA D % MO
CANTIDA D 0.050000
TOTAL P.U.
ANALISIS DE COSTO UNITARIO PROYECTO: DESCRIPCION: RENDIMIENTO EN 8 HRS: APORTE: EXAMEN PARCIAL TABLERO DE DISTRIBUCION 24 POLOS 1.00 pza 0.1250 h/pza UNIDA D hh hh hh CANTIDA D 8.000000 8.000000 4.000000 COST O 18.14 15.12 11.84 TOTAL COST O 314.0 0 TOTAL COST O 313.4 4 TOTAL SUBTOTA L 145.12 120.96 47.36 313.44 SUBTOTA L
UNIDA D pza
CANTIDA D
1.000000
EQUIPOS
UNIDA D % MO
CANTIDA D
HERRAMIENTA MANUAL
0.050000
TOTAL P.U.
ANALISIS DE COSTO UNITARIO PROYECTO: DESCRIPCION: RENDIMIENTO EN 8 HRS: APORTE: MANO DE OBRA CAPATAZ OPERARIO OFICIAL PEON EXAMEN PARCIAL ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS 11.00 m2 1.3750 h/m2 UNIDAD hh hh hh hh CANTIDAD 0.110000 1.090000 1.310000 0.440000 COSTO 18.14 15.12 13.14 11.84 TOTAL COSTO 5.40 3.02 2.96 TOTAL COSTO 40.90 TOTAL TOTAL P.U. SUBTOTAL 2.00 16.48 17.21 5.21 40.90 SUBTOTAL 36.23 0.72 0.62 37.58 SUBTOTAL 1.23 1.23 79.71
UNIDAD pza kg kg
UNIDAD % MO
CANTIDAD 0.030000
ANALISIS DE COSTO UNITARIO PROYECTO: DESCRIPCION: RENDIMIENTO EN 8 HRS: APORTE: MANO DE OBRA CAPATAZ OPERARIO PEON OPERADOR DE EQUIPO LIVIANO EXAMEN PARCIAL CONCRETO PREMEZCLADO F'c = 175 Kg/CM2 100.00 m3 12.5000 h/m3 UNIDAD hh hh hh hh CANTIDAD 0.081000 0.320000 0.720000 0.160000 COSTO 18.14 15.12 13.14 17.39 TOTAL COSTO 208.80 TOTAL COSTO 412.8 5.53 18.55 TOTAL TOTAL P.U. SUBTOTAL 1.47 4.84 9.46 2.78 18.55 SUBTOTAL 208.80 208.80 SUBTOTAL 33.02 0.88 0.56 34.47 261.82
UNIDAD m3
CANTIDAD 1.000000
UNIDAD hm hm % MO
ANALISIS DE COSTO UNITARIO EXAMEN PARCIAL ACARREO DE MATERIAL EXCEDENTE 6.00 m3 0.7500 h/m3 UNIDAD hh hh CANTIDAD 0.130000 1.330000 COSTO 18.14 11.84 TOTAL COSTO 18.11 TOTAL TOTAL P.U. SUBTOTAL 2.36 15.75 18.11 SUBTOTAL 0.54 0.54 18.65
UNIDAD % MO
CANTIDAD 0.030000
PROYECTO: DESCRIPCION: RENDIMIENTO EN 8 HRS: APORTE: MANO DE OBRA CAPATAZ OPERARIO OFICIAL PEON
ANALISIS DE COSTO UNITARIO EXAMEN PARCIAL ENCOFRADO Y DESENCOFRADO 14.00 m2 1.7500 h/m2 UNIDAD hh hh hh hh CANTIDAD 0.080000 0.770000 0.990000 0.990000 COSTO 18.14 15.12 13.14 11.84 TOTAL COSTO 5.40 3.02 2.96 TOTAL COSTO 37.82 TOTAL TOTAL P.U. SUBTOTAL 1.45 11.64 13.01 11.72 37.82 SUBTOTAL 27.81 0.33 0.30 28.44 SUBTOTAL 1.13 1.13 67.40
UNIDAD p2 kg kg
UNIDAD % MO
CANTIDAD 0.030000
ANALISIS DE COSTO UNITARIO PROYECTO: DESCRIPCION: RENDIMIENTO EN 8 HRS: APORTE: MANO DE OBRA CAPATAZ OPERARIO OFICIAL PEON EXAMEN PARCIAL
ENCOFRADO Y DESENCOF. NORMAL EN LOSAS MACIZAS
m2 h/m2 CANTIDAD 0.070000 0.670000 0.850000 0.360000 COSTO 18.14 15.12 13.14 11.84 TOTAL COSTO 5.40 3.02 2.96 TOTAL COSTO 26.83 TOTAL TOTAL P.U. SUBTOTAL 1.27 10.13 11.17 4.26 26.83 SUBTOTAL 32.02 0.42 0.30 32.74 SUBTOTAL 0.80 0.80 60.38
UNIDAD p2 kg kg
UNIDAD % MO
CANTIDAD 0.030000
ANALISIS DE COSTO UNITARIO PROYECTO: DESCRIPCION: RENDIMIENTO EN 8 HRS: APORTE: MANO DE OBRA CAPATAZ OPERARIO OFICIAL PEON OPERADOR EQUIPO LIVIANO EXAMEN PARCIAL
CONCRETO EN MUROS TABIQUES Y PLACAS F'C= 175 KG/CM2
m3 h/m3 CANTIDAD 0.230000 2.000000 2.000000 10.270000 3.000000 COSTO 18.14 15.12 13.14 11.84 17.35 TOTAL COSTO 14.45 35.00 41.00 TOTAL COSTO 30.5 5.53 5.53 234.34 TOTAL TOTAL P.U. SUBTOTAL 4.17 30.24 26.28 121.60 52.05 234.34 SUBTOTAL 121.81 18.90 22.55 163.26 SUBTOTAL 30.50 5.53 5.53 7.03 48.59 446.19
UNIDAD bls m3 m3
EQUIPOS MEZCLADORA DE 9-11 P3 VIBRADOR DE 2.0" 4HP WINCHE ELECTRICO HERRAMIENTA MANUAL
UNIDAD hm hm hm % MO
ANALISIS DE COSTO UNITARIO PROYECTO: DESCRIPCION: RENDIMIENTO EN 8 HRS: APORTE: MANO DE OBRA CAPATAZ OPERARIO OFICIAL PEON OPERADOR EQUIPO LIVIANO EXAMEN PARCIAL
CONCRETO EN MUROS F'c=175 KG/m2 , CON 10 CM
m3 h/m3 CANTIDAD 0.120000 0.960000 0.640000 3.680000 0.960000 COSTO 18.14 15.12 13.14 11.84 17.35 TOTAL COSTO 14.45 35.00 41.00 TOTAL COSTO 30.5 5.53 5.53 85.33 TOTAL TOTAL P.U. SUBTOTAL 2.18 14.52 8.41 43.57 16.66 85.33 SUBTOTAL 121.81 18.90 22.55 163.26 SUBTOTAL 9.76 1.77 1.77 25.60 38.90 287.49
UNIDAD bls m3 m3
EQUIPOS MEZCLADORA DE 9-11 P3 VIBRADOR DE 2.0" 4HP WINCHE ELECTRICO DE 2 TAMBORES HERRAMIENTA MANUAL
UNIDAD hm hm hm % MO
ANALISIS DE COSTO UNITARIO PROYECTO: DESCRIPCION: RENDIMIENTO EN 8 HRS: APORTE: MANO DE OBRA CAPATAZ OPERARIO PEON EXAMEN PARCIAL MURO CON LADRILLO PANDERETA DE CUELLO 9.00 m2 1.1250 h/m2 UNIDAD hh hh hh CANTIDAD 0.112000 1.120000 0.784000 COSTO 18.14 15.12 11.84 TOTAL COSTO 14.45 35.00 3.02 0.56 TOTAL COSTO 5.4 28.25 TOTAL TOTAL P.U. SUBTOTAL 2.03 16.93 9.28 28.25 SUBTOTAL 1.79 0.63 0.07 16.80 19.29 SUBTOTAL 3.13 0.85 3.98 51.52
MATERIALES CEMENTO PORTLAND TIPO I ARENA GRUESA CLAVOS DE 3" LADRILLO PANDERETA
UNIDAD bls m3 kg pz
UNIDAD P2 % MO
PROYECTO: DESCRIPCION: RENDIMIENTO EN 8 HRS: APORTE: MANO DE OBRA CAPATAZ OPERARIO PEON
ANALISIS DE COSTO UNITARIO EXAMEN PARCIAL MURO DE LADRILLO PANDERETA DE SOGA 12.00 m2 1.5000 h/m2 UNIDAD hh hh hh CANTIDAD 0.073000 1.734000 0.631000 COSTO 18.14 15.12 11.84 TOTAL COSTO 14.45 35.00 3.02 0.56 TOTAL COSTO 5.4 35.01 TOTAL TOTAL P.U. SUBTOTAL 1.32 26.22 7.47 35.01 SUBTOTAL 2.36 0.81 0.07 19.60 22.83 SUBTOTAL 3.13 1.05 4.18 62.02
MATERIALES CEMENTO PORTLAND TIPO I ARENA GRUESA CLAVOS DE 3" LADRILLO PANDERETA
UNIDAD bls m3 kg pz
UNIDAD P2 % MO
PROYECTO: DESCRIPCION: RENDIMIENTO EN 8 HRS: APORTE: MANO DE OBRA CAPATAZ OPERARIO PEON
ANALISIS DE COSTO UNITARIO EXAMEN PARCIAL TARRAJEO PRIMARIO O RAYADO 17.00 m2 2.1250 h/m2 UNIDAD hh hh hh CANTIDAD 0.057000 0.571000 0.286000 COSTO 18.14 15.12 11.84 TOTAL COSTO 14.45 3.02 38.00 TOTAL COSTO 5.4 5.2 13.05 TOTAL TOTAL P.U. SUBTOTAL 1.03 8.63 3.39 13.05 SUBTOTAL 1.69 0.07 0.61 2.37 SUBTOTAL 3.13 0.13 0.39 3.65 19.07
UNIDAD bls kg m3
UNIDAD P2 P2 % MO
PROYECTO: DESCRIPCION: RENDIMIENTO EN 8 HRS: APORTE: MANO DE OBRA CAPATAZ OPERARIO PEON
ANALISIS DE COSTO UNITARIO EXAMEN PARCIAL TARRAJEO EN INTERIORES 34.00 m2 4.2500 h/m2 UNIDAD hh hh hh CANTIDAD 0.063000 0.635000 0.278000 COSTO 18.14 15.12 11.84 TOTAL COSTO 14.45 3.02 38.00 TOTAL COSTO 5.4 5.2 14.04 TOTAL TOTAL P.U. SUBTOTAL 1.14 9.60 3.29 14.04 SUBTOTAL 1.69 0.07 0.61 2.37 SUBTOTAL 3.13 0.13 0.42 3.68 20.08
UNIDAD bls kg m3
UNIDAD P2 P2 % MO
PROYECTO: DESCRIPCION: RENDIMIENTO EN 8 HRS: APORTE: MANO DE OBRA CAPATAZ OPERARIO PEON
ml h/ml CANTIDAD 0.400000 0.400000 0.132000 COSTO 18.14 15.12 11.84 TOTAL COSTO 14.45 38.00 TOTAL COSTO 14.87 TOTAL TOTAL P.U. SUBTOTAL 7.26 6.05 1.56 14.87 SUBTOTAL 0.45 0.15 0.60 SUBTOTAL 0.45 0.45 15.91
UNIDAD bls m3
UNIDAD % MO
CANTIDAD 0.030000
PROYECTO: DESCRIPCION: RENDIMIENTO EN 8 HRS: APORTE: MANO DE OBRA CAPATAZ OPERARIO PEON
ANALISIS DE COSTO UNITARIO EXAMEN PARCIAL COLOCACION INODORO 4.00 pz 0.5000 h/pz UNIDAD hh hh hh CANTIDAD 0.400000 4.000000 2.000000 COSTO 18.14 15.12 11.84 TOTAL COSTO 91.42 TOTAL TOTAL P.U. SUBTOTAL 7.26 60.48 23.68 91.42 SUBTOTAL 2.74 2.74 94.16
UNIDAD % MO
CANTIDAD 0.030000
m3 h/m3 CANTIDAD 0.110000 1.140000 COSTO 18.14 11.84 TOTAL COSTO 30.00 TOTAL COSTO 15.49 TOTAL TOTAL P.U. SUBTOTAL 2.00 13.50 15.49 SUBTOTAL 39.00 39.00 SUBTOTAL 0.46 0.46 54.96
UNIDAD m3
CANTIDAD 1.300000
UNIDAD % MO
CANTIDAD 0.030000
PROYECTO: DESCRIPCION: RENDIMIENTO EN 8 HRS: APORTE: MANO DE OBRA CAPATAZ OPERARIO PEON
ANALISIS DE COSTO UNITARIO EXAMEN PARCIAL NIVELACION INTERIOR Y COMPACTACION 120.00 m2 15.0000 h/m2 UNIDAD hh hh hh CANTIDAD 0.007000 0.067000 0.067000 COSTO 18.14 15.12 11.84 TOTAL COSTO 3.02 TOTAL COSTO 5.2 1.93 TOTAL TOTAL P.U. SUBTOTAL 0.13 1.01 0.79 1.93 SUBTOTAL 0.03 0.03 SUBTOTAL 0.16 0.06 0.21 2.18
UNIDAD kg
CANTIDAD 0.010000
UNIDAD P2 % MO
PROYECTO: DESCRIPCION: RENDIMIENTO EN 8 HRS: APORTE: MANO DE OBRA CAPATAZ OPERARIO OFICIAL
ANALISIS DE COSTO UNITARIO EXAMEN PARCIAL ACERO EN SOBRECIMIENTO REFORZADO GRADO 60 280.00 kg 35.0000 h/kg UNIDAD hh hh hh CANTIDAD 0.004000 0.032000 0.032000 COSTO 18.14 15.12 13.14 TOTAL COSTO 2.96 3.50 TOTAL COSTO 4.2 0.98 TOTAL TOTAL P.U. SUBTOTAL 0.07 0.48 0.42 0.98 SUBTOTAL 0.18 3.75 3.92 SUBTOTAL 0.13 0.03 0.16 5.06
UNIDAD kg kg
UNIDAD hm % MO
PROYECTO: DESCRIPCION: RENDIMIENTO EN 8 HRS: APORTE: MANO DE OBRA CAPATAZ OPERARIO OFICIAL
ANALISIS DE COSTO UNITARIO EXAMEN PARCIAL ACERO GRADO 60 EN MUROS TABIQUES Y PLACAS 280.00 kg 35.0000 h/kg UNIDAD hh hh hh CANTIDAD 0.004000 0.032000 0.032000 COSTO 18.14 15.12 13.14 TOTAL COSTO 2.96 3.50 TOTAL COSTO 4.2 0.98 TOTAL TOTAL P.U. SUBTOTAL 0.07 0.48 0.42 0.98 SUBTOTAL 0.18 3.75 3.92 SUBTOTAL 0.13 0.03 0.16 5.06
UNIDAD kg kg
UNIDAD hm % MO
PROYECTO: DESCRIPCION: RENDIMIENTO EN 8 HRS: APORTE: MANO DE OBRA CAPATAZ OPERARIO OFICIAL
ANALISIS DE COSTO UNITARIO EXAMEN PARCIAL ACERO GRADO 60 EN VIGAS 280.00 kg 35.0000 h/kg UNIDAD hh hh hh CANTIDAD 0.004000 0.032000 0.032000 COSTO 18.14 15.12 13.14 TOTAL COSTO 2.96 3.50 TOTAL COSTO 4.2 0.98 TOTAL TOTAL P.U. SUBTOTAL 0.07 0.48 0.42 0.98 SUBTOTAL 0.18 3.75 3.92 SUBTOTAL 0.13 0.03 0.16 5.06
UNIDAD kg kg
UNIDAD hm % MO
PROYECTO: DESCRIPCION: RENDIMIENTO EN 8 HRS: APORTE: MANO DE OBRA CAPATAZ OPERARIO OFICIAL
ANALISIS DE COSTO UNITARIO EXAMEN PARCIAL ACERO GRADO 60 EN LOSAS ALIGERADAS 280.00 kg 35.0000 h/kg UNIDAD hh hh hh CANTIDAD 0.004000 0.032000 0.032000 COSTO 18.14 15.12 13.14 TOTAL COSTO 2.96 3.50 TOTAL COSTO 4.2 0.98 TOTAL TOTAL P.U. SUBTOTAL 0.07 0.48 0.42 0.98 SUBTOTAL 0.18 3.75 3.92 SUBTOTAL 0.13 0.03 0.16 5.06
UNIDAD kg kg
UNIDAD hm % MO
PROYECTO: DESCRIPCION: RENDIMIENTO EN 8 HRS: APORTE: MANO DE OBRA CAPATAZ OPERARIO OFICIAL
ANALISIS DE COSTO UNITARIO EXAMEN PARCIAL ACERO GRADO 60 EN LOSAS MACIZAS 280.00 kg 35.0000 h/kg UNIDAD hh hh hh CANTIDAD 0.004000 0.032000 0.032000 COSTO 18.14 15.12 13.14 TOTAL COSTO 2.96 3.50 TOTAL COSTO 4.2 0.98 TOTAL TOTAL P.U. SUBTOTAL 0.07 0.48 0.42 0.98 SUBTOTAL 0.18 3.75 3.92 SUBTOTAL 0.13 0.03 0.16 5.06
UNIDAD kg kg
UNIDAD hm % MO
PROYECTO: DESCRIPCION: RENDIMIENTO EN 8 HRS: APORTE: MANO DE OBRA CAPATAZ OPERARIO OFICIAL
ANALISIS DE COSTO UNITARIO EXAMEN PARCIAL ACERO EN MURO DE ALBANILERIA ARMADA 280.00 kg 35.0000 h/kg UNIDAD hh hh hh CANTIDAD 0.004000 0.032000 0.032000 COSTO 18.14 15.12 13.14 TOTAL COSTO 2.96 3.50 TOTAL COSTO 4.2 0.98 TOTAL TOTAL P.U. SUBTOTAL 0.07 0.48 0.42 0.98 SUBTOTAL 0.18 3.75 3.92 SUBTOTAL 0.13 0.03 0.16 5.06
UNIDAD kg kg
UNIDAD hm % MO
PROYECTO: DESCRIPCION: RENDIMIENTO EN 8 HRS: APORTE: MANO DE OBRA CAPATAZ OPERARIO OFICIAL PEON
m2 h/m2 CANTIDAD 0.100000 1.000000 1.200000 0.400000 COSTO 18.14 15.12 13.14 11.84 TOTAL COSTO 5.4 2.96 3.02 TOTAL COSTO 37.44 TOTAL TOTAL P.U. SUBTOTAL 1.81 15.12 15.77 4.74 37.44 SUBTOTAL 27.86 0.89 0.51 29.27 SUBTOTAL 1.12 1.12 67.83
UNIDAD P2 kg kg
UNIDAD % MO
CANTIDAD 0.030000
ANALISIS DE COSTO UNITARIO PROYECTO: DESCRIPCION: RENDIMIENTO EN 8 HRS: APORTE: MANO DE OBRA CAPATAZ OPERARIO PEON EXAMEN PARCIAL MURO DE LADRILLO DE SOGA KING KONG 12.00 m2 1.5000 h/m2 UNIDAD CANTIDAD COSTO SUBTOTAL hh hh hh 0.085000 0.846000 0.719000 18.14 15.12 11.84 TOTAL 1.54 12.79 8.51 22.85
MATERIALES CEMENTO PORTLAND TIPO I ARENA GRUESA CLAVOS DE 3" LADRILLO KIN KONG 18 HUECOS
UNIDAD CANTIDAD COSTO SUBTOTAL bls m3 kg mll 0.218000 0.031000 0.022000 0.050000 14.45 35.00 3.02 571.43 TOTAL 3.15 1.09 0.07 28.57 32.87
UNIDAD CANTIDAD COSTO SUBTOTAL P2 % MO 0.580000 0.030000 5.4 22.85 TOTAL 3.13 0.69 3.82 59.54
TOTAL P.U.
ANALISIS DE COSTO UNITARIO PROYECTO: DESCRIPCION: RENDIMIENTO EN 8 HRS: APORTE: MANO DE OBRA CAPATAZ OPERARIO OFICIAL PEON OPERADOR EQUIPO EXAMEN PARCIAL FALSO CIMIENTO m3 h/m3
25.00 3.1250
UNIDAD CANTIDAD COSTO SUBTOTAL hh hh hh hh hh 0.0640 0.6400 0.3200 2.5600 0.3200 18.14 15.12 13.14 11.84 17.35 TOTAL 1.16 9.68 4.20 30.31 5.55 50.90
MATERIALES PIEDRA GRANDE HORMIGON AGUA CEMENTO PORTLAND TIPO I (BLS.:42.5 KG)
UNIDAD CANTIDAD COSTO SUBTOTAL m3 m3 m3 bls 0.5200 0.7800 0.1620 2.9000 30.00 22.50 5.70 14.45 TOTAL 15.60 17.55 0.92 41.91 75.98
COMB. Y LUB. GASOLINA 84 OCTANOS (GRIFO LIMA) ACEITE MOTOR GASOLINA SAE 30W GRASA MULTIPLE EP
UNIDAD CANTIDAD COSTO SUBTOTAL gal gal lb 0.1200 0.0040 0.0080 11.70 57.00 5.80 TOTAL 1.40 0.23 0.05 1.68
UNIDAD CANTIDAD COSTO SUBTOTAL hm % MO 0.3200 0.030000 30.5 50.90 TOTAL 9.76 1.53 11.29 139.85
TOTAL P.U.
ANALISIS DE COSTO UNITARIO PROYECTO: DESCRIPCION: RENDIMIENTO EN 8 HRS: APORTE: MANO DE OBRA CAPATAZ OPERARIO OFICIAL PEON OPERADOR EQUIPO LIVIANO EXAMEN PARCIAL
CONCRETO PREMEZCLADO F'c=100 SOBRECIMIENTOS
m3 h/m3 CANTIDAD 0.0133 0.2667 0.1333 0.5333 0.1333 COSTO 18.14 15.12 13.14 11.84 17.35 TOTAL COSTO 185.00 TOTAL COSTO 5.38 14.65 TOTAL TOTAL P.U. SUBTOTAL 0.24 4.03 1.75 6.31 2.31 14.65 SUBTOTAL 190.55 190.55 SUBTOTAL 0.72 0.44 1.16 206.36
UNIDAD m3
CANTIDAD 1.0300
UNIDAD hm % MO
ANALISIS DE COSTO UNITARIO PROYECTO: DESCRIPCION: RENDIMIENTO EN 8 HRS: APORTE: MANO DE OBRA CAPATAZ OPERARIO OFICIAL PEON OPERADOR EQUIPO EXAMEN PARCIAL CONCRETO PARA VIGAS DE F'c= 280 KG/m2 25.00 m3 3.1250 h/m3 UNIDAD hh hh hh hh hh CANTIDAD 0.0640 0.6400 0.3200 2.5600 0.6400 COSTO 18.14 15.12 13.14 11.84 17.35 TOTAL COSTO 35 41 14.45 TOTAL COMB. Y LUB. GASOLINA 84 OCTANOS (GRIFO LIMA) ACEITE MOTOR GASOLINA SAE 30W GRASA MULTIPLE EP UNIDAD gal gal lb CANTIDAD 0.1200 0.0040 0.0080 COSTO 11.70 57.00 5.80 TOTAL COSTO 30.5 5.38 56.46 TOTAL TOTAL P.U. SUBTOTAL 1.16 9.68 4.20 30.31 11.10 56.46 SUBTOTAL 17.50 32.80 121.38 0.00 171.68 SUBTOTAL 1.40 0.23 0.05 1.68 SUBTOTAL 9.76 1.72 2.82 14.30 244.12
MATERIALES ARENA GRUESA PIEDRA CHANCADA DE " - " HUSO 67 CEMENTO PORTLAND TIPO I (BLS.:42.5 KG) AGUA
UNIDAD m3 m3 bls m3
EQUIPOS MEZCLADORA DE CONCRETO T.TAMBOR 23HP 11 - 12P3 VIBRADOR DE CONCRETO 4HP 2.40 plg HERRAMIENTA MANUAL
UNIDAD hm hm % MO
ANALISIS DE COSTO UNITARIO PROYECTO: DESCRIPCION: RENDIMIENTO EN 8 HRS: APORTE: MANO DE OBRA CAPATAZ OPERARIO OFICIAL PEON OPERADOR EQUIPO LIVIANO EXAMEN PARCIAL CONCRETO PREMEZCLADO F'c = 175 Kg/CM2 60.00 m3 7.5000 h/m3 UNIDAD hh hh hh hh hh CANTIDAD 0.0133 0.2667 0.1333 0.5333 0.1333 COSTO 18.14 15.12 13.14 11.84 17.35 TOTAL COSTO 208.8 TOTAL COSTO 5.38 14.65 TOTAL TOTAL P.U. SUBTOTAL 0.24 4.03 1.75 6.31 2.31 14.65 SUBTOTAL 212.98 212.98 SUBTOTAL 0.72 0.44 1.16 228.79
UNIDAD m3
CANTIDAD 1.0200
UNIDAD hm % MO
ANALISIS DE COSTO UNITARIO PROYECTO: DESCRIPCION: RENDIMIENTO EN 8 HRS: APORTE: MANO DE OBRA CAPATAZ OPERARIO OFICIAL PEON OPERADOR EQUIPO LIVIANO EXAMEN PARCIAL CONCRETO PREMEZCLADO F'C=175 kg/cm2 LOSA MASIZA 100.00 m3 12.5000 h/m3 UNIDAD hh hh hh hh hh CANTIDAD 0.0133 0.2667 0.1333 0.5333 0.1333 COSTO 18.14 15.12 13.14 11.84 17.35 TOTAL COSTO 208.8 TOTAL COSTO 5.38 14.65 TOTAL TOTAL P.U. SUBTOTAL 0.24 4.03 1.75 6.31 2.31 14.65 SUBTOTAL 212.98 212.98 SUBTOTAL 0.72 0.44 1.16 228.79
UNIDAD m3
CANTIDAD 1.0200
UNIDAD hm % MO
PROYECTO: DESCRIPCION: RENDIMIENTO EN 8 HRS: APORTE: MANO DE OBRA CAPATAZ OPERARIO PEON
ANALISIS DE COSTO UNITARIO EXAMEN PARCIAL COLOCACION LAVATORIO DE PARED BLANCO 4.00 pz 0.5000 h/pz UNIDAD hh hh hh CANTIDAD 0.400000 4.000000 2.000000 COSTO 18.14 15.12 11.84 TOTAL COSTO 91.42 TOTAL TOTAL P.U. SUBTOTAL 7.26 60.48 23.68 91.42 SUBTOTAL 2.74 2.74 94.16
UNIDAD % MO
CANTIDAD 0.030000
PROYECTO: DESCRIPCION: RENDIMIENTO EN 8 HRS: APORTE: MANO DE OBRA CAPATAZ OPERARIO PEON
ANALISIS DE COSTO UNITARIO EXAMEN PARCIAL COLOCACION DE LAVADERO DE ACERO INOXIDABLE 4.00 pz 0.5000 h/pz UNIDAD hh hh hh CANTIDAD 0.400000 4.000000 2.000000 COSTO 18.14 15.12 11.84 TOTAL COSTO 91.42 TOTAL TOTAL P.U. SUBTOTAL 7.26 60.48 23.68 91.42 SUBTOTAL 2.74 2.74 94.16
UNIDAD % MO
CANTIDAD 0.030000
PROYECTO: DESCRIPCION: RENDIMIENTO EN 8 HRS: APORTE: MANO DE OBRA CAPATAZ OPERARIO PEON
ANALISIS DE COSTO UNITARIO EXAMEN PARCIAL COLOCACION LAVADERO DE GRANITO 4.00 pz 0.5000 h/pz UNIDAD hh hh hh CANTIDAD 0.400000 4.000000 2.000000 COSTO 18.14 15.12 11.84 TOTAL COSTO 91.42 TOTAL TOTAL P.U. SUBTOTAL 7.26 60.48 23.68 91.42 SUBTOTAL 2.74 2.74 94.16
UNIDAD % MO
CANTIDAD 0.030000
PROYECTO: DESCRIPCION: RENDIMIENTO EN 8 HRS: APORTE: MANO DE OBRA CAPATAZ OPERARIO PEON
pz h/pz CANTIDAD 0.400000 4.000000 2.000000 COSTO 18.14 15.12 11.84 TOTAL COSTO 91.42 TOTAL TOTAL P.U. SUBTOTAL 7.26 60.48 23.68 91.42 SUBTOTAL 2.74 2.74 94.16
UNIDAD % MO
CANTIDAD 0.030000
ANALISIS DE COSTO UNITARIO PROYECTO: DESCRIPCION: RENDIMIENTO EN 8 HRS: APORTE: MANO DE OBRA CAPATAZ OPERARIO OFICIAL PEON OPERADOR EQUIPO LIVIANO EXAMEN PARCIAL CONTRAPISO DE 50 mm 80.00 m2 10.0000 h/m2 UNIDAD CANTIDAD COSTO SUBTOTAL hh hh hh hh hh 0.030000 0.300000 0.100000 0.600000 0.1000 18.14 15.12 13.14 11.84 17.35 TOTAL 0.54 4.54 1.31 7.10 1.74 15.23
EQUIPOS MEZCLADORA DE CONCRETO T.TAMBOR 23HP 11 - 12P3 REGLA DE MADERA HERRAMIENTA MANUAL
UNIDAD CANTIDAD COSTO SUBTOTAL hm P2 % MO 0.1000 0.060000 0.030000 30.5 5.2 15.23 TOTAL 3.05 0.31 0.46 3.82 19.05
TOTAL P.U.
ANALISIS DE COSTO UNITARIO PROYECTO: DESCRIPCION: RENDIMIENTO EN 8 HRS: APORTE: MANO DE OBRA CAPATAZ OPERARIO OFICIAL PEON OPERADOR EQUIPO LIVIANO EXAMEN PARCIAL CONTRAPISO DE 35 mm 100.00 m2 12.5000 h/m2 UNIDAD CANTIDAD COSTO SUBTOTAL hh hh hh hh hh 0.024000 0.240000 0.080000 0.480000 0.0800 18.14 15.12 13.14 11.84 17.35 TOTAL 0.44 3.63 1.05 5.68 1.39 12.19
EQUIPOS MEZCLADORA DE CONCRETO T.TAMBOR 23HP 11 - 12P3 REGLA DE MADERA HERRAMIENTA MANUAL
UNIDAD CANTIDAD COSTO SUBTOTAL hm P2 % MO 0.0800 0.060000 0.030000 30.5 5.2 12.19 TOTAL 2.44 0.31 0.37 3.12 15.30
TOTAL P.U.
ANALISIS DE COSTO UNITARIO PROYECTO: DESCRIPCION: RENDIMIENTO EN 8 HRS: APORTE: MANO DE OBRA CAPATAZ OPERARIO OFICIAL PEON OPERADOR EQUIPO LIVIANO EXAMEN PARCIAL PISO DE CEMENTO PULIDO Y BRUADO 120.00 m2 15.0000 h/m2 UNIDAD CANTIDAD COSTO SUBTOTAL hh hh hh hh hh 0.032000 0.280000 0.670000 0.520000 0.0670 18.14 15.12 13.14 11.84 17.35 TOTAL 0.58 4.23 8.80 6.16 1.16 20.94
MATERIALES CEMENTO PORTLAND TIPO I ARENA GRUESA PIEDRA CHANCADA " ARENA FINA
UNIDAD CANTIDAD COSTO SUBTOTAL bls m3 m3 m3 0.450000 0.021000 0.027000 0.009000 14.45 35.00 41.00 38.00 TOTAL 6.50 0.74 1.11 0.34 8.69
EQUIPOS MEZCLADORA DE CONCRETO T.TAMBOR 23HP 11 - 12P3 REGLA DE MADERA HERRAMIENTA MANUAL
UNIDAD CANTIDAD COSTO SUBTOTAL hm P2 % MO 0.0670 0.099000 0.030000 30.5 5.2 20.94 TOTAL 2.04 0.51 0.63 3.19 32.81
TOTAL P.U.
ANALISIS DE COSTO UNITARIO PROYECTO: DESCRIPCION: RENDIMIENTO EN 8 HRS: APORTE: MANO DE OBRA CAPATAZ OPERARIO PEON EXAMEN PARCIAL PISO DE CERAMICO 20 x 20 12.00 m2 1.5000 h/m2 UNIDAD CANTIDAD COSTO SUBTOTAL hh hh hh 0.089000 0.088900 0.444000 18.14 15.12 11.84 TOTAL 1.61 1.34 5.26 8.22
UNIDAD CANTIDAD COSTO SUBTOTAL bls m2 m3 0.262000 1.050000 0.027000 14.45 16.00 38.00 TOTAL 3.79 16.80 1.03 21.61
UNIDAD CANTIDAD COSTO SUBTOTAL P2 % MO 0.055000 0.030000 5.2 8.22 TOTAL 0.29 0.25 0.53 30.36
TOTAL P.U.
ANALISIS DE COSTO UNITARIO PROYECTO: DESCRIPCION: RENDIMIENTO EN 8 HRS: APORTE: MANO DE OBRA CAPATAZ OPERARIO PEON EXAMEN PARCIAL BRUAS EN MUROS 25.00 3.1250 UNIDAD hh hh hh ml h/ml CANTIDAD 0.030000 0.320000 0.110000 COSTO 18.14 15.12 11.84 TOTAL COSTO 6.69 TOTAL TOTAL P.U. SUBTOTAL 0.54 4.84 1.30 6.69 SUBTOTAL 0.20 0.20 6.89
UNIDAD % MO
CANTIDAD 0.030000
ANALISIS DE COSTO UNITARIO PROYECTO: DESCRIPCION: RENDIMIENTO EN 8 HRS: APORTE: MANO DE OBRA CAPATAZ OPERARIO OFICIAL EXAMEN PARCIAL PUERTA PRINCIPAL DE CEDRO DE 0.80 M DE ANCHO 32.00 m 4.0000 h/m2 UNIDAD hh hh hh CANTIDAD 0.400000 4.000000 4.000000 COSTO 18.14 15.12 13.14 TOTAL COSTO 3.02 5.40 1.00 22.70 TOTAL COSTO 4.29 3.91 120.30 TOTAL TOTAL P.U. SUBTOTAL 7.26 60.48 52.56 120.30 SUBTOTAL 0.23 91.80 1.10 2.72 95.85 SUBTOTAL 3.43 3.13 6.01 12.57 228.72
MATERIALES CLAVO C/CABEZA P/CONSTRUCCCION D. PROMEDIO MADERA CEDRO LIJA P/MADERA COLA SINTETICA
UNIDAD hm hm % MO
ANALISIS DE COSTO UNITARIO PROYECTO: DESCRIPCION: RENDIMIENTO EN 8 HRS: APORTE: MANO DE OBRA CAPATAZ OPERARIO OFICIAL EXAMEN PARCIAL PUERTA CORREDIZA DE 1.80 X 1.80 M 32.00 m 4.0000 h/m2 UNIDAD hh hh hh CANTIDAD COSTO SUBTOTAL 0.800000 4.000000 2.000000 18.14 15.12 13.14 TOTAL 14.51 60.48 26.28 101.27
MATERIALES CLAVO C/CABEZA P/CONSTRUCCCION D. PROMEDIO MADERA CEDRO LIJA P/MADERA COLA SINTETICA
CANTIDAD COSTO SUBTOTAL 0.075000 25.400000 1.100000 0.120000 3.02 5.40 1.00 22.70 TOTAL 0.23 137.16 1.10 2.72 141.21
UNIDAD hm hm % MO
CANTIDAD COSTO SUBTOTAL 0.800000 0.800000 0.030000 4.29 3.91 101.27 TOTAL 3.43 3.13 3.04 9.60 252.08
TOTAL P.U.
ANALISIS DE COSTO UNITARIO PROYECTO: DESCRIPCION: RENDIMIENTO EN 8 HRS: APORTE: MANO DE OBRA CAPATAZ OPERARIO PEON EXAMEN PARCIAL SALIDA DE INTERRUPTOR SIMPLE 4.00 pto 0.5000 h/pto UNIDAD hh hh hh CANTIDAD COSTO SUBTOTAL 0.200000 2.000000 2.000000 18.14 15.12 11.84 TOTAL 3.63 30.24 23.68 57.55
MATERIALES ALAMBRE TW 12 AWG INTERRUPTOR SIMPLE CAJA DE PASE RECTANGULAR F.G. LIVIANA 50 X 100mm CAJA DE PASE OCTOGONAL F.G. LIVIANA 4" CINTA AISLANTE ELECTRICA TUBO PVC ELECTRICO SAP " X 3M CONEXIN A CAJA PVC ELECTRICA SAP " CURVA PVC ELECTRICA SAP " X 45 UNION PVC ELECTRICA SAP "
CANTIDAD COSTO SUBTOTAL 8.000000 1.050000 1.050000 1.000000 0.100000 1.500000 1.000000 2.000000 1.000000 1.23 5.40 1.35 1.60 2.50 4.89 0.37 1.71 0.61 TOTAL 9.84 5.67 1.42 1.60 0.25 7.34 0.37 3.42 0.61 30.51
UNIDAD % MO
TOTAL P.U.
ANALISIS DE COSTO UNITARIO PROYECTO: DESCRIPCION: RENDIMIENTO EN 8 HRS: APORTE: MANO DE OBRA CAPATAZ OPERARIO PEON EXAMEN PARCIAL SALIDA DE INTERRUPTOR DOBLE 4.00 pto 0.5000 h/pto UNIDAD hh hh hh CANTIDAD COSTO SUBTOTAL 0.200000 2.000000 2.000000 18.14 15.12 11.84 TOTAL 3.63 30.24 23.68 57.55
MATERIALES ALAMBRE TW 12 AWG INTERRUPTOR DOBLE CAJA DE PASE RECTANGULAR F.G. LIVIANA 50 X 100mm CAJA DE PASE OCTOGONAL F.G. LIVIANA 4" CINTA AISLANTE ELECTRICA TUBO PVC ELECTRICO SAP " X 3M CONEXIN A CAJA PVC ELECTRICA SAP " CURVA PVC ELECTRICA SAP " X 45 UNION PVC ELECTRICA SAP "
CANTIDAD COSTO SUBTOTAL 16.000000 1.050000 1.050000 1.000000 0.100000 1.500000 2.000000 2.000000 1.000000 1.23 5.40 1.35 1.60 2.50 4.89 0.37 1.71 0.61 TOTAL 19.68 5.67 1.42 1.60 0.25 7.34 0.74 3.42 0.61 40.72
UNIDAD % MO
TOTAL P.U.
ANALISIS DE COSTO UNITARIO PROYECTO: DESCRIPCION: RENDIMIENTO EN 8 HRS: APORTE: MANO DE OBRA CAPATAZ OPERARIO PEON EXAMEN PARCIAL SALIDA DE INTERRUPTOR DE CONMUTACION 4.00 pto 0.5000 h/pto UNIDAD hh hh hh CANTIDAD COSTO SUBTOTAL 0.200000 2.000000 2.000000 18.14 15.12 11.84 TOTAL 3.63 30.24 23.68 57.55
MATERIALES ALAMBRE TW 12 AWG INTERRUPTOR CONMUTACION CAJA DE PASE RECTANGULAR F.G. LIVIANA 50 X 100mm CAJA DE PASE OCTOGONAL F.G. LIVIANA 4" CINTA AISLANTE ELECTRICA TUBO PVC ELECTRICO SAP " X 3M CONEXIN A CAJA PVC ELECTRICA SAP " CURVA PVC ELECTRICA SAP " X 45 UNION PVC ELECTRICA SAP "
CANTIDAD COSTO SUBTOTAL 16.000000 2.050000 2.050000 1.000000 0.100000 1.500000 2.000000 3.000000 1.000000 1.23 5.40 1.35 1.60 2.50 4.89 0.37 1.71 0.61 TOTAL 19.68 11.07 2.77 1.60 0.25 7.34 0.74 5.13 0.61 49.18
UNIDAD % MO
TOTAL P.U.
ANALISIS DE COSTO UNITARIO PROYECTO: DESCRIPCION: RENDIMIENTO EN 8 HRS: APORTE: MANO DE OBRA OPERARIO PEON EXAMEN PARCIAL LIMPIEZA GENERAL DE OBRA m2 h/m2 CANTIDAD 0.020000 0.200000 COSTO 15.12 11.84 TOTAL COSTO 2.67 TOTAL TOTAL P.U. SUBTOTAL 0.30 2.37 2.67 SUBTOTAL 0.13 0.13 2.80
UNIDAD % MO
CANTIDAD 0.050000
ANALISIS DE COSTO UNITARIO PROYECTO: DESCRIPCION: RENDIMIENTO EN 8 HRS: APORTE: MANO DE OBRA CAPATAZ OPERARIO OFICIAL PEON EXAMEN PARCIAL CONCRETO LIQUIDO PREMEZCLADO EN MUROS 8.00 m3 1.0000 h/m3 UNIDAD hh hh hh hh CANTIDAD 0.0133 0.2667 0.1333 0.5333 COSTO 18.14 15.12 13.14 11.84 TOTAL COSTO 250.73 TOTAL COSTO 12.34 TOTAL TOTAL P.U. SUBTOTAL 0.24 4.03 1.75 6.31 12.34 SUBTOTAL 255.74 255.74 SUBTOTAL 0.37 0.37 268.45
UNIDAD m3
CANTIDAD 1.0200
UNIDAD % MO
CANTIDAD 0.0300
ANALISIS DE COSTO UNITARIO PROYECTO: DESCRIPCION: RENDIMIENTO EN 8 HRS: APORTE: MANO DE OBRA OPERARIO PEON EXAMEN PARCIAL VENTANA PRINCIPAL DE 1.80 X 0.90 M DE 2 HOJAS 2.50 m 0.3125 h/m2 UNIDAD hh hh CANTIDAD 3.200000 3.200000 COSTO 15.12 11.84 TOTAL COSTO 12.71 40 TOTAL COSTO 4.50 86.27 TOTAL TOTAL P.U. SUBTOTAL 48.38 37.89 86.27 SUBTOTAL 1.58 66.00 67.58 SUBTOTAL 14.40 4.31 18.71 172.57
MATERIALES SOLDADURA CELLOCORD P E6010 ANGULO ACERO NEGRO IGUAL 1" X 1" X " X 6m
UNIDAD kg pza
UNIDAD hm % MO
ANALISIS DE COSTO UNITARIO PROYECTO: DESCRIPCION: RENDIMIENTO EN 8 HRS: APORTE: MANO DE OBRA OPERARIO PEON EXAMEN PARCIAL VENTANA POSTERIOR DE 1.20 X 0.90 M DE 2 HOJAS 2.50 m 0.3125 h/m2 UNIDAD hh hh CANTIDAD 3.200000 3.200000 COSTO 15.12 11.84 TOTAL COSTO 12.71 40 TOTAL COSTO 4.50 86.27 TOTAL TOTAL P.U. SUBTOTAL 48.38 37.89 86.27 SUBTOTAL 1.58 66.00 66.00 SUBTOTAL 14.40 4.31 4.31 156.59
MATERIALES SOLDADURA CELLOCORD P E6010 ANGULO ACERO NEGRO IGUAL 1" X 1" X " X 6m
UNIDAD kg pza
UNIDAD hm % MO
ANALISIS DE COSTO UNITARIO PROYECTO: DESCRIPCION: RENDIMIENTO EN 8 HRS: APORTE: MANO DE OBRA OPERARIO PEON EXAMEN PARCIAL VENTANAS EN DORMITORIOS DE 1.50 X .90 M DE 2 HOJAS 2.50 m 0.3125 h/m2 UNIDAD hh hh CANTIDAD 3.200000 3.200000 COSTO 15.12 11.84 TOTAL COSTO 12.71 40 TOTAL COSTO 4.50 86.27 TOTAL TOTAL P.U. SUBTOTAL 48.38 37.89 86.27 SUBTOTAL 1.58 66.00 66.00 SUBTOTAL 14.40 4.31 4.31 156.59
MATERIALES SOLDADURA CELLOCORD P E6010 ANGULO ACERO NEGRO IGUAL 1" X 1" X " X 6m
UNIDAD kg pza
UNIDAD hm % MO
ANALISIS DE COSTO UNITARIO PROYECTO: DESCRIPCION: RENDIMIENTO EN 8 HRS: APORTE: MANO DE OBRA OPERARIO PEON EXAMEN PARCIAL VENTANA CORREDIZA DE 1.55 X .90 M DE 2 HOJAS 2.50 m 0.3125 h/m2 UNIDAD hh hh CANTIDAD 3.200000 3.200000 COSTO 15.12 11.84 TOTAL COSTO 12.71 40 TOTAL COSTO 4.50 86.27 TOTAL TOTAL P.U. SUBTOTAL 48.38 37.89 86.27 SUBTOTAL 1.58 66.00 66.00 SUBTOTAL 14.40 4.31 4.31 156.59
MATERIALES SOLDADURA CELLOCORD P E6010 ANGULO ACERO NEGRO IGUAL 1" X 1" X " X 6m
UNIDAD kg pza
UNIDAD hm % MO
PROYECTO: DESCRIPCION: RENDIMIENTO EN 8 HRS: APORTE: MANO DE OBRA CAPATAZ OPERARIO PEON
ANALISIS DE COSTO UNITARIO EXAMEN PARCIAL MURO DE LADRILLO SILICO CALCAREO 7.50 m2 0.9375 h/m2 UNIDAD hh hh hh CANTIDAD 0.085000 0.846000 0.719000 COSTO 18.14 15.12 11.84 TOTAL COSTO 48.42 TOTAL COSTO 22.85 TOTAL TOTAL P.U. SUBTOTAL 1.54 12.79 8.51 22.85 SUBTOTAL 49.87 49.87 SUBTOTAL 0.69 0.69 73.40
UNIDAD m2
CANTIDAD 1.030000
UNIDAD % MO
CANTIDAD 0.030000