BILL OF QUANTITY

PROPOSED LANDSCAPE DESIGN AT.


1/4/2013 LAS STUDIO PART2

BQ 1: GENERAL AND PRELIMINARY


BIL DESCRIPTION UNIT QUANTITY RATE AMOUNT

General and preliminaries


Insurance Provide 3 insurance policies as follows: A Contract Works Policy in joint names of Employer and Contractor. B SOCSO and Workmens Compensation Policy. C Public liability and Fire Policy in joint names of the Employer and Contractor. Performance Bond D Allow here for expenses in connection with providing unconditional Performance Bond by way of Bankers or Insurance Guarantee approved by the Employer and severally bound to the Employer in a sum to live (5) percent of the due observance of this contract. TOTAL

L/S L/S

3000

00

3000 L/S

00

3000

00

12000

00

BQ 2: SITE CLEARING
BIL DESCRIPTION Site clearing A To provide labour, transport, all tools and equipments and to clear all plant materials from existing planter bed and to cart away and to clean up the work area to the satisfaction and approval of the Employer or Employers Representative. To provide labour, transport, all tools and equipments and to B excavate existing soil from the planter bed and cart away and to clean up the work area to the satisfaction and approval of the Employer or Employers Representative. Work shall also include rectification works to the existing planter bed. L/S 3000 00 UNIT QUANTITY RATE AMOUNT

L/S

4000

00

TOTAL

7000

00

BQ 3: PLANT MATERIALS (INGREDIANTS)

BIL

DESCRIPTION

UNIT

QUANTITY

RATE

AMOUNT

Plant Materials To supply nursery grown plant materials listed below, transport to site and provide labour for planting as indicated in the drawing. Rates by the contractor shall include the following:

RM

RM

Soil Mixture Supply, deliver, unload and spread soil mixture, compose of one part of good approved organic matter/ compost and three parts of approved topsoil into planter bed as indicated in the drawing. The soil mixture should be well- mixed. Trees (1.0 x 1.0 x 1.0 m) Palm (1.0 x 1.0 x1.0m) Shrub (0.3 x 0.3 x 0.3m) Groundcover (0.15 x 0.15 x 0.15m) TOTAL
m3 m3 m3 m3

57 9 2245 60

35.00 35.00 15.00 8.00

1995 315 33675 480 36465

00 00 00 00 00

BQ 3: PLANT MATERIALS (INGREDIENTS)

BIL

DESCRIPTION

UNIT

QUANTITY

RATE

AMOUNT

C Crusher Run for Drainage Supply, deliver, unload and spread crusher run into planter boxes as drainage layer between 75-100mm thick (20mm dia. average size.)

RM

RM

17500

00

D Filter Membrane To provide geotextile filter membrane terram or equivalent (to Landscape Architects approval) on top of crusher run layer in all planter boxes.

40000

00

TOTAL

57500

00

BQ 3: PLANT MATERIALS (SPECIES)

BIL

DESCRIPTION This Bills of Quantities shall be read in conjunction with Specification and Preambles

UNIT

QUANTITY

RATE

AMOUNT

RM

RM

Palm 1. Veitchia merrilli 9 160.00 140 00

Trees 1. Bucida molineti 2. Citrus aurantifolia 3. Citrus hystrix 4. Eugenia oleina 5. Michelia champaca 6. Mussaenda phillipica Aurorae 7. Magnifera indica 8. Plumeria rubra 9. Tabebuai penthaphylla TOTAL 8 3 11 5 6 2 3 6 13 150.00 5.00 5.00 70.00 120.00 30.00 20.00 120.00 120.00 1200 15 55 5350 720 60 60 720 1560 9880 00 00 00 00 00 00 00 00 00 00

BQ 3: PLANT MATERIALS (SPECIES)


BIL DESCRIPTION This Bills of Quantities shall be read in conjunction with Specification and Preambles D Shrubs 1. Alpinia galangga 2. Allamanda schottii 3. Curcuma Longga 4. Coleus blumei
5. Cymbopogen citrate

UNIT QUANTITY RATE

AMOUNT

RM

RM

Nos Nos Nos Nos Nos Nos Nos Nos Nos Nos Nos Nos Nos Nos Nos

90 310 30 140 60 90 180 520 170 7 60 18 220 110 240

10.00 10.00 5.00 3.00 5.00 5.00 8.00 8.00 5.00 5.00 5.00 8.00 5.00 5.00 6.00

900 3100 150 420 300 450 1440 4160 850 35 300 144 1100 550 1440

00 00 00 00 00 00 00 00 00 00 00 00 00 00 00

6. Etlingera elatior E 7. Hymenocaulis carribea 8. Ixora japonica 9. Kaemfera galangal linn 10. Murraya koenigii 11. Murraya paniculata 12. Ochna kirkii
13. Ophipogun jaburan

variegate 14. Panadanus amarytifolius 15. Phyllanthus mrytifolius

Groundcovers 1. Axonoupus compressus TOTAL


m

60

4.00

240 15579

00 00

BQ 4: COMPUSORY MAINTENANCE
ITEM DESCRIPTION UNIT QUANTITY RATE AMOUNT

Compulsory Maintenance. A To provide all labor, tools, equipment, transport, etc and carry out maintenance in all planted areas for 12 months. L/S
2500 00

Maintenance shall include but not necessarily be limited to watering, weeding, pruning, fertilizing, spraying and clearing of unnecessary growth.etc and any other horticultural management as directed but the S.O or S.Os representative as necessary for the proper growth of plants.

L/S

2500

00

C From the time planting until the end of maintenance period, the landscape constructor is required to replace dead, dying or missing plants, or those severely damaged by pests or diseases to the original sizes of the plants due to the replaced and true to types at the contractors own coasts as and when directed by the S.O or TOTAL

L/S

4000

00

9000

00

BQ 5: HARD LANDSCAPE ITEMS


BIL DESCRIPTION UNIT
QUANTITY

RATE

AMOUNT

This Bills of Quantities shall be read in conjunction with Specification and Preambles Hard landscape items To provide all labour, tools, equipment, transport, etc. and carry out maintenance in all process in finish the work and built the gazebo, pergola, stage and pavement around the side.

RM

RM

I. Pergola (14.0 m x 6.0m) II. Gazebo ( 5.0m x 5.0m) III. Pedestrian walkway (1.5m width) IV. Fish Pond (2.0 m x 4.0m) V. Planter Box VI. Wooden Table and Seating VII. Rabbits Hut (4.0m x 2.0m) VIII. Birds Cage (3.0m x 2.0m) TOTAL

L/S

3000.00

3000

00

Nos L/S L/S L/S Nos Nos Nos

3
165m

1500.00 50.00 1000.00 3500.00

4500 8250 1000 3500 1600 900 500

00 00 00 00 00 00 00

2 1 1

800.00 900.00 500.00

23250

00

BQ 6: SUMMARY -TOTAL PROJECT COST


The following are the prices in Ringgit Malaysia of the items making up the Total Contract Prince. The price of each item includes the use of all tools and equipment, supervision, overheads and profits, taxes, transportation and all other incidental costs. The Total Contract Price is for completely supply, erection, handing over ITEM BQ 1 BQ 2 BQ 3 BQ 3 BQ 4 BQ 5 DESCRIPTION General and preliminaries Site clearing Plant materials (Ingredients) Plant materials (Species) Compulsory maintenance Hard landscape items TOTAL SUM AMOUNT 12000 7000 36465 25459 9000 23250 113174 00 00 00 00 00 00 00

-------------------------(Signature of Witness) Name : NRIC No: Address: Date:

------------------------(Signature of Tenderer) Name : NRIC No: Address: Date: