Variances
Schedule variance, SV = EV PV Cost variance, CV = EV AC Performance Index Schedule Performance Index, SPI = EV/PV Cost Performance Index, CPI = EV/AC
Variances
SV = EV PV CV = EV AC
Performance Index
SPI = EV/PV CPI = EV/AC
EAC = AC + Bottom-up ETC EAC forecast for ETC work performed at the budgeted rate
EAC = AC + (BAC EV)
EAC forecast for ETC work considering both SPI and CPI factors
EAC = AC + [(BAC AC) /(CPI * SPI)]
EVM Exercise
You have a project to build a new fence. The fence is four sided, 10 meter long each side. Each side to take 1 week, and budgeted for Rs 1000 per side. At the end of Day-3, 25 meters of fencing is done and spent Rs 2800. Calculate below EVM measures
PV EV AC
BAC CV
ETC VAC